ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / SADA SUNDARAM HEIGHTS WING B

Registered No litigation declared Residential / Group Housing project

SADA SUNDARAM HEIGHTS WING B

By B CHAVAN ENTERPRISES

RG-MH-79006 · RERA P52100052568 · Last updated on MahaRERA portal: 1 Apr 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jul 2027Possession promisedno revision filed
3 of 11Construction stages donefurthest along: Stilt Floor, 85%
3 of 9Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 69 documents Report an error

SADA SUNDARAM HEIGHTS WING B is a Residential / Group Housing project by B CHAVAN ENTERPRISES in Pune, Maharashtra, registered with MahaRERA as P52100052568 on 11 Sep 2023. Possession is promised by 31 Jul 2027. 6 of the 9 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.

At a glance

Project

  • NameSADA SUNDARAM HEIGHTS WING B
  • TypeResidential / Group Housing
  • Location
    • NARHE AMBEGAON ROAD
    • NARHE
    • Wadgaon Bk
    • Haveli
    • Pune
    • 411041
  • Pincode411041
  • RERA no.P52100052568
  • ReraGenie IDRG-MH-79006

Builder

  • NameB CHAVAN ENTERPRISES
  • Entity typePartnership
  • PartnersACHALKUMAR NARAYANRAO CHAVAN, KALPAK CHANDRAKANT PATIL, PRAVIN VITTHAL CHORGHADE

Key dates

this monthRegisteredSep 2023PromisedJul 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on11 Sep 2023
  • Promised completion31 Jul 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed69 files

Current status

67%6 of 9 units booked
95.7%Work done, per cost certificate

Figures as on 1 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SADA SUNDARAM HEIGHTS WING BNA66909

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 1 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 85%.

SADA SUNDARAM HEIGHTS WING B: 46% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor85%
Slabs of Super Structure64%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises55%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 1 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed65

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots65
Closed/Covered32
Open Space33

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,850 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on24 May 2025
LandownerVillageDistrict
ACHALKUMAR NARAYANRAO CHAVANWadgaon BkPune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI3553.37
Proposed, not sanctioned1,910 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchWARJE PUNE
Estimated costRs 4.73 cr
Cost incurredRs 4.52 cr
Work done95.69%
BuildingWingEstimatedIncurred
SADA SUNDARAM HEIGHTS WING BNARs 4.21 crRs 3.90 cr
-NARs 51.41 lakhRs 62.01 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTRUSHALI KHOMANE
EngineerRushikesh Dhebe
EngineerArati Andhare
Chartered AccountantA M KALE & ASSOCIATES
PartnerRole in project
B CHAVAN ENTERPRISES-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Aug 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Jun 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Jun 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Jun 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Jul 2027

Documents filed69

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM NO 1.pdf1 Apr 2026
Withdrawal Update Form 1File: FORM NO 1.pdf1 Apr 2026
Withdrawal Update Form 1File: FORM NO 1 311225.pdf1 Apr 2026
Withdrawal Update Form 2File: Form 2 300925.pdf1 Apr 2026
Withdrawal Update Form 2File: Form 2 300925.pdf1 Apr 2026
Withdrawal Update Form 2File: Form 2 311225.pdf1 Apr 2026
Withdrawal Update Form 3File: CA Form 3.pdf1 Apr 2026
Withdrawal Update Form 3File: CA Form 3.pdf1 Apr 2026
Withdrawal Update Form 3File: CA Form 3.pdf1 Apr 2026
Withdrawal Update Form 1File: FORM NO1 Architect Certificate.pdf14 Oct 2025
Withdrawal Update Form 2File: FORM 2 ENGINEERS CERTIFICATE FOR RERA 15-4-24 QTR RET-2_11zon.pdf14 Oct 2025
Withdrawal Update Form 3File: FORM 3 B CHAVAN ENTERPRISES 10-4-2024 QTR RET-2 (1)_11zon.pdf14 Oct 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf30 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1 311224.pdf27 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3 311224.pdf27 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2 311224.pdf27 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERT 30092024.pdf21 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERT 30092024.pdf21 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: ENGINEERS CERT FORM 2A 31032024.pdf20 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Form-3 30092024.pdf20 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM NO 1 30092024.pdf20 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: CA CERTIFICATE FORM 5 31032024.pdf20 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 30062024.pdf20 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM NO 1 30092024.pdf20 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 30062024.pdf20 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 30062024.pdf20 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 30062024.pdf20 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM NO 1 30092024.pdf20 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Form-3 30092024.pdf20 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 30062024.pdf20 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM NO 1 30092024.pdf20 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 30062024.pdf20 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: ENGINEERS CERT FORM 2A 31032024.pdf20 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: CA CERTIFICATE FORM 5 31032024.pdf20 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM NO1 Architect Certificate.pdf16 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEERS CERTIFICATE FOR RERA 15-4-24 QTR RET-2_11zon.pdf16 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 B CHAVAN ENTERPRISES 10-4-2024 QTR RET-2 (1)_11zon.pdf16 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf5 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf5 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form No 1.pdf5 Feb 2024
Copy of the legal title reportFile: BCHAVAN-TITLE REPORT latest.pdf29 Aug 2023
Copy of the legal title reportFile: Declaration.pdf29 Aug 2023
Copy of the legal title reportFile: Annexure of legal title report.pdf20 Jul 2023
Proforma of Agreement for saleFile: Agreement.pdf20 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf1 Jul 2023
Building plan approvalFile: plan 03-05.pdf19 Jun 2023
Building plan approvalFile: plan 04-05.pdf19 Jun 2023
Building plan approvalFile: plan 05-05.pdf19 Jun 2023
Building plan approvalFile: plan 02-05.pdf19 Jun 2023
Layout approvalFile: plan 01-05.pdf19 Jun 2023
PAN CardFile: B CHAVAN ENTERPRISES PAN CARD0001.pdf19 Jun 2023
Details of encumbrances concerned to FinanceFile: Encumbarance Declaration.pdf19 Jun 2023
Details of encumbrances concerned to LegalFile: Encumbarance Declaration.pdf19 Jun 2023
Copy of Layout Approval (in case of layout)File: plan 01-05.pdf19 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: plan 02-05.pdf19 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: plan 03-05.pdf19 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: plan 04-05.pdf19 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: plan 05-05.pdf19 Jun 2023
Commencement Certificates / NA Order for plotted developmentFile: cc.pdf19 Jun 2023
Declaration about Commencement CertificateFile: Commencement Certificate Declaration.pdf19 Jun 2023
Declaration in FORM BFile: Form B Promoter.pdf19 Jun 2023
CERSAI detailsFile: CERSAI REPORT.pdf19 Jun 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Declaration Chavan.pdf19 Jun 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Declaration Kalpak P.pdf19 Jun 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Declaration Pravin C.pdf19 Jun 2023
Proforma of Allotment letterFile: allotment letter.pdf19 Jun 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Account Declaration.pdf19 Jun 2023
Deviation Report with respect to Allotment letterFile: Allotment Letter Declaration.pdf19 Jun 2023
Deviation Report with respect to model copy of AgreementFile: Agreement Letter Declaration.pdf19 Jun 2023

How this compares with Pune

67%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SADA SUNDARAM HEIGHTS WING B on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NARHE13,700+ in Pune

Builder: B CHAVAN ENTERPRISES

B CHAVAN ENTERPRISES has 1 registration on MahaRERA, including SADA SUNDARAM HEIGHTS WING B. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if SADA SUNDARAM HEIGHTS WING B is delayed beyond 31 Jul 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SADA SUNDARAM HEIGHTS WING B?

The registered promoter entity is B CHAVAN ENTERPRISES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SADA SUNDARAM HEIGHTS WING B?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SADA SUNDARAM HEIGHTS WING B?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SADA SUNDARAM HEIGHTS WING B?

The professionals named in the filing: Architect: TRUSHALI KHOMANE; Engineer: Rushikesh Dhebe; Engineer: Arati Andhare; Chartered Accountant: A M KALE & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SADA SUNDARAM HEIGHTS WING B?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SADA SUNDARAM HEIGHTS WING B. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SADA SUNDARAM HEIGHTS WING B to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.