Red flags
- Registration lapsed
- Possession 13 months past the filed date
- Litigation declared, 2 cases
- 6 complaints at MahaRERA
- Completion date moved by 33 months
- 3 extensions taken
- Rs 10.00 crore secured on the land, in favour of PRABODH ARTHASANCHAY PVT LTD
- The declared charge does not appear in the CERSAI report on the filing
Clear
- Separate project account declared
- Allotment letter follows the model form
8 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Saarrthi Skybay II is a Residential / Group Housing project by Siddharth Properties in Pune, Maharashtra, registered with MahaRERA as P52100016176 on 20 Apr 2018. Possession was promised by 30 Sep 2025 and is now 13 months past that date. The completion date has moved by 33 months from the original filing. 289 of the 317 units on this registration are recorded sold or booked, and 20 of 22 construction stages are filed complete. 6 complaints are on record with the regulator.
At a glance
Project
- NameSaarrthi Skybay II
- TypeResidential / Group Housing
- Location
- Mahalunge
- Pune (M Corp.)
- Pune City
- Pune
- 411045
- Pincode411045
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100016176
- ReraGenie IDRG-MH-33895
Builder
- NameSiddharth Properties
- Entity typePartnership
- GSTIN27AAZFS3607C1ZY
- GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- PartnersAbhijeet Vasant Shende, Nilesh Vasant Shende, Swapneel Shashikant Shende, Yogesh Ramesh Shende
- Other registrations8 more →
- Completed4 of 9
- No longer live2 lapsed, de-registered or revoked
- Declared earlier projects7 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on20 Apr 2018
- Promised completion30 Sep 2025
- Revised completionRevised to 30 Sep 2025 (originally 30 Dec 2022)
- Buildings2 building records
- Documents filed143 files
Current status
Figures as on 26 Dec 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| C | NA | 23 | 18 | 141 | 0 | 141 |
| D | NA | 24 | 21 | 138 | 38 | 176 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 26 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
20 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 0%.
C91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
D91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 26 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 90% |
| Street Lighting | Yes | 90% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed2
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| C | 1 | 1 |
| D | 1 | 1 |
Land and ownership2
MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
| Landowner | Village | District |
|---|---|---|
| Ramdas Baban Kolekar | Pune (M Corp.) | Pune |
| Tuka Vithu Kolekar | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| D | NA | Rs 24.32 cr | Rs 24.08 cr |
| C | NA | Rs 22.20 cr | Rs 22.13 cr |
| - | NA | Rs 13.26 cr | Rs 12.87 cr |
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Abhikalpan Architects & planners |
| Architect | Ideal Design Architects |
| Engineer | G.A Bhilare Consultants Pvt Ltd. |
| Engineer | Raviraj Karande |
| Chartered Accountant | K M Deo |
| Chartered Accountant | CA Saransh Dey |
| Chartered Accountant | H N V & Co |
| Partner | Role in project |
|---|---|
| Siddharth Properties | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to heavy rainfall waterlogged on road resulting into stoppage of supply of materials, process of external plastering was also suspended. Further due to situations beyond control of the Promoter it is not possible for us to deliver possession on declared date.
Reason as filed by the promoterThe Construction of the project is almost completed only the finishing work of the building is yet to be completed. We require Extension for only 9 months to complete the Finishing work of the building.
Reason as filed by the promoterDue to the disruption in the supply chain caused by the pandemic, the completion of the project has been delayed. Only the finishing work remains pending, so we request an extension for the completion of the project.
Litigation declared2
| Case | Court | Status |
|---|---|---|
| RCS/1757/2022 | Civil Judge Junior Division Pune | Closed |
| RCS/1757/2022 | CJJD | Closed |
Complaints filed with MahaRERA6
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000064905 | Ojaswini Sapatnekar | Saarthi Skybay II | 15/11/2022 |
| CC005000000177808 | Ojaswini Sapatnekar | Siddharth Properties | 15/11/2022 |
| CC005000000370988 | Prathamesh Gajanan Sonawane | M/s Siddharth Properties | 01/06/2024 |
| CC005000000370996 | Sourjya Brata Chatterjee | M/s Siddharth Properties | 01/06/2024 |
| CC12503618 | Charushila Satish Patil | Siddharth Properties | 11/10/2025 |
| CC12601337 | Charushila Satish Patil | Siddharth Properties | 11/03/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 24 Sep 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 24 Sep 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 24 Sep 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 24 Sep 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed143
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 143 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Sept 25 Skybay II Architect Cert.pdf | 26 Dec 2025 |
| Withdrawal Update Form 2File: Engineers Certificate - 30-09-2025 - Skybay II.pdf | 26 Dec 2025 |
| Withdrawal Update Form 3File: FORM 3.pdf | 26 Dec 2025 |
| Form 1File: FORM 1 ARCHITECT CERTIFICATE.pdf | 4 Oct 2025 |
| Form 2File: FORM 2 ENGINEER CERTIFICATE.pdf | 4 Oct 2025 |
| Form 3File: FORM 3 CA CERTIFICATE.pdf | 4 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY DATED 30-06-2025.pdf | 4 Oct 2025 |
| Form 1File: Mar 25 Skybay II Architect Cert.pdf | 30 May 2025 |
| Form 2File: Mar 25 2.pdf | 30 May 2025 |
| Form 3File: C A Certificate - Form 3 - Saarrthi Skybay ll.pdf | 30 May 2025 |
| Disclosure of Sold and Booked InventoryFile: Skybay ll.pdf | 30 May 2025 |
| Disclosure of sold/ booked inventoryFile: Skybay ll.pdf | 29 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Mar 25 Skybay II Architect Cert.pdf | 19 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Mar 25 2.pdf | 19 Apr 2025 |
| Certificates of CA (Form 3)File: Form 3 Saarrthi Skybay II latest final uploaded.pdf | 5 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: From 2A - Revised format_Skybay II_2020-21.pdf | 5 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: From 2A - Revised format_Skybay II_2022-23.pdf | 5 Apr 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - SkybayII FY 2022-23.pdf | 5 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: From 2A - Revised format_Skybay II_2023-24.pdf | 5 Apr 2025 |
| Certificates of CA (Form 3)File: Form 03-Saarrthi Skybay II - Final uploaded.pdf | 25 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Final Sold Unsold - Saarrthi Skybay II.pdf | 25 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: skybay II form 2.pdf | 25 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Dec 24 Skybay II Architect Cert.pdf | 21 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Skybay II Dec 24 Sold Unsold Inventory Certificate.pdf | 21 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Skybay II.pdf | 20 Jan 2025 |
| Certificates of CA (Form 3)File: FORM 3 SKYBAY II.pdf | 28 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FROM 2 SKYBAY II.pdf | 25 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sept 24 Skybay II Architect Cert_page-0001.pdf | 19 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: SKYBAY II SOLD UNSOLD.pdf | 19 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: SKYBAY II SOLD UNSOLD.pdf | 19 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: March'2023.pdf | 20 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: Sep'2023.pdf | 20 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: Dec'2023.pdf | 20 Aug 2024 |
| Declaration in FORM BFile: Form B - Saarrthi Skybay II - Final Upload.pdf | 13 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: Saarrthi Skybay II - Siddharth Properties.pdf | 8 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: Jun 24 SKYBAY II_Sold Unsold Inventory Certificate.pdf | 3 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Skybay II Form 1 - June 24 - Architect Cert.pdf | 29 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Skybay II Form 2 - June 24 -Eng.pdf | 29 Jul 2024 |
| Certificates of CA (Form 3)File: Skybay II Form 3 - June 24 - CA.pdf | 29 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Mar 24 SKYBAY II_Sold Unsold Inventory Certificate.pdf | 5 May 2024 |
| Form 2AFile: Mar 24 CD Skybay_ii.pdf | 4 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Mar 24 Skybay II Architect Cert.pdf | 29 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Mar 24 CDSkybay II_Registration_E cert.pdf | 29 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Mar 24 CDSkybay II_Registration_E cert.pdf | 29 Apr 2024 |
| Certificates of CA (Form 3)File: C A Cretificate - Skybay II.pdf | 29 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Dec 23 Skybay II Architect Cert_240111_214856.pdf | 12 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 (2)_compressed.pdf | 12 Jan 2024 |
| Certificates of CA (Form 3)File: Form 03 - Saarrthi Skybay II Dec 2023.pdf | 12 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Skybay2_Sept23_compressed.pdf | 19 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Skybay2_Sept23_compressed.pdf | 19 Oct 2023 |
| Certificates of CA (Form 3)File: Form 3 Skybay2_Sept23_compressed.pdf | 19 Oct 2023 |
| Details of encumbrances concerned to FinanceFile: Index 2.pdf | 17 Aug 2023 |
| Details of encumbrancesFile: Encumbarance Declaration.pdf | 17 Aug 2023 |
| Details of encumbrances concerned to LegalFile: Index 2.pdf | 17 Aug 2023 |
| Certificates of CA (Form 3)File: Saarrthl Skybay II_compressed_compressed.pdf | 20 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1_Jun 23_Skybay 2.pdf | 19 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2_Skybay2_compressed.pdf | 19 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_March23_SKYBAY II.pdf | 19 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2_M23_Skybay 2.pdf | 18 Apr 2023 |
| Certificates of CA (Form 3)File: Form 03 Saarrthi Skybay 2.pdf | 18 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form2A_M23_Skybay2.pdf | 17 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Dec 22_Skybay ll.pdf | 9 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form No2 Skybay2_Dec22_c.pdf | 9 Feb 2023 |
| Certificates of CA (Form 3)File: Form No3 Skybay2_Dec22_compressed.pdf | 7 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Mar 22 SkybayII_Registration_Q cert.pdf | 10 Nov 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form5_SkybayII_March22_c.pdf | 10 Nov 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1_SkybayII_Sept22.pdf | 20 Oct 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2_SkybayII_Sept22_c.pdf | 20 Oct 2022 |
| Certificates of CA (Form 3)File: Form3_SkybayII_Sept22_c.pdf | 20 Oct 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1_Jun 22_Skybay II.pdf | 20 Jul 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate saarrthi skybay ll_compressed.pdf | 20 Jul 2022 |
| Certificates of CA (Form 3)File: Form no 03 in Saarrthi SKYBAY 2_compressed.pdf | 20 Jul 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form5_March21_Skybay II.pdf | 19 Jul 2022 |
| Certificates of CA (Form 3)File: Form No3_Skybay II_March22_c.pdf | 18 Jul 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Saarrthi Skybay II.pdf | 28 Apr 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Mar 22 CDSkybay_Registration_E cert.pdf | 28 Apr 2022 |
| Form 2AFile: Mar CDSkybay_Registration_Q cert.pdf | 28 Apr 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Dec 21 Skybay II Engg Certificate.pdf | 31 Jan 2022 |
| Certificates of CA (Form 3)File: SKYBAY -II.pdf | 1 Nov 2021 |
| Disclosure of sold/ booked inventoryFile: SKYBAY-II_Discloser of Sold Unsold.pdf | 12 Oct 2021 |
Promoter's earlier projects5
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Souvenir | S.NO 15- 6- 1 MAU MAHALUNGE TAL MULSHI PUNE | 246 | Completed | May 2016 | Jul 2015 |
| Shimmer and Shine | S.NO 19 HINGNE KHURD | 147 | Completed | Mar 2016 | Late, Apr 2016 |
| Sovereign | MARUNJI TAL MULSHI PUNE | 259 | Completed | Dec 2015 | Mar 2015 |
| Signor | S.NO 273 HINJEWADI TAL MULSHI PUNE. | 129 | Completed | Sep 2013 | May 2013 |
| Satin Hills | S no 37 Bavdhan BK Pune 411021 | 101 | Completed | Dec 2010 | Late, Jan 2011 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 8 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 8 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 143 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Saarrthi Skybay II on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Mahalunge13,700+ in Pune
Filed coordinates, straight-line distance. 200 registered projects within 2 km.
EARTH 1 BY VTP LUXE PHASE 1
MAHALUNGE REAL ESTATE DEVELOPERS PVT. LTD.
Godrej Meadows
Mahalunge Township Developers Private Limi
Godrej Green Vistas
Mahalunge Township Developers Private Limi
Godrej Hill Retreat
Mahalunge Township Developers Private Limi
Godrej Green Cove
Mahalunge Township Developers Private Limi
NYATI EMERALD I
NYATI BUILDERS PRIVATE LIMITED
Builder: Siddharth Properties
Siddharth Properties has 9 registrations on MahaRERA, including Saarrthi Skybay and Success Square. Its filings disclose 7 earlier MahaRERA projects: declares 4 of 7 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that Saarrthi Skybay II shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Saarrthi Skybay II is delayed beyond 30 Sep 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Saarrthi Skybay II?
The registered promoter entity is Siddharth Properties, a partnership as per the filing. Its GSTIN 27AAZFS3607C1ZY can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Saarrthi Skybay II?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Saarrthi Skybay II?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Saarrthi Skybay II?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Saarrthi Skybay II?
The professionals named in the filing: Architect: Abhikalpan Architects & planners; Architect: Ideal Design Architects; Engineer: G.A Bhilare Consultants Pvt Ltd.; Engineer: Raviraj Karande; Chartered Accountant: K M Deo; Chartered Accountant: CA Saransh Dey. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Saarrthi Skybay II?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback