Home / Browse projects / Ruparel Ariana
Ruparel Ariana
By SHREE SUKHAKARTA DEVELOPERS PVT.LTD.
RG-MH-09470 · RERA P51900003250 · Last updated on MahaRERA portal: 23 Oct 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 34 months past the filed date
- Litigation declared, 1 case
- 30 complaints at MahaRERA
- Completion date moved by 12 months
- 1 extension taken
Clear
- Separate project account declared
- Allotment letter follows the model form
6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Ruparel Ariana is a Residential / Group Housing project by SHREE SUKHAKARTA DEVELOPERS PVT.LTD. in Parel, 400015, registered with MahaRERA as P51900003250 on 5 Aug 2017. Possession was promised by 30 Dec 2023 and is now 34 months past that date. The completion date has moved by 12 months from the original filing. 30 complaints are on record with the regulator.
At a glance
Project
- NameRuparel Ariana
- TypeResidential / Group Housing
- Location
- Jerbai Wadia Raod
- Parel
- 400015
- Pincode400015
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51900003250
- ReraGenie IDRG-MH-09470
Builder
- NameSHREE SUKHAKARTA DEVELOPERS PVT.LTD.
- Entity typeCompany
- CINU45200MH2013PTC245154
- DirectorsAmit Ruparel, Parikshit Sharma, Pradeep Ahire
- Other registrations2 more →
- No longer live3 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on5 Aug 2017
- Promised completion30 Dec 2023
- Revised completionRevised to 30 Dec 2023 (originally 30 Dec 2022)
- Buildings2 building records
- Documents filed46 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Ruparel Ariana Ph I | NA | 84 | 0 | 0 | 0 | 0 |
| Ruparel Ariana Ph II | NA | 4 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 23 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
2 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 95%.
Ruparel Ariana Ph I86%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 95% |
| Podiums (if any) | 95% |
| Plinth | 95% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 89% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 89% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 89% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 30% |
Ruparel Ariana Ph II0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 23 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 50% |
| Water Supply | Yes | 50% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 50% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 50% |
| Solid Waste Management And Disposal | Yes | 50% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 50% |
| Electrical meter room, sub-station, receiving station | Yes | 50% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed386
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Mr Rahul Kamathi Kamathi |
| Engineer | Sanjeev Sinha |
| Chartered Accountant | Sarveshwar Sharma |
| Chartered Accountant | Shereena Jacob |
| Partner | Role in project |
|---|---|
| Shree Siddhivinayak Classic Construction pvt Ltd | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe, Shree Sukhakarta Developers Pvt. Ltd. (Promoters) would like to inform you that we have received height approval for our project Ruparel Ariana vide RERA Regn. No. P51900003250 on June 30, 2022. We had applied for the NOC from Ministry of Civil Aviation for the height the project on 04/02/2016. After verifying the plans documents and relevant details, we were granted initial NOC dated 07/06/2016 as per the GSR norms applicable for a height 211.76 mtr. Further on 29/12/2017 we again applied for the NOC to which were again granted interim NOC for height of 225.01mts. With changes in GSR norm
Litigation declared1
| Case | Court | Status |
|---|---|---|
| 755/2015 | Bombay City Civil Court | Disposed |
Complaints filed with MahaRERA30
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000089676 | MR. BHARAT KANