Home / Browse projects / Pune, Maharashtra / Saarrthi Savvy Homes

Completed No litigation declared Residential / Group Housing project

Saarrthi Savvy Homes

By Siddharth Value Homes Limited Liability partnership

RG-MH-09638 · RERA P52100001288 · Last updated on MahaRERA portal: 20 Jan 2025

Source: official MahaRERA filing

Red flags

  • 3 complaints at MahaRERA
  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2021Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
3Complaints at MahaRERAon this registration
Jump to the 65 documents Report an error

Saarrthi Savvy Homes is a Residential / Group Housing project by Siddharth Value Homes Limited Liability partnership in Pune, Maharashtra, registered with MahaRERA as P52100001288 on 27 Jul 2017. The registration is recorded completed; possession was promised by 30 Dec 2021. The completion date has moved by 24 months from the original filing. 3 complaints are on record with the regulator.

At a glance

Project

  • NameSaarrthi Savvy Homes
  • TypeResidential / Group Housing
  • Location
    • Hinjavadi (CT)
    • Mulshi
    • Pune
    • 411057
  • Pincode411057
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100001288
  • ReraGenie IDRG-MH-09638

Builder

  • NameSiddharth Value Homes Limited Liability partnership
  • Entity typeOthers
  • Named personsYogesh Ramesh Shende, Abhijeet Vasant Shende, Nilesh Vasant Shende, Swapneel Shashikant Shende
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects5 →

Key dates

this monthRegisteredJul 2017First promiseDec 2019Revised toDec 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on27 Jul 2017
  • Promised completion30 Dec 2021
  • Revised completionRevised to 30 Dec 2021 (originally 31 Dec 2019)
  • Buildings1 building record
  • Documents filed65 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANA160000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

A: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities16

As on 20 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes95%
Street LightingYes90%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes90%
Open ParkingYes100%
swimming poolYes100%

Parking filed118

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots118
Closed/Covered30
Open Space88

Land and ownership3

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area825 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
LandownerVillageDistrict
Balkrishna Baban SakharePune (M Corp.)Pune
Jeevan Balkrishna SakharePune (M Corp.)Pune
Vivek Balkrishna SakharePune (M Corp.)Pune

Approvals and building plan

Permissible FSI8453.17
Proposed, not sanctioned6,086 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBhandarkar Road

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAbhikalpan Architects & planners
ArchitectIdeal Design Architects
EngineerG.A Bhilare Consultants Pvt Ltd.
Chartered AccountantH N V & Co
Chartered AccountantCA Saransh Dey
PartnerRole in project
Siddharth Value Homes Limited Liability partnership-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100003809Dec 2019 → Dec 2020

Reason as filed by the promoterForce majeure conditions on site have led to delay.

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC005000000095968A307 MAYUR SALUNKE A310 SAGAR CHAVAN A607 HRUSHIKESH ANAPM/S.SIDDHARTH VALUE HOM LLP05/10/2021
CC005000000095948Mohammad KhurshidSiddharth Value Homes LLP01/09/2021
CC12500288Syed Tarique NawazSiddharth Value Homes Limited Liability partnership26/01/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Aug 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Aug 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Aug 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 14 Aug 2021

Documents filed65

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: savvy homes.pdf20 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Mar 22 Savvy I registration_Q cert.pdf10 Nov 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Saarrthi Savvy Homes.pdf28 Apr 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Mar 22 Savvy I registration_E cert.pdf28 Apr 2022
Form 2AFile: Mar 22 Savvy I registration_Q cert.pdf28 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form5_March21_Savvy Homes 1.pdf28 Apr 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Dec 21 Savvy I Ar Certificate.pdf31 Jan 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Dec 21 Savvy I Engg Certificate.pdf31 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: SAVVY -I _FORM 2A.pdf11 Nov 2021
Certificates of CA (Form 3)File: Savvy Homes Rera Certificate.pdf3 Nov 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FY 2019-20_Form No 5_Savvy Homes 1.pdf3 Nov 2021
Disclosure of sold/ booked inventoryFile: SAVVY HOMES-I_Discloser of Sold Unsold.pdf7 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SAVVY HOMES-I_FORM 2.pdf6 Oct 2021
Form 2AFile: SAVVY -I _FORM 2A.pdf6 Oct 2021
Declaration about Commencement CertificateFile: Savvy Homes -I.pdf24 Sep 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: Savvy Homes-I.pdf24 Sep 2021
Disclosure of sold/ booked inventoryFile: Savvy homes-I.pdf18 Aug 2021
Certificates of CA (Form 3)File: SAVVY HOMES A CA CERTIFICATE FORM 3.pdf15 Aug 2021
Layout approvalFile: 01-08.pdf14 Aug 2021
Layout approvalFile: 02-08 - Layout.pdf14 Aug 2021
Building plan approvalFile: 03-08.pdf14 Aug 2021
Building plan approvalFile: 04-08.pdf14 Aug 2021
Building plan approvalFile: 05-08.pdf14 Aug 2021
Copy of Layout Approval (in case of layout)File: 01-08.pdf14 Aug 2021
Copy of Layout Approval (in case of layout)File: 02-08 - Layout.pdf14 Aug 2021
Building Plan Approval (IOD)File: 03-08.pdf14 Aug 2021
Building Plan Approval (IOD)File: 04-08.pdf14 Aug 2021
Building Plan Approval (IOD)File: 05-08.pdf14 Aug 2021
Commencement Certificates / NA Order for plotted developmentFile: Comencement Certificate - 21 01 2021.pdf14 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SAVVY HOMES_A_ENGINEER CERTIFICATE_JUN-21.pdf14 Aug 2021
Form 2AFile: SAVVY HOMES_A_QUALITY CERTIFICATE_JUN-21.pdf14 Aug 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate 08 02 2021 A WING.pdf14 Aug 2021
Architect’s Certificate on Completion of Project (Form 4)File: SAVVY HOMES_A_ARCHITECT COMPLETION CERTIFICATE_FORM 4.pdf14 Aug 2021
Proforma of Allotment letterFile: 4 Savvy 1_Draft.pdf3 Jul 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate - Savvy Homes 1 Building A Building.pdf9 Feb 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Savvy1.pdf9 Feb 2021
Form 2AFile: Savvy1.pdf9 Feb 2021
Layout approvalFile: Layout Approval.pdf8 Sep 2020
Building plan approvalFile: Building Plan.pdf8 Sep 2020
Copy of Layout Approval (in case of layout)File: Layout Approval.pdf8 Sep 2020
Building Plan Approval (IOD)File: Building Plan.pdf8 Sep 2020
Commencement Certificates / NA Order for plotted developmentFile: Commecment certificate - SAVVY A.pdf8 Sep 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Scan0063.pdf17 Dec 2019
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Scan0065.pdf17 Dec 2019
Form 2AFile: Engineers Certificate - Saarrthi Saavvy Homes - Form - 2A - 31-03-2019.pdf12 Apr 2019
Certificates of CA (Form 5)File: Form 5 - Savvy Homes.pdf21 Dec 2018
Declaration in FORM BFile: Affidavit Cum Declaration - Savvy Homes _updated.pdf5 Dec 2017
Details of encumbrancesFile: 1-10.pdf14 Nov 2017
Details of encumbrancesFile: 10-20.pdf14 Nov 2017
Details of encumbrancesFile: 21-30.pdf14 Nov 2017
Details of encumbrancesFile: No encumbarances.pdf26 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch cert_savvy.pdf26 Jul 2017
Certificates of CA (Form 3)File: Savvy Final CA letter.pdf26 Jul 2017
Declaration in FORM BFile: Form B_ promoters_ savvy.pdf25 Jul 2017
Proforma of Allotment letterFile: Allotment and ATS_Savvy.pdf25 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form - 2 - Saarrthi Savvy Homes - Engineer Certificate.pdf24 Jul 2017
Building plan approvalFile: Savvy building layout.pdf19 Jul 2017
Copy of the legal title reportFile: 1_Title_Certiificate_1-3.pdf19 Jul 2017
Copy of the legal title reportFile: 1_Title_Certiificate_4-5.pdf19 Jul 2017
Building Plan Approval (IOD)File: Savvy building layout.pdf19 Jul 2017
OtherFile: Demarcation.pdf19 Jul 2017
Layout approvalFile: Savvy_Homes_Hinjawadi_-_Layout_.pdf18 Jul 2017
Copy of Layout Approval (in case of layout)File: Savvy_Homes_Hinjawadi_-_Layout_.pdf18 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Savvy_Homes_Hinjwadi_-_Commencement_Certificate.pdf18 Jul 2017
PAN CardFile: Pan Card - Siddharth Value Homes LLP.pdf15 Jul 2017

Promoter's earlier projects5

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise2 delivered late
ProjectLocationFlatsStatusPromisedDelivered
SouvenirS.NO 15- 6- 1 MAU MAHALUNGE TAL MULSHI PUNE246CompletedMay 2016Jul 2015
Shimmer and ShineS NO 19 HINGNE KHURD147CompletedMar 2016Late, Apr 2016
SovereignMARUNJI TAL MULSHI PUNE259CompletedDec 2015Mar 2015
SignorS NO 273 HINJEWADI TAL MULSHI PUNE129CompletedSep 2013May 2013
Satin HillsS NO 37 BAVDHAN BK PUNE 411021101CompletedDec 2010Late, Jan 2011

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 24 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Saarrthi Savvy Homes on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Hinjavadi (CT)13,700+ in Pune

2 kmSaarrthi Savvy HomesCompleted 84Lapsed / revoked 34Other 62Dot size: filed unitsN

Filed coordinates, straight-line distance. 180 registered projects within 2 km.

Builder: Siddharth Value Homes Limited Liability partnership

Siddharth Value Homes Limited Liability partnership has 2 registrations on MahaRERA, including Saarrthi Savvy Homes and Saarrthi Savvy Biz. Its filings disclose 5 earlier MahaRERA projects: declares 3 of 5 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Saarrthi Savvy Homes is delayed beyond 30 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Saarrthi Savvy Homes?

The registered promoter entity is Siddharth Value Homes Limited Liability partnership, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Saarrthi Savvy Homes?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Saarrthi Savvy Homes?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Saarrthi Savvy Homes?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Saarrthi Savvy Homes?

The professionals named in the filing: Architect: Abhikalpan Architects & planners; Architect: Ideal Design Architects; Engineer: G.A Bhilare Consultants Pvt Ltd.; Chartered Accountant: H N V & Co; Chartered Accountant: CA Saransh Dey. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Saarrthi Savvy Homes?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Saarrthi Savvy Homes. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Saarrthi Savvy Homes to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.