ReraGenieLog inGet a buyer report

Home / Browse projects / Kolhapur, Maharashtra / S.B. HEIGHTS

Registration lapsed No litigation declared Residential / Group Housing project

S.B. HEIGHTS

By SIDRA DEVELOPERS

RG-MH-48205 · RERA P53000018982 · Last updated on MahaRERA portal: 31 Jul 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • Completion date moved by 43 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Kolhapur registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
5 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 95%
0Complaints at MahaRERAon this registration
Jump to the 73 documents Report an error

S.B. HEIGHTS is a Residential / Group Housing project by SIDRA DEVELOPERS in Kolhapur, Maharashtra, registered with MahaRERA as P53000018982 on 28 Dec 2018. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 43 months from the original filing.

At a glance

Project

  • NameS.B. HEIGHTS
  • TypeResidential / Group Housing
  • Location
    • shahapur road
    • sangli naka
    • Ichalkaranji (M Cl)
    • Hatkanangle
    • Kolhapur
    • 416115
  • Pincode416115
  • RERA no.P53000018982
  • ReraGenie IDRG-MH-48205

Builder

  • NameSIDRA DEVELOPERS
  • Entity typePartnership
  • PartnersSabiha Firoj Shikalagar, samir shabbir shaikh, Shirin Samir Shaikh
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked

Key dates

10 months past promisethis monthRegisteredDec 2018First promiseMay 2022Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on28 Dec 2018
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 14 May 2022)
  • Buildings1 building record
  • Documents filed73 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SBHEIGHTSNA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 31 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.

SBHEIGHTS: 71% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 31 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes90%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes90%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,035 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1490.18
Proposed, not sanctioned1,490 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchICHALKARANJI

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVarsha A Shinde
ArchitectRahul R Shreshthi
EngineerAmar Dhumal
PartnerRole in project
SIDRA DEVELOPERS-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT53000011542May 2022 → Apr 2023

Reason as filed by the promoterDue to covid 19 second layer and probability of third layer scope of work was not completed.

EXT53000015262May 2022 → Jul 2024

Reason as filed by the promoterDue to manpower shortages in our area, the completion of project is delayed. now we have arranged such team and calculated the total time required for completion. kindly sanction such extension for the project.

EXT53000025544May 2022 → Dec 2025

Reason as filed by the promoterTo, The Maharashtra Real Estate Regulatory Authority (MAHARERA) Subject: Request for Extension of MAHARERA Project Completion Deadline by 31/07/2024 Respected Sir/Madam, We,SIDRA DEVELOPER, the promoters of the project S B HIGHTS registered under MAHARERA with registration number P53000018982, hereby submit this formal request for an extension of the project completion deadline. The unforeseen and unavoidable challenges listed below have significantly impacted the project's progress and completion timeline: 1. Worker Problem: The project has faced severe labour shortages due to various reasons

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Nov 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Nov 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Nov 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Nov 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 14 Nov 2024

Documents filed73

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: FORM 01.pdf31 Jul 2025
Form 2File: FORM 02.pdf31 Jul 2025
Form 3File: FORM 3 C0001.pdf31 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD.pdf31 Jul 2025
Declaration in FORM BFile: 3 NOTARY.pdf28 Jun 2025
Certificates of CA (Form 3)File: FORM 3_compressed.pdf28 Jun 2025
Disclosure of sold/ booked inventoryFile: disclosure sold unsold.pdf28 Jun 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf28 Jun 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: disclosure of interest (1).pdf28 Jun 2025
Declaration in FORM BFile: 3 NOTARY.pdf21 Jun 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1A FORM 1.pdf21 Jun 2025
Certificates of CA (Form 3)File: 1D FORM 3 CA.pdf21 Jun 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 1B FORM 2.pdf21 Jun 2025
Disclosure of sold/ booked inventoryFile: 2 SOLD UNSOLD INVENTORY.pdf21 Jun 2025
CERSAI detailsFile: 4 CERSAI details.pdf21 Jun 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: 6 SEPEARATE BANK DESCLOSURE.pdf21 Jun 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: 5A Annexure A samir shaikh.pdf21 Jun 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: 5B Annexure A shirin samir shaikh.pdf21 Jun 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: 5C Annexure A Firoj B shikalgar.pdf21 Jun 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: 5D Annexure A sabiha firoj shikalgar.pdf21 Jun 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 1C A FORM -2A QUALITY ASSURANCE.pdf21 Jun 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 1E FORM 5 2022 -23.pdf21 Jun 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 1C A FORM -2A QUALITY ASSURANCE.pdf21 Jun 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: 1E FORM 5 2023 - 24.pdf21 Jun 2025
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 ARCHITECH CERTIFICATE.pdf4 Dec 2024
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 ARCHITECH CERTIFICATE.pdf14 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: COMPLETION CERTIFICATE.pdf14 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: NEW Form 2.pdf18 Feb 2023
Certificates of CA (Form 3)File: NEW FORM 3.pdf18 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: PDFGallery_20230216_223314_compressed (1).pdf16 Feb 2023
Proforma of Agreement for saleFile: agreement to sale.pdf5 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: CA 2021 22.pdf22 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: CA 2021 22.pdf22 Jan 2023
Details of encumbrances concerned to FinanceFile: declaration of encumbrance.pdf19 Jan 2023
Details of encumbrances concerned to LegalFile: declaration of encumbrance.pdf19 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2019 to 2021.pdf19 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: QUALITY ASSURANCE 2.pdf19 Jan 2023
Certificates of CA (Form 3)File: Re upload Form 3.pdf19 Jan 2023
Certificates of CA (Form 5)File: Re upload Form 5.pdf19 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 2019 to 2021.pdf19 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 2020 to 2021.pdf19 Jan 2023
Certificates of CA (Form 5)File: CA 1.pdf9 Jun 2022
Disclosure of sold/ booked inventoryFile: 11zon_JPEG-to-PDF.pdf30 May 2022
Proforma of Allotment letterFile: allotment letter s b heights.pdf7 May 2022
Proforma of Allotment letterFile: consent 1-converted.pdf5 May 2022
Details of encumbrancesFile: declaration of encumbrance.pdf25 Apr 2022
Declaration about Commencement CertificateFile: declaration of commencement.pdf25 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: QUALITY ASSURANCE 2.pdf25 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QUALITY ASSURANCE 2.pdf25 Apr 2022
Disclosure of sold/ booked inventoryFile: DISCLOSER A-converted_11zon.pdf25 Apr 2022
CERSAI detailsFile: CERSAI.pdf25 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 2018-19 ANUAL REPORT.pdf25 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 2019-20 ANUAL REPORT.pdf25 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 2021-21 ANUAL REPORT.pdf25 Apr 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy part completion.pdf25 Apr 2022
CERSAI detailsFile: Original final sanction drawing-compressed_11zon.pdf9 Mar 2022
Declaration about Commencement CertificateFile: 1 Commencement Certificates _ NA Order for plotted development.pdf11 Dec 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architecture Certificate.pdf26 Nov 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Architecture Certificate.pdf26 Nov 2018
Layout approvalFile: LAYOUT PLAN.pdf24 Nov 2018
Building plan approvalFile: AMAL COMMISSION PLAN sanction drg.pdf24 Nov 2018
PAN CardFile: pancard 4.pdf24 Nov 2018
Copy of the legal title reportFile: search report.pdf24 Nov 2018
Details of encumbrancesFile: 7-12 encumb.pdf24 Nov 2018
Copy of Layout Approval (in case of layout)File: LAYOUT PLAN.pdf24 Nov 2018
Building Plan Approval (IOD)File: AMAL COMMISSION PLAN sanction drg.pdf24 Nov 2018
Commencement Certificates / NA Order for plotted developmentFile: nakasha manjuri patra.pdf24 Nov 2018
Declaration in FORM BFile: Form B3.pdf24 Nov 2018
Certificates of CA (Form 3)File: CA form 3 5.pdf24 Nov 2018
Certificates of CA (Form 5)File: CA form 3 5.pdf24 Nov 2018
Proforma of Allotment letterFile: d-1.pdf24 Nov 2018
Declaration in FORM BFile: Form B1.pdf23 Nov 2018
Declaration in FORM BFile: Form B.pdf23 Nov 2018

How this compares with Kolhapur

17%of Kolhapur projects moved their completion datethis one moved by 43 months
25%of Kolhapur registrations have lapsed or been cancelledthis one is among them

Computed across the 880+ Kolhapur projects on ReraGenie, from their own filings.

Keep S.B. HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near sangli naka880+ in Kolhapur

Builder: SIDRA DEVELOPERS

SIDRA DEVELOPERS has 2 registrations on MahaRERA, including S.B. HEIGHTS and NISARGAYAN. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Kolhapur district page.

Frequently asked questions

What does it mean that S.B. HEIGHTS shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if S.B. HEIGHTS is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of S.B. HEIGHTS?

The registered promoter entity is SIDRA DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in S.B. HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for S.B. HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at S.B. HEIGHTS?

The professionals named in the filing: Architect: Varsha A Shinde; Architect: Rahul R Shreshthi; Engineer: Amar Dhumal. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in S.B. HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About S.B. HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save S.B. HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.