Home / Browse projects / Pune, Maharashtra / Saarrthi Savvy Homes II

Registration lapsed No litigation declared Residential / Group Housing project

Saarrthi Savvy Homes II

By Siddharth Properties

RG-MH-79348 · RERA P52100016105 · Last updated on MahaRERA portal: 10 Jul 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 7 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 39 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2026Possession promised7 months past this date
18 of 22Construction stages doneacross 2 buildings; furthest along: Basement (if any), 0%
47 of 196Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 169 documents Report an error

Saarrthi Savvy Homes II is a Residential / Group Housing project by Siddharth Properties in Pune, Maharashtra, registered with MahaRERA as P52100016105 on 17 Apr 2018. Possession was promised by 31 Mar 2026 and is now 7 months past that date. The completion date has moved by 39 months from the original filing. 149 of the 196 units on this registration are recorded sold or booked, and 18 of 22 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSaarrthi Savvy Homes II
  • TypeResidential / Group Housing
  • Location
    • Hinjewadi
    • Hinjavadi (CT)
    • Mulshi
    • Pune
    • 411057
  • Pincode411057
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100016105
  • ReraGenie IDRG-MH-79348

Builder

  • NameSiddharth Properties
  • Entity typeOthers
  • PartnersNilesh Vasant Shende, Swapneel Shashikant Shende, Abhijeet Vasant Shende
  • Other registrations8 more →
  • Completed4 of 9
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects7 →

Key dates

7 months past promisethis monthRegisteredApr 2018First promiseDec 2022Revised toMar 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on17 Apr 2018
  • Promised completion31 Mar 2026
  • Revised completionRevised to 31 Mar 2026 (originally 30 Dec 2022)
  • Buildings2 building records
  • Documents filed169 files

Current status

76%149 of 196 units booked
101.2%Work done, per cost certificate

Figures as on 10 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
CNA16151120112
DNA161584084

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 10 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 0%.

C82%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
D82%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 10 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed155

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots155
Closed/Covered2
Open Space153
BuildingClosed/CoveredOpen SpaceTotal
C19192
D16263

Land and ownership3

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,529 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on13 Oct 2025
LandownerVillageDistrict
Raosaheb Nathu SakharePune (M Corp.)Pune
Bhagwan Nathu SakharePune (M Corp.)Pune
Bhahgwan Nathu SakhareHinjavadi (CT)Pune

Approvals and building plan

Sanctioning authorityPune Metropolitan Regional Devlopment Authority Pune
Permissible FSI11662.69
Proposed, not sanctioned11,663 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShivajinagar
Estimated costRs 41.00 cr
Cost incurredRs 41.50 cr
Work done101.21%
BuildingWingEstimatedIncurred
CNARs 20.00 crRs 20.00 cr
DNARs 16.00 crRs 16.10 cr
-NARs 5.00 crRs 5.40 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAbhikalpan Architects & planners
ArchitectIdeal Design Architects
EngineerHansal Parikh & Associates
EngineerRaviraj karande
Chartered AccountantNITESH M SHAH & CO
Chartered AccountantH N V & Co
Chartered AccountantCA Saransh Dey
PartnerRole in project
Siddharth Properties-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100018409Dec 2022 → Dec 2024

Reason as filed by the promoterThe Construction of the project is almost completed only the finishing work of the project is yet to be completed. We only require extension for 12 months.

EXT52100012811Dec 2022 → Dec 2023

Reason as filed by the promoterDue to heavy rainfall waterlogged on road resulting into stoppage of supply of materials, process of external plastering was also suspended. Further due to situations beyond control of the Promoter it is not possible for us to deliver possession on declared date.

EXT52100027951Dec 2022 → Mar 2026

Reason as filed by the promoterThe project work is completed nearly around 96% , finishing work is in process and we are in process of obtaining occupancy certificate. Therefore, we request to grant extension till 31/03/2026.

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC005000000228422SAURABH RAKESH JAINAbhijeet Vasant Shende02/03/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 13 Apr 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Apr 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Apr 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Apr 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed169

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 169 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Dec 25_Savvy II Architect Cert.pdf10 Jul 2026
Withdrawal Update Form 1File: Dec 25_Savvy II Architect Cert.pdf10 Jul 2026
Withdrawal Update Form 1File: FORM 1.pdf10 Jul 2026
Withdrawal Update Form 2File: Dec 25 Savvy II registration_E cert.pdf10 Jul 2026
Withdrawal Update Form 2File: Dec 25 Savvy II registration_E cert.pdf10 Jul 2026
Withdrawal Update Form 2File: FORM 2.pdf10 Jul 2026
Withdrawal Update Form 3File: FORM 3 FINAL.pdf10 Jul 2026
Withdrawal Update Form 3File: FORM 3 FINAL.pdf10 Jul 2026
Withdrawal Update Form 3File: FORM 3.pdf10 Jul 2026
Withdrawal Update Form 1File: Sept 25 Savvy II Architect Cert.pdf8 Dec 2025
Withdrawal Update Form 2File: Engineers Certificate - 30-09-2025 - Savvy II.pdf8 Dec 2025
Withdrawal Update Form 3File: Form 3 - Savvy Homes II - Sept 2025.pdf8 Dec 2025
Form 5 (FY 2024-2025)File: Form 5 - FY 24-25 - Savvy2.pdf29 Nov 2025
Form 1File: FORM 1 ARCHITECT CERTIFICATE.pdf4 Oct 2025
Form 2File: FORM 2 ENGINEER CERTIFICATE.pdf4 Oct 2025
Form 3File: FORM 3 CA CERTIFICATE.pdf4 Oct 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY DATED 30-06-2025.pdf4 Oct 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Mar 25 Savvy II Architect Cert.pdf3 May 2025
Certificates of CA (Form 3)File: C A Certificate - Form 3 - 31-03-2021 done.pdf3 May 2025
Certificates of CA (Form 3)File: C A Certificate - Form 3 - 31-03-2022.pdf3 May 2025
Certificates of CA (Form 3)File: C A Certificate - Form 3 - 30-09-2022done .pdf3 May 2025
Certificates of CA (Form 3)File: C A Certificate - Form 3 - 31-03-2023 done .pdf3 May 2025
Certificates of CA (Form 3)File: C A Certificate - Form 3 - 30-06-2023 done.pdf3 May 2025
Certificates of CA (Form 3)File: Form III - Savvy Homes II - March 2025.pdf3 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 30-12-2023 done.pdf3 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Mar 25 Savvy II registration_E cert.pdf3 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 31-12-2024done.pdf3 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 30-09-2024 done.pdf3 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 30-06-2024done .pdf3 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 31-03-2024.pdf3 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 30-09-2023done.pdf3 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 31-03-2023 done.pdf3 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 31-12-2022.pdf3 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 30-09-2022.pdf3 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 30-06-2022done.pdf3 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 31-03-2022.pdf3 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 31-03-2021.pdf3 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 31-12-2020.pdf3 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 30-06-2023done.pdf3 May 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD 31-03-2025 SAVVY HOMES II.pdf3 May 2025
Disclosure of sold/ booked inventoryFile: Discolsure Of Sold - Saarrthi Savvy Homes ll - 30-09-2023.pdf3 May 2025
Disclosure of sold/ booked inventoryFile: Discolsure Of Sold - Saarrthi Savvy Homes ll - 30-06-2023.pdf3 May 2025
Disclosure of sold/ booked inventoryFile: Discolsure Of Sold - Saarrthi Savvy Homes ll - 31-03-2023.pdf3 May 2025
Disclosure of sold/ booked inventoryFile: Discolsure Of Sold - Saarrthi Savvy Homes ll - 30-09-2022 done.pdf3 May 2025
Disclosure of sold/ booked inventoryFile: Discolsure Of Sold - Saarrthi Savvy Homes ll - 30-06-2022 done .pdf3 May 2025
Disclosure of sold/ booked inventoryFile: Discolsure Of Sold - Saarrthi Savvy Homes ll - 31-12-2021.pdf3 May 2025
Disclosure of sold/ booked inventoryFile: Discolsure Of Sold - Saarrthi Savvy Homes ll - 31-03-2021.pdf3 May 2025
Disclosure of sold/ booked inventoryFile: Discolsure Of Sold - Saarrthi Savvy Homes ll - 30-03-2020.pdf3 May 2025
Disclosure of sold/ booked inventoryFile: Discolsure Of Sold - Saarrthi Savvy Homes ll - 31-04-2019.pdf3 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architecture Certificate - 31-12-2020 - Saarrthi Savvy Homes ll.pdf2 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architecture Certificate - 27-09-2021 - Saarrthi Savvy Homes ll.pdf2 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architecture Certificate - 31-03-2022 - Saarrthi Savvy Homes ll.pdf2 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architecture Certificate - 30-06-2022 - Saarrthi Savvy Homes ll.pdf2 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architecture Certificate - 30-09-2022 - Saarrthi Savvy Homes ll.pdf2 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architecture Certificate - 30-12-2022 - Saarrthi Savvy Homes ll.pdf2 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architecture Certificate - 31-03-2023 - Saarrthi Savvy Homes ll.pdf2 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architecture Certificate - 30-06-2023 - Saarrthi Savvy Homes ll.pdf2 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architecture Certificate - 30-09-2023 - Saarrthi Savvy Homes ll.pdf2 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Mar 25 Savvy II Architect Cert.pdf19 Apr 2025
Form 2AFile: From 2A - Revised format_Savvy II_2018-19.pdf9 Apr 2025
Form 2AFile: From 2A - Revised format_Savvy II_2019-20.pdf9 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: From 2A - Revised format_Savvy II_2020-21.pdf9 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: From 2A - Revised format_Savvy II_2021-22.pdf9 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: From 2A - Revised format_Savvy II_2022-23.pdf9 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: From 2A - Revised format_Savvy II_2023-24.pdf9 Apr 2025
Declaration in FORM BFile: FORM B - PROMOTER DECLARATION.pdf21 Mar 2025
Other - TechnicalFile: Pert Chart.pdf21 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A saarrthi savvy homes ii.pdf21 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Dec 24 Savvy II registration_E cert.pdf29 Jan 2025
Certificates of CA (Form 3)File: Form 03-Saarrthi Savvy Homes 2 (2).pdf24 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Dec 24 Savvy Homes II Architect Cert.pdf21 Jan 2025
Disclosure of sold/ booked inventoryFile: Savvy Dec 24 Sold Unsold Inventory Certificate.pdf21 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: C A Certificate - Saarrthi Savvy Homes ll.pdf21 Jan 2025
Certificates of CA (Form 3)File: Form 3 Saarrthi Savvy Homes II.pdf29 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Savvy II.pdf29 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 SAVY HOMES II.pdf25 Oct 2024
Disclosure of sold/ booked inventoryFile: Savvy Homes II Sold Unsold.pdf25 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: June 24 Savvy II Architect Cert.pdf31 Jul 2024
Disclosure of sold/ booked inventoryFile: Jun 24 Savvy 2_Sold Unsold Inventory Certificate.pdf31 Jul 2024
Certificates of CA (Form 3)File: Savvy Homes-II.pdf31 Jul 2024

Promoter's earlier projects5

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise2 delivered late
ProjectLocationFlatsStatusPromisedDelivered
SouvenirS.NO 15- 6- 1 MAU MAHALUNGE TAL MULSHI PUNE246CompletedMay 2016Jul 2015
Shimmer and ShineS NO 19 HINGNE KHURD147CompletedMar 2016Late, Apr 2016
SovereignMARUNJI TAL MULSHI PUNE259CompletedDec 2015Mar 2015
SignorS NO 273 HINJEWADI TAL MULSHI PUNE129CompletedSep 2013May 2013
Satin HillsS NO 37 BAVDHAN BK PUNE 411021101CompletedDec 2010Late, Jan 2011

How this compares with Pune

76%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 39 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Saarrthi Savvy Homes II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Hinjewadi13,700+ in Pune

2 kmSaarrthi Savvy Homes IICompleted 85Lapsed / revoked 32Other 62Dot size: filed unitsN

Filed coordinates, straight-line distance. 179 registered projects within 2 km.

Builder: Siddharth Properties

Siddharth Properties has 9 registrations on MahaRERA, including Saarrthi Skybay and Success Square. Its filings disclose 7 earlier MahaRERA projects: declares 4 of 7 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Saarrthi Savvy Homes II shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Saarrthi Savvy Homes II is delayed beyond 31 Mar 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Saarrthi Savvy Homes II?

The registered promoter entity is Siddharth Properties, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Saarrthi Savvy Homes II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Saarrthi Savvy Homes II?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Saarrthi Savvy Homes II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Saarrthi Savvy Homes II?

The professionals named in the filing: Architect: Abhikalpan Architects & planners; Architect: Ideal Design Architects; Engineer: Hansal Parikh & Associates; Engineer: Raviraj karande; Chartered Accountant: NITESH M SHAH & CO; Chartered Accountant: H N V & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Saarrthi Savvy Homes II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Saarrthi Savvy Homes II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Saarrthi Savvy Homes II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.