Home / Browse projects / Pune, Maharashtra / Saarrthi Savvy Homes II
Saarrthi Savvy Homes II
RG-MH-79348 · RERA P52100016105 · Last updated on MahaRERA portal: 10 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 7 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 39 months
- 3 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Saarrthi Savvy Homes II is a Residential / Group Housing project by Siddharth Properties in Pune, Maharashtra, registered with MahaRERA as P52100016105 on 17 Apr 2018. Possession was promised by 31 Mar 2026 and is now 7 months past that date. The completion date has moved by 39 months from the original filing. 149 of the 196 units on this registration are recorded sold or booked, and 18 of 22 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameSaarrthi Savvy Homes II
- TypeResidential / Group Housing
- Location
- Hinjewadi
- Hinjavadi (CT)
- Mulshi
- Pune
- 411057
- Pincode411057
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100016105
- ReraGenie IDRG-MH-79348
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on17 Apr 2018
- Promised completion31 Mar 2026
- Revised completionRevised to 31 Mar 2026 (originally 30 Dec 2022)
- Buildings2 building records
- Documents filed169 files
Current status
Figures as on 10 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| C | NA | 16 | 15 | 112 | 0 | 112 |
| D | NA | 16 | 15 | 84 | 0 | 84 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 10 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
18 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 0%.
C82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
D82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 10 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed155
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| C | 1 | 91 | 92 |
| D | 1 | 62 | 63 |
Land and ownership3
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Raosaheb Nathu Sakhare | Pune (M Corp.) | Pune |
| Bhagwan Nathu Sakhare | Pune (M Corp.) | Pune |
| Bhahgwan Nathu Sakhare | Hinjavadi (CT) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| C | NA | Rs 20.00 cr | Rs 20.00 cr |
| D | NA | Rs 16.00 cr | Rs 16.10 cr |
| - | NA | Rs 5.00 cr | Rs 5.40 cr |
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Abhikalpan Architects & planners |
| Architect | Ideal Design Architects |
| Engineer | Hansal Parikh & Associates |
| Engineer | Raviraj karande |
| Chartered Accountant | NITESH M SHAH & CO |
| Chartered Accountant | H N V & Co |
| Chartered Accountant | CA Saransh Dey |
| Partner | Role in project |
|---|---|
| Siddharth Properties | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe Construction of the project is almost completed only the finishing work of the project is yet to be completed. We only require extension for 12 months.
Reason as filed by the promoterDue to heavy rainfall waterlogged on road resulting into stoppage of supply of materials, process of external plastering was also suspended. Further due to situations beyond control of the Promoter it is not possible for us to deliver possession on declared date.
Reason as filed by the promoterThe project work is completed nearly around 96% , finishing work is in process and we are in process of obtaining occupancy certificate. Therefore, we request to grant extension till 31/03/2026.
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000228422 | SAURABH RAKESH JAIN | Abhijeet Vasant Shende | 02/03/2023 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 13 Apr 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 13 Apr 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 13 Apr 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 13 Apr 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed169
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 169 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Dec 25_Savvy II Architect Cert.pdf | 10 Jul 2026 |
| Withdrawal Update Form 1File: Dec 25_Savvy II Architect Cert.pdf | 10 Jul 2026 |
| Withdrawal Update Form 1File: FORM 1.pdf | 10 Jul 2026 |
| Withdrawal Update Form 2File: Dec 25 Savvy II registration_E cert.pdf | 10 Jul 2026 |
| Withdrawal Update Form 2File: Dec 25 Savvy II registration_E cert.pdf | 10 Jul 2026 |
| Withdrawal Update Form 2File: FORM 2.pdf | 10 Jul 2026 |
| Withdrawal Update Form 3File: FORM 3 FINAL.pdf | 10 Jul 2026 |
| Withdrawal Update Form 3File: FORM 3 FINAL.pdf | 10 Jul 2026 |
| Withdrawal Update Form 3File: FORM 3.pdf | 10 Jul 2026 |
| Withdrawal Update Form 1File: Sept 25 Savvy II Architect Cert.pdf | 8 Dec 2025 |
| Withdrawal Update Form 2File: Engineers Certificate - 30-09-2025 - Savvy II.pdf | 8 Dec 2025 |
| Withdrawal Update Form 3File: Form 3 - Savvy Homes II - Sept 2025.pdf | 8 Dec 2025 |
| Form 5 (FY 2024-2025)File: Form 5 - FY 24-25 - Savvy2.pdf | 29 Nov 2025 |
| Form 1File: FORM 1 ARCHITECT CERTIFICATE.pdf | 4 Oct 2025 |
| Form 2File: FORM 2 ENGINEER CERTIFICATE.pdf | 4 Oct 2025 |
| Form 3File: FORM 3 CA CERTIFICATE.pdf | 4 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY DATED 30-06-2025.pdf | 4 Oct 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Mar 25 Savvy II Architect Cert.pdf | 3 May 2025 |
| Certificates of CA (Form 3)File: C A Certificate - Form 3 - 31-03-2021 done.pdf | 3 May 2025 |
| Certificates of CA (Form 3)File: C A Certificate - Form 3 - 31-03-2022.pdf | 3 May 2025 |
| Certificates of CA (Form 3)File: C A Certificate - Form 3 - 30-09-2022done .pdf | 3 May 2025 |
| Certificates of CA (Form 3)File: C A Certificate - Form 3 - 31-03-2023 done .pdf | 3 May 2025 |
| Certificates of CA (Form 3)File: C A Certificate - Form 3 - 30-06-2023 done.pdf | 3 May 2025 |
| Certificates of CA (Form 3)File: Form III - Savvy Homes II - March 2025.pdf | 3 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 30-12-2023 done.pdf | 3 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Mar 25 Savvy II registration_E cert.pdf | 3 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 31-12-2024done.pdf | 3 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 30-09-2024 done.pdf | 3 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 30-06-2024done .pdf | 3 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 31-03-2024.pdf | 3 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 30-09-2023done.pdf | 3 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 31-03-2023 done.pdf | 3 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 31-12-2022.pdf | 3 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 30-09-2022.pdf | 3 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 30-06-2022done.pdf | 3 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 31-03-2022.pdf | 3 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 31-03-2021.pdf | 3 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 31-12-2020.pdf | 3 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 30-06-2023done.pdf | 3 May 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD 31-03-2025 SAVVY HOMES II.pdf | 3 May 2025 |
| Disclosure of sold/ booked inventoryFile: Discolsure Of Sold - Saarrthi Savvy Homes ll - 30-09-2023.pdf | 3 May 2025 |
| Disclosure of sold/ booked inventoryFile: Discolsure Of Sold - Saarrthi Savvy Homes ll - 30-06-2023.pdf | 3 May 2025 |
| Disclosure of sold/ booked inventoryFile: Discolsure Of Sold - Saarrthi Savvy Homes ll - 31-03-2023.pdf | 3 May 2025 |
| Disclosure of sold/ booked inventoryFile: Discolsure Of Sold - Saarrthi Savvy Homes ll - 30-09-2022 done.pdf | 3 May 2025 |
| Disclosure of sold/ booked inventoryFile: Discolsure Of Sold - Saarrthi Savvy Homes ll - 30-06-2022 done .pdf | 3 May 2025 |
| Disclosure of sold/ booked inventoryFile: Discolsure Of Sold - Saarrthi Savvy Homes ll - 31-12-2021.pdf | 3 May 2025 |
| Disclosure of sold/ booked inventoryFile: Discolsure Of Sold - Saarrthi Savvy Homes ll - 31-03-2021.pdf | 3 May 2025 |
| Disclosure of sold/ booked inventoryFile: Discolsure Of Sold - Saarrthi Savvy Homes ll - 30-03-2020.pdf | 3 May 2025 |
| Disclosure of sold/ booked inventoryFile: Discolsure Of Sold - Saarrthi Savvy Homes ll - 31-04-2019.pdf | 3 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architecture Certificate - 31-12-2020 - Saarrthi Savvy Homes ll.pdf | 2 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architecture Certificate - 27-09-2021 - Saarrthi Savvy Homes ll.pdf | 2 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architecture Certificate - 31-03-2022 - Saarrthi Savvy Homes ll.pdf | 2 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architecture Certificate - 30-06-2022 - Saarrthi Savvy Homes ll.pdf | 2 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architecture Certificate - 30-09-2022 - Saarrthi Savvy Homes ll.pdf | 2 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architecture Certificate - 30-12-2022 - Saarrthi Savvy Homes ll.pdf | 2 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architecture Certificate - 31-03-2023 - Saarrthi Savvy Homes ll.pdf | 2 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architecture Certificate - 30-06-2023 - Saarrthi Savvy Homes ll.pdf | 2 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architecture Certificate - 30-09-2023 - Saarrthi Savvy Homes ll.pdf | 2 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Mar 25 Savvy II Architect Cert.pdf | 19 Apr 2025 |
| Form 2AFile: From 2A - Revised format_Savvy II_2018-19.pdf | 9 Apr 2025 |
| Form 2AFile: From 2A - Revised format_Savvy II_2019-20.pdf | 9 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: From 2A - Revised format_Savvy II_2020-21.pdf | 9 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: From 2A - Revised format_Savvy II_2021-22.pdf | 9 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: From 2A - Revised format_Savvy II_2022-23.pdf | 9 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: From 2A - Revised format_Savvy II_2023-24.pdf | 9 Apr 2025 |
| Declaration in FORM BFile: FORM B - PROMOTER DECLARATION.pdf | 21 Mar 2025 |
| Other - TechnicalFile: Pert Chart.pdf | 21 Mar 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A saarrthi savvy homes ii.pdf | 21 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Dec 24 Savvy II registration_E cert.pdf | 29 Jan 2025 |
| Certificates of CA (Form 3)File: Form 03-Saarrthi Savvy Homes 2 (2).pdf | 24 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Dec 24 Savvy Homes II Architect Cert.pdf | 21 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Savvy Dec 24 Sold Unsold Inventory Certificate.pdf | 21 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: C A Certificate - Saarrthi Savvy Homes ll.pdf | 21 Jan 2025 |
| Certificates of CA (Form 3)File: Form 3 Saarrthi Savvy Homes II.pdf | 29 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Savvy II.pdf | 29 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 SAVY HOMES II.pdf | 25 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Savvy Homes II Sold Unsold.pdf | 25 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: June 24 Savvy II Architect Cert.pdf | 31 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Jun 24 Savvy 2_Sold Unsold Inventory Certificate.pdf | 31 Jul 2024 |
| Certificates of CA (Form 3)File: Savvy Homes-II.pdf | 31 Jul 2024 |
Promoter's earlier projects5
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Souvenir | S.NO 15- 6- 1 MAU MAHALUNGE TAL MULSHI PUNE | 246 | Completed | May 2016 | Jul 2015 |
| Shimmer and Shine | S NO 19 HINGNE KHURD | 147 | Completed | Mar 2016 | Late, Apr 2016 |
| Sovereign | MARUNJI TAL MULSHI PUNE | 259 | Completed | Dec 2015 | Mar 2015 |
| Signor | S NO 273 HINJEWADI TAL MULSHI PUNE | 129 | Completed | Sep 2013 | May 2013 |
| Satin Hills | S NO 37 BAVDHAN BK PUNE 411021 | 101 | Completed | Dec 2010 | Late, Jan 2011 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 8 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 169 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Saarrthi Savvy Homes II on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Hinjewadi13,700+ in Pune
Filed coordinates, straight-line distance. 179 registered projects within 2 km.
Godrej Evergreen Square
Godrej Projects Development Limited
The Aqua Retreat at Godrej Park World
Maan-Hinje Township Developers Private Lim
The Gale at Godrej Park World
Maan-Hinje Township Developers LLP
VTP BELLISSIMO PHASE 1
MAGNITE DEVELOPERS PRIVATE LIMITED
Life Republic Sector R1 - 1st Avenue
KOLTE-PATIL DEVELOPERS LIMITED
The Greenfront at Godrej Park World
Maan Hinje Township Developers Private Lim
Builder: Siddharth Properties
Siddharth Properties has 9 registrations on MahaRERA, including Saarrthi Skybay and Success Square. Its filings disclose 7 earlier MahaRERA projects: declares 4 of 7 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that Saarrthi Savvy Homes II shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Saarrthi Savvy Homes II is delayed beyond 31 Mar 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Saarrthi Savvy Homes II?
The registered promoter entity is Siddharth Properties, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Saarrthi Savvy Homes II?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Saarrthi Savvy Homes II?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Saarrthi Savvy Homes II?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Saarrthi Savvy Homes II?
The professionals named in the filing: Architect: Abhikalpan Architects & planners; Architect: Ideal Design Architects; Engineer: Hansal Parikh & Associates; Engineer: Raviraj karande; Chartered Accountant: NITESH M SHAH & CO; Chartered Accountant: H N V & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Saarrthi Savvy Homes II?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback