Home / Browse projects / RUSTOMJEE CROWN - PHASE I
RUSTOMJEE CROWN - PHASE I
By Realgem Buildtech Private Limited
RG-MH-11591 · RERA P51900003268 · Last updated on MahaRERA portal: 30 Sep 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 22 months past the filed date
- 65 complaints at MahaRERA
- Completion date moved by 24 months
- 2 extensions taken
- Rs 2,190.00 crore secured on the land, in favour of Axis Bank Limited
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
RUSTOMJEE CROWN - PHASE I is a Residential / Group Housing project by Realgem Buildtech Private Limited in prabhadevi, 400025, registered with MahaRERA as P51900003268 on 5 Aug 2017. Possession was promised by 30 Dec 2024 and is now 22 months past that date. The completion date has moved by 24 months from the original filing. 65 complaints are on record with the regulator.
At a glance
Project
- NameRUSTOMJEE CROWN - PHASE I
- TypeResidential / Group Housing
- Location
- Gokhale road
- prabhadevi
- 400025
- Pincode400025
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51900003268
- ReraGenie IDRG-MH-11591
Builder
- NameRealgem Buildtech Private Limited
- Entity typeCompany
- DirectorZubin Patel
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on5 Aug 2017
- Promised completion30 Dec 2024
- Revised completionRevised to 30 Dec 2024 (originally 30 Dec 2022)
- Buildings2 building records
- Documents filed194 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Tower A | NA | 71 | 0 | 0 | 0 | 0 |
| Tower B | NA | 71 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 30 Sep 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
19 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 99%.
Tower A100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Tower B100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 99% |
| Sanitary Fittings within the flats / premises | 97% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 99% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities28
As on 30 Sep 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
| Outdoor Swimming Pool | Yes | 0% |
| Jacuzzi Steam and Sauna | Yes | 0% |
| Indoor Lap Pool | Yes | 0% |
| In common with Phase II | Yes | 0% |
| Children Play Area | Yes | 0% |
| Welfare Centre | Yes | 0% |
| Changing Rooms | Yes | 0% |
| Sports and Recreation Activity Area | Yes | 0% |
| Double Height Sports Court | Yes | 0% |
| Society Office | Yes | 0% |
| Society Amusement Area | Yes | 0% |
| Fitness Centre | Yes | 0% |
| Massage Room | Yes | 0% |
Parking filed929
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| Tower A | 465 | 465 |
| Tower B | 464 | 464 |
Land and ownership1
MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
| Landowner | Village | District |
|---|---|---|
| Bhishma Realty Limited | Mumbai City | Mumbai City |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Chartered Accountant | V A Shimpi and Associates |
| Partner | Role in project |
|---|---|
| Realgem Buildtech Private Limited | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter(1) On account of Covid-19 pandemic, the supply chains and logistics were adversely affected due to which there was extreme shortage of construction material and availability of equipment, mass labour shortage, import shipment delays which impacted the projected timelines for construction. (2) Geopolitical tensions have impacted supply of goods, equipment and materials to the said Real Estate Project. (3) The said Real Estate Project being of a very large scale is dependent upon overseas supplies which have taken a hit right from 2020. Several vendors have delayed in delivery of goods or attem
Reason as filed by the promoterDue to the several difficulties encountered by our project contractors owing to the difficulties posed due to the covid - 19 pandemic situation including restrictions on travel , transport and delivery of material and goods, curfew related restrictions that impacted the working hours of various industries and commute to work places , they may not be able to meet the previously estimated timelines for completing work of Facade, internal furnishing and lift installation, which is likely to affect the project completion timelines. In view thereof, we are estimating that we will not be able to com
Litigation declared14
| Case | Court | Status |
|---|---|---|
| SC Suit No 424 of 2011/2011 | City Civil Court | suit is filed for executing AFS now the matter is pending before HC suit is stayed |
| SC Suit No 423 of 2011/2011 | City Civil Court | suit is filed for executing AFS now the matter is pending before HC suit is stayed |
| CC No 4107409/SS/2017/2017 | Magistrate Court Shindewadi | dispossed off |
| Suit No 141 of 2017/2017 | High Court Bombay | suit is filed for executing AFS now the matter is kept for hearing on Notice of Motion |
| Suit No 840 of 2016/2016 | High Court Bombay | suit is filed for executing AFS now the matter is kept for hearing on Notice of Motion |
| Suit No 4064 of 2013/2013 | High Court Bombay | Motion pending for delay condonation in filing WS |
| WP 62 of 2016/2016 | High Court Bombay | This WP is disposed of |
| CC 1426 of 2018/2018 | Delhi NCDRC | Matter kept for hearing |
| WP No 5446 of 2017/2017 | High Court Bombay | Matter pending |
| CC No 2491/2018 | Delhi NCDRC | matter pending for hearing |
| 4544/2019 | NCLT | Matter Disposed off |
| 4544/2019 | NCLT | Matter Disposed off |
| 4544/2019 | NCLT | Matter Disposed off |
| 4544/2019 | NCLT | Mater Disposed off |
Complaints filed with MahaRERA65
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000000411 | PRADEEP BANKA | REALGEM BUILDTECH PRIVATE LIMITED | 08/09/2017 |
| CC006000000193924 | JAIKUMAR GUPTA HUF | REAL GEM BUILDTECH PVT LTD | 10/09/2020 |
| CC006000000195172 | JAIKUMAR GUPTA HUF | REAL GEM BUILDTECH PVT LTD | 07/12/2020 |
| CC006000000023635 | Bhavesh Gandhi HUF | Realgem Buildtech Private Limited (DB Group) | 09/03/2018 |
| CC006000000023654 | Nikhil Gandhi HUF | Realgem Buildtech Private Limited (DB Group) | 09/03/2018 |
| CC006000000043990 | Anshul Gupta | Real Gem Buildtech Private Limited | 12/04/2018 |
| CC006000000055089 | Anshul Gupta | Real GEm Buildtech Pvt. Ltd. | 26/06/2018 |
| CC006000000068165 | Anshul Gupta | Real Gem Buildtech Pvt. Ltd | 20/02/2019 |
| CC006000000044305 | RADHAKRISHNA SHETTY | REALGEM BUILDTECH PVTLTD | 27/04/2018 |
| CC006000000057156 | MR. SANDEEP SHASHIDHAR PHANASGAONKAR AND MRS. AISHWARYA SANDEEP PHANASGAONKAR | REAL GEM BUILDTECH PRIVATE LIMITED | 24/12/2018 |
| CC006000000209961 | SUDARSHAN PROPERTIES PRIVATE LIMITED | BHISHMA REALTY LIMITED | 09/02/2022 |
| CC006000000057404 | KRISH VASWANI | REAL GEM BUILDTECH PVT LTD | 04/01/2019 |
| CC006000000057395 | MOHIT VASWANI | REAL GEM BUILDTECH PVT LTD | 04/01/2019 |
| CC006000000057394 | VARUN WASWANI | REAL GEM BUILDTECH PVT LTD | 18/01/2019 |
| CC006000000057506 | Crimson Interactive Pvt Ltd | Realgm Buildtech Pvt Ltd | 09/01/2019 |
| CC006000000078497 | Kapil Trikha | Bhishma Realty Limited | 15/03/2019 |
| CC006000000078571 | Rajesh Balkrishnan | Realgem Build-Tech Private Limited | 25/03/2019 |
| CC006000000078578 | Umesh Shishupal Punia | Kingmaker Developes Pvt Ltd | 25/03/2019 |
| CC006000000078638 | Kingmaker Developers Pvt Ltd | VArun and Gehena Vaswani | 26/03/2019 |
| CC006000000078640 | Kingmaker Developers Pvt Ltd | Krish and Ravi Vaswani | 26/03/2019 |
| CC006000000078641 | Kingmaker Developers Pvt Ltd | Mohit and Janak Vaswani | 26/03/2019 |
| CC006000000078645 | Kingmaker Developers Pvt Ltd | Crimson Interactive Pvt Ltd | 26/03/2019 |
| CC006000000078773 | NITYA BUXANI | REAL GEM BUILDTECH PVT LTD | 05/04/2019 |
| CC006000000199191 | Mr. Suresh Kolhapure | Real Gem Buildtech Pvt. Ltd | 10/01/2022 |
| CC006000000079173 | PANKAJ KISHORE AGRAWAL | REAL GEM BUILDTECH PRIVATE LIMITED | 07/05/2019 |
| CC006000000079251 | Julia Maria Aisha De Sequeira | Real Gem Buildtech Private Limited | 11/05/2019 |
| CC006000000171633 | Realgem Buildtech Pvt Ltd and Ors | Akhil Jindal and Anr | 19/12/2019 |
| CC006000000171634 | RealGem Buildtech Pvt Ltd and Ors | Viraang Shah | 22/11/2019 |
| CC006000000171945 | Realgem Buildtech Pvt Ltd and Ors | Kheraj Chavvda and Anr | 23/12/2019 |
