Home / Browse projects / Pune, Maharashtra / S R SWASTHI

Registration lapsed No litigation declared Residential / Group Housing project

S R SWASTHI

By S R Buildpro Icon LLP

RG-MH-04911 · RERA P52100021323 · Last updated on MahaRERA portal: 22 Nov 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 32 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Feb 2024Possession promised32 months past this date
0 of 11Construction stages donefurthest along: Excavation, 0%
0Complaints at MahaRERAon this registration
Jump to the 19 documents Report an error

S R SWASTHI is a Residential / Group Housing project by S R Buildpro Icon LLP in Pune, Maharashtra, registered with MahaRERA as P52100021323 on 21 Jun 2019. Possession was promised by 28 Feb 2024 and is now 32 months past that date.

At a glance

Project

  • NameS R SWASTHI
  • TypeResidential / Group Housing
  • Location
    • Balewadi
    • Haveli
    • Pune
    • 411045
  • Pincode411045
  • RERA no.P52100021323
  • ReraGenie IDRG-MH-04911

Builder

  • NameS R Buildpro Icon LLP
  • Entity typePartnership
  • GSTIN27ACUFS0429D1ZZ
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersMeenakshi Rajendra Reddy, Meenakshi Rajendra Reddy
  • Other registrations3 more →
  • No longer live2 lapsed, de-registered or revoked

Key dates

32 months past promisethis monthRegisteredJun 2019PromisedFeb 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on21 Jun 2019
  • Promised completion28 Feb 2024
  • Revised completionNone
  • Buildings1 building record
  • Documents filed19 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING ANA120000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 22 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.

BUILDING A: 0% average across the applicable activities

ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 22 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed36

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots36
Closed/Covered26
Open Space10

Land and ownership3

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,536 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
LandownerVillageDistrict
MRS. INDUMATI BALASAHEB MOREThane (M Corp.)Thane
MR. MANOJ GOPALJI LAKHANIMumbai CityMumbai City
RAJENDRA VENKAT REDDYBanerPune

Approvals and building plan

Permissible FSI3174.29
Proposed, not sanctioned1,582 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchS NO 140/1 PASHAN -SUS ROAD , PASHAN ,PUNE 411021

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVILAS TARWADI
EngineerMR. RAM RANDHAVE
PartnerRole in project
S R Buildpro Icon LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 May 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Jun 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Jun 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 May 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 22 Nov 2024

Documents filed19

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: completion certificate swasthi10-9-24.pdf22 Nov 2024
Proforma of Allotment letterFile: BlancRERA - SWASTHI.pdf4 Jan 2022
Certificates of CA (Form 3)File: Form 3_SR Swasthi_Signed.pdf12 Apr 2021
Building plan approvalFile: Demarcation Balewadi 37.pdf19 Jun 2019
Layout approvalFile: hp_scan_3.pdf19 Jun 2019
Copy of Layout Approval (in case of layout)File: hp_scan_3.pdf19 Jun 2019
Building Plan Approval (IOD)File: Demarcation Balewadi 37.pdf19 Jun 2019
Certificates of CA (Form 3)File: Form 3.pdf30 May 2019
Building plan approvalFile: Commencement Certificate.pdf3 May 2019
Layout approvalFile: hp_scan_1.pdf3 May 2019
Layout approvalFile: hp_scan_2.pdf3 May 2019
Copy of the legal title reportFile: Search Report Title Certificate-min_compressed.pdf3 May 2019
Details of encumbrancesFile: Encumbrance Letter.pdf3 May 2019
Copy of Layout Approval (in case of layout)File: hp_scan_1.pdf3 May 2019
Copy of Layout Approval (in case of layout)File: hp_scan_2.pdf3 May 2019
Building Plan Approval (IOD)File: Commencement Certificate.pdf3 May 2019
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf3 May 2019
Declaration in FORM BFile: FORM B SCAN COPY_compressed.pdf3 May 2019
Proforma of Allotment letterFile: Allotment Letter format.pdf3 May 2019

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep S R SWASTHI on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Balewadi13,700+ in Pune

Builder: S R Buildpro Icon LLP

S R Buildpro Icon LLP has 4 registrations on MahaRERA, including Aaishwaryam and S R SWASTHI. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that S R SWASTHI shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if S R SWASTHI is delayed beyond 28 Feb 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of S R SWASTHI?

The registered promoter entity is S R Buildpro Icon LLP, a partnership as per the filing. Its GSTIN 27ACUFS0429D1ZZ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in S R SWASTHI?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for S R SWASTHI?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at S R SWASTHI?

The professionals named in the filing: Architect: VILAS TARWADI; Engineer: MR. RAM RANDHAVE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in S R SWASTHI?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About S R SWASTHI. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save S R SWASTHI to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.