Home / Browse projects / Pune, Maharashtra / S.S.HEIGHTS

Registration lapsed No litigation declared Residential / Group Housing project

S.S.HEIGHTS

By AJINKYA REALITY

RG-MH-16141 · RERA P52100025266 · Last updated on MahaRERA portal: 1 Oct 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 19 months past the filed date
  • Completion date moved by 30 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2025Possession promised19 months past this date
6 of 11Construction stages donefurthest along: Staircases, 95%
0Complaints at MahaRERAon this registration
Jump to the 80 documents Report an error

S.S.HEIGHTS is a Residential / Group Housing project by AJINKYA REALITY in Pune, Maharashtra, registered with MahaRERA as P52100025266 on 31 Mar 2020. Possession was promised by 31 Mar 2025 and is now 19 months past that date. The completion date has moved by 30 months from the original filing.

At a glance

Project

  • NameS.S.HEIGHTS
  • TypeResidential / Group Housing
  • Location
    • B T Kawade Road
    • Ghorpadi
    • Pune (M Corp.)
    • Pune City
    • Pune
    • 411001
  • Pincode411001
  • RERA no.P52100025266
  • ReraGenie IDRG-MH-16141

Builder

  • NameAJINKYA REALITY
  • Entity typePartnership
  • PartnersAkshay Anilrao Deshmukh, Aditya Suresh Khedkar, Mahesh Kamalakar Suryavanshi

Key dates

19 months past promisethis monthRegisteredMar 2020First promiseSep 2022Revised toMar 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on31 Mar 2020
  • Promised completion31 Mar 2025
  • Revised completionRevised to 31 Mar 2025 (originally 30 Sep 2022)
  • Buildings1 building record
  • Documents filed80 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
S S HEIGHTSNA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 1 Oct 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 95%.

S S HEIGHTS: 97% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises92%
Sanitary Fittings within the flats / premises92%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.93%

Progress on shared amenities15

As on 1 Oct 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes95%
Water SupplyYes93%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes91%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes90%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed61

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots61
Closed/Covered61

Land and ownership3

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area906 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
LandownerVillageDistrict
Ajinkya RealityMundhawaPune
Sunil Tukaram SawantPune (M Corp.)Pune
Soniya Sunil SawantPune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI993.37
Proposed, not sanctioned993 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKeshavnagar

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSagar Karale
EngineerGanesh Narayan Kalbhor
Chartered AccountantAkshay Kadam and Associates
Chartered AccountantDnyaneshwar Shelar
PartnerRole in project
AJINKYA REALITY-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100013765Sep 2022 → Mar 2024

Reason as filed by the promoterWE WANT PROJECT EXTENSION FOR RAISE IN ADDITIONAL FLOORS IN THE SAID BUILDING .

EXT52100019208Sep 2022 → Mar 2025

Reason as filed by the promoterExtension is requested due to the additional work in Project. The project could not be completed as per the proposed completion date due to non availability of required resources on time, such as skill-full labour/contractors/raw material etc., due to which the suitable season got delayed ultimately resulting in the overall delay in the project.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Mar 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Nov 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 Nov 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed80

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2024-2025)File: Form 5 FY 24-25 Ajinkya Reality.pdf1 Oct 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM3.pdf4 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2.pdf4 Dec 2024
Disclosure of sold/ booked inventoryFile: sold unsold.pdf4 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form1_11zon.pdf23 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 FY 23-24 Ajinkya Reality_Signed.pdf25 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architeture Certificate March 24.pdf20 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate June 24.pdf20 Aug 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Inventory- June 24.pdf20 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 June 24 Ajinkya Reality_11zon.pdf20 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 Form 1 Architect Certificate March 24.pdf25 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4 Final Form 2 Engineer Certificate March 24.pdf25 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Final Form 2A FY 23-24 Signed.pdf25 Jun 2024
Disclosure of sold/ booked inventoryFile: 4 Sold Unsold Inventory March 24.pdf25 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 4 Form 3 March 24.pdf25 Jun 2024
Commencement Certificates / NA Order for plotted developmentFile: Latest CC SKMBT-C28023041112360.pdf14 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Form 1 June 23.pdf14 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 Form 1 Sept 23.pdf14 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3 Form 1 Dec 23.pdf14 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 Final Form 2 Engineer Certificate June 23.pdf14 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Final Form 2 Engineer Certificate Sept 23.pdf14 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3 Final Form 2 Engineer Certificate Dec 23.pdf14 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Final FORM 2A 22-23 Signed.pdf14 Mar 2024
Disclosure of sold/ booked inventoryFile: 1 Sold Unsold Inventory June 23.pdf14 Mar 2024
Disclosure of sold/ booked inventoryFile: 2 Sold Unsold Inventory Sept 23.pdf14 Mar 2024
Disclosure of sold/ booked inventoryFile: 3 Sold Unsold Inventory Dec 23.pdf14 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 Form 3 June 23 Compressed.pdf14 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2 Form 3 Sept 23 Compressed.pdf14 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 Form 3 Dec 23 Compressed.pdf14 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form - 5 - FY 21-22_Signed.pdf14 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form - 5 - FY 22-23_Signed.pdf14 Mar 2024
Proforma of Agreement for saleFile: SS Hights rera draft.pdf9 Dec 2023
Layout approvalFile: HPSC0765_compressed.pdf1 Nov 2023
Layout approvalFile: HPSC0766_compressed_compressed.pdf1 Nov 2023
Building plan approvalFile: HPSC0765_compressed.pdf1 Nov 2023
Copy of Layout Approval (in case of layout)File: HPSC0765_compressed.pdf1 Nov 2023
Copy of Layout Approval (in case of layout)File: HPSC0766_compressed_compressed.pdf1 Nov 2023
Building Plan Approval / NA Order for plotted developmentFile: HPSC0765_compressed.pdf1 Nov 2023
Commencement Certificates / NA Order for plotted developmentFile: SKMBT_C28023041112360.pdf1 Nov 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosuer of interest.pdf17 Mar 2023
Proforma of Agreement for saleFile: sale agreement.pdf17 Mar 2023
Proforma of Allotment letterFile: allotment letter.pdf17 Mar 2023
Deviation Report with respect to Allotment letterFile: Deviation from allotment letter.pdf17 Mar 2023
Deviation Report with respect to model copy of AgreementFile: Deviation with respect to agreement.pdf17 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3_compressed (2).pdf16 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 FY 2018-19 - Ajinkya Realty.pdf16 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 FY 2019-20 - Ajinkya Realty.pdf16 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 FY 2020-21 - Ajinkya Realty.pdf16 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2019-2020.pdf21 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2020-2021.pdf21 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2021-22.pdf21 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate Ajinkya REality.pdf13 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate cost.pdf13 Jan 2023
Disclosure of sold/ booked inventoryFile: sold and unsold inventory.pdf13 Jan 2023
CERSAI detailsFile: CERSAI_Search_Report_200257484303_For_Asset_Based_Search_13_01_2023_11_29_13_466.pdf13 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 2022.pdf13 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5.pdf13 Jan 2023
Proforma of Agreement for saleFile: PROFORMA AGREEMENT FOR SALE.pdf13 Jan 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Rera Bank details.pdf13 Jan 2023
Deviation Report with respect to Allotment letterFile: deviation report of allotement letter.pdf13 Jan 2023
Deviation Report with respect to model copy of AgreementFile: DEVIATION REPORT WITH RESPECT MODEL COPY OF AGREEMENT_compressed.pdf13 Jan 2023
Details of encumbrances concerned to FinanceFile: DETAILS OF ENCUMBRANCES.pdf6 Jan 2023
Details of encumbrances concerned to LegalFile: DETAILS OF ENCUMBRANCES.pdf6 Jan 2023
Declaration about Commencement CertificateFile: CC DECLARATION.pdf18 May 2022
Disclosure of sold/ booked inventoryFile: DETAILS FOR SOLD AND UNSOLD INVENTORY.pdf18 May 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate_compressed.pdf23 Mar 2020
Proforma of Allotment letterFile: Kararnama_PDF-1-8.pdf23 Mar 2020
Proforma of Allotment letterFile: Kararnama New_Draft_Assaintmeny_Deed_PDF-1-7.pdf23 Mar 2020
OtherFile: Notrised Partnership Deed_compressed.pdf23 Mar 2020
Building plan approvalFile: HPSC0003_compressed.pdf10 Mar 2020
Layout approvalFile: HPSC0002_compressed.pdf10 Mar 2020
PAN CardFile: FIRM PAN.pdf10 Mar 2020
Copy of the legal title reportFile: search report_compressed.pdf10 Mar 2020
Details of encumbrancesFile: Encumbrance Details.pdf10 Mar 2020
Copy of Layout Approval (in case of layout)File: HPSC0002_compressed.pdf10 Mar 2020
Building Plan Approval / NA Order for plotted developmentFile: HPSC0003_compressed.pdf10 Mar 2020
Commencement Certificates / NA Order for plotted developmentFile: commencement certificate_compressed.pdf10 Mar 2020
Commencement Certificates / NA Order for plotted developmentFile: NA order_compressed(1).pdf10 Mar 2020
Declaration in FORM BFile: form B_compressed.pdf10 Mar 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3_compressed.pdf10 Mar 2020

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 30 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep S.S.HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Ghorpadi13,700+ in Pune

Builder: AJINKYA REALITY

AJINKYA REALITY has 1 registration on MahaRERA, including S.S.HEIGHTS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that S.S.HEIGHTS shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if S.S.HEIGHTS is delayed beyond 31 Mar 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of S.S.HEIGHTS?

The registered promoter entity is AJINKYA REALITY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in S.S.HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for S.S.HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at S.S.HEIGHTS?

The professionals named in the filing: Architect: Sagar Karale; Engineer: Ganesh Narayan Kalbhor; Chartered Accountant: Akshay Kadam and Associates; Chartered Accountant: Dnyaneshwar Shelar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in S.S.HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About S.S.HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save S.S.HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.