| CC006000000171948 | Realgem Buildtech Pvt Ltd and Ors | Karnail Singh Cheema and Anr | 24/12/2019 |
| CC006000000192265 | Realgem Buildtech Pvt Ltd and Anr | Chandraprakash Agarwal | 22/01/2020 |
| CC006000000192337 | Realgem Buildtech and Ors | Blooming Mining Pvt Ltd | 29/01/2020 |
| CC006000000192805 | VINOD S PASARI | REAL GEM BUILDTECH PVT LTD | 03/03/2020 |
| CC006000000192808 | VINOD S PASARI | BHISHMA REALTY LTD | 03/03/2020 |
| CC006000000193132 | Kashyap K Mehta | Bhishma Realty Limited | 03/04/2020 |
| CC006000000193606 | KASHYAP K MEHTA | Bhishma Realty Limited | 28/07/2020 |
| CC006000000193603 | Tushar Raul | Real Gem Builders Private Limited | 28/07/2020 |
| CC006000000197954 | Opera Clothing Private Limited | Real Gem Buildtech Private Limited | 11/08/2021 |
| CC006000000198108 | Bhavesh Jayantilal Jain | Real Gem Buildtech Pvt Ltd | 26/08/2021 |
| CC006000000194894 | M/s Jhawar Trade and Investment Pvt. Ltd. | Bhishma Realty Limited | 09/12/2020 |
| CC006000000209990 | Chandraprakash Agarwal | Real Gem Buildtech Private Limited | 10/02/2022 |
| CC006000000197918 | Dr. Priyadarshini Sanyal | RealGem Buildtech Private Limited | 25/08/2021 |
| CC006000000198377 | Bhavesh Gnadhi HUF | Real Gem Build Tech Pvt. Ltd | 18/09/2021 |
| CC006000000209851 | Nikhil Gandhi HUF | Real Gem Build Tech Pvt. Ltd | 28/01/2022 |
| CC006000000198965 | K R Pradeep | Bhishma Realty Limited | 14/11/2021 |
| CC006000000199180 | KRISHNAKUMAR TAORI | REALGEM BUILDTECH PVT. LTD | 29/11/2021 |
| CC006000000292852 | Anil Kumar Dattani | Realgem Buildtech Private Limited | 27/09/2022 |
| CC006000000333943 | Karnail Singh Cheema | REAL GEM BUILDTECH PVT LTD | 13/01/2023 |
| CC006000000364754 | Beekaylon Synthetics Private Limited | Realgem Buildtech Private Limited | 10/03/2023 |
| CC006000000374883 | SUSHIL RAMSWAROOP GADIA | REAL GEM BUILDTECH PRIVATE LIMITED | 23/03/2023 |
| CC006000000374880 | SURESH MAHAVEER PANSARI | REAL GEM BUILDTECH PRIVATE LIMITED | 23/03/2023 |
| CC006000000374892 | MANJU SURESH PANSARI | REAL GEM BUILDTECH PVT. LTD. | 23/03/2023 |
| CC006000000395674 | R. C. REALTORS PRIVATE LIMITED | REAL GEM BUILDTECH PRIVATE LIMITED | 09/05/2023 |
| CC006000000395754 | keyur manoj dalal | Real Gem Buildtech pvt ltd | 11/05/2023 |
| CC006000000396026 | Jatin Harish Shah | Real Gem Buildtech Private Limited | 02/06/2023 |
| CC006000000396829 | BALKRISHNA DOKANIA | REAL GEM BUILDTECH PRIVATE LIMITED | 26/07/2023 |
| CC006000000396823 | PRAJITA INVESTMENTS PVT. LTD. | REAL GEM BUILDTECH PRIVATE LIMITED | 26/07/2023 |
| CC006000000396824 | BALKRISHNA DOKANIA | REAL GEM BUILDTECH PRIVATE LIMITED | 26/07/2023 |
| CC006000000209733 | Avinash Pahuja | Real Gem Buildtech Private Limited | 27/01/2022 |
| CC006000000209717 | Ravish Mahesh Pahuja | Real Gem Buildtech Private Limited & Anr. | 27/01/2022 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 16 Jan 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 29 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 11 Jan 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 25 Apr 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 25 Feb 2025
Documents filed194
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 194 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 5 (FY 2024-2025)File: Form 5 - Crown Wing A&B.pdf | 30 Sep 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: FORM 4 Architect Certificate Wing A and B.pdf | 25 Feb 2025 |
| Certificates of CA (Form 3)File: 2025 01 23 RG RGBTPL CROWN FORM 3- DEC 24 WING AB.pdf | 20 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 engineer certificate- Phase 1 - Dec 2024.pdf | 20 Feb 2025 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 Architect Certificate Wing A and B.pdf | 1 Feb 2025 |
| Certificates of CA (Form 3)File: 2024 10 20 RG RGBTPL CROWN AB FORM 3 SEPT 2024.pdf | 31 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 engineer certificate- Phase 1 - Sep'2024.pdf | 22 Oct 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 2445318_OC_signed.pdf | 17 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5-RGBPL - Crown Phase I Mar 24 Signed.pdf | 15 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 engineer certificate- Phase 1 - Jun'2024.pdf | 13 Aug 2024 |
| Certificates of CA (Form 3)File: 2024 07 20 RG RGBTPL CROWN RERA JUNE 2024 WING AB R1_11zon.pdf | 13 Aug 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: CC REVALIDATION LETTER VALID UPTO 17022025.pdf | 25 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 engineer certificate- Phase 1 - Mar'2024.pdf | 25 Apr 2024 |
| Certificates of CA (Form 3)File: fORM 3 RG RGBTPL CROWN RERA MAR 2024 WING AB.pdf | 25 Apr 2024 |
| Details of encumbrancesFile: Details of encumbrances - Crown Phase 1.pdf | 12 Apr 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: PART OC LETTER ( TOWER A 63RD FLOOR PART ).pdf | 12 Mar 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 2401103_OC_signed.pdf | 12 Mar 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 engineer certificate- Phase 1 - Dec'2023.pdf | 6 Mar 2024 |
| Certificates of CA (Form 3)File: 2024 01 20 RG RGBTPL RERA FORM 3 DEC 23 CROWN WING AB compressed.pdf | 6 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 7 - Form 5 FY 2022-23.pdf | 11 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 3 - FORM 1 wing A B up to December 2023.pdf | 10 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure.pdf | 26 Dec 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 engineer certificate- Phase 1 - Dec'2022.pdf | 17 Dec 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 engineer certificate- Phase 1 - Mar'2023.pdf | 17 Dec 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 engineer certificate- Phase 1 - Jun'2023 (1).pdf | 17 Dec 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 engineer certificate- Phase 1 - Sep'2023 (1).pdf | 17 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21).pdf | 14 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A- Engineer's Certificate for Quality Assurance - Phase 1 - FY 22-23.pdf | 14 Dec 2023 |
| Certificates of CA (Form 3)File: Form 3 Crown Phase I March 2023_11zon.pdf | 3 Dec 2023 |
| Certificates of CA (Form 3)File: Form 3 Crown Phase I June 2023.pdf | 3 Dec 2023 |
| Certificates of CA (Form 3)File: Form 3 Crown Phase I September 2023_11zon.pdf | 3 Dec 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20231019 FORM 1 PHASE I.pdf | 20 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20231019 FORM 1 PHASE II.pdf | 20 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Signed Form 5 RGBPL Crown Phase I Mar 23 compressed.pdf | 30 Sep 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 2354058 OC signed.pdf | 9 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20221231 Phase I.pdf | 22 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20230331 FORM 1.pdf | 22 May 2023 |
| Certificates of CA (Form 5)File: 20221231 FORM P1.pdf | 22 May 2023 |
| Certificates of CA (Form 5)File: 20221231 FORM P2.pdf | 22 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20210930 FORM 1.pdf | 9 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20211231 FORM 1.pdf | 9 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20220630 FORM 1.pdf | 9 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20220930 FORM 1.pdf | 9 May 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Phase-1 Panora March'20.pdf | 9 May 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Enginner Certificate Mar'2021 - Phase 1.pdf | 9 May 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Enginner Certificate Sep'2021 - Phase 1.pdf | 9 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 MAHA RERA FORM 1 wing A B 26102018.pdf | 31 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20181231 FORM 1.pdf | 31 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20190331 FORM 1.pdf | 31 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20190630 FORM 1.pdf | 31 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20190930 FORM 1.pdf | 31 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20191231 FORM 1.pdf | 31 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20200331 FORM 1.pdf | 31 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20200630 FORM 1.pdf | 31 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20200930 FORM 1.pdf | 31 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20201231 FORM 1.pdf | 31 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20210331 FORM 1.pdf | 31 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: MAHA RERA FORM 1 Architect Certificate wing A B up to 30092022.pdf | 10 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: MAHA RERA FORM 1 Architect Certificate wing A B up to 30062022.pdf | 10 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: MAHA RERA FORM 1 Architect Certificate wing A B up to 25092021.pdf | 10 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: MAHA RERA FORM 1 Architect Certificate wing A B up to 30122021.pdf | 10 Feb 2023 |
| Certificates of CA (Form 3)File: 20220331 FORM 3 P1.pdf | 11 Jan 2023 |
| Certificates of CA (Form 3)File: 20220331 FORM 3 P2.pdf | 11 Jan 2023 |
| Certificates of CA (Form 3)File: 20220331 FORM 3 P3.pdf | 11 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20221231 Phase I.pdf | 10 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 engineer certificate- Phase 1 - Sep'2022.pdf | 29 Dec 2022 |
| Certificates of CA (Form 3)File: 01.pdf | 29 Dec 2022 |
| Certificates of CA (Form 3)File: 02.pdf | 29 Dec 2022 |
| Certificates of CA (Form 3)File: 03.pdf | 29 Dec 2022 |
| Certificates of CA (Form 3)File: 04.pdf | 29 Dec 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.pdf | 29 Dec 2022 |
| Certificates of CA (Form 5)File: Form 5 CROWN PHASE I.pdf | 30 Sep 2022 |
| CERSAI detailsFile: Cersai Report.pdf | 8 Sep 2022 |
| Details of encumbrancesFile: 20220616 Encumbrance Certificate.pdf | 10 Aug 2022 |
| Details of encumbrancesFile: 20220112 Crown Encumbrances Certificate.pdf | 14 Jul 2022 |
| Details of encumbrancesFile: 20220614 Crown Encumbrances Certificate.pdf | 14 Jul 2022 |
| CERSAI detailsFile: CERSAI Search Report.pdf | 2 Jul 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 202203 Phase I architect certificate_compressed.pdf | 21 May 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 202203 Crown Phase I form 2A.pdf | 21 May 2022 |
| Details of encumbrancesFile: 20211224 Encumbrance Certificate.pdf | 4 Apr 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 6 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 194 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep RUSTOMJEE CROWN - PHASE I on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near prabhadevi
Filed coordinates, straight-line distance. 27 registered projects within 2 km.
RUSTOMJEE CROWN -PHASE II
REAL GEM BUILDTECH PRIVATE LIMITED
Lodha Worli Residential Project
Lodha Developers Limited
Twenty Five South - North Tower
Twenty Five South Realty Limited
ARTESIA - RESIDENTIAL WING CONSTRUCTED ON PART
K RAHEJA PRIVATE LIMITED
Lotus Aquaria
SRI LOTUS DEVELOPERS AND REALTY LTD.
The V Mansion
ROOF ABOVE REALTORS LLP
Builder: Realgem Buildtech Private Limited
Realgem Buildtech Private Limited has 1 registration on MahaRERA, including RUSTOMJEE CROWN - PHASE I. Its filings disclose no earlier MahaRERA projects. Read the full track record.
Frequently asked questions
What does it mean that RUSTOMJEE CROWN - PHASE I shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if RUSTOMJEE CROWN - PHASE I is delayed beyond 30 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of RUSTOMJEE CROWN - PHASE I?
The registered promoter entity is Realgem Buildtech Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in RUSTOMJEE CROWN - PHASE I?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against RUSTOMJEE CROWN - PHASE I?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for RUSTOMJEE CROWN - PHASE I?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at RUSTOMJEE CROWN - PHASE I?
The professionals named in the filing: Chartered Accountant: V A Shimpi and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in RUSTOMJEE CROWN - PHASE I?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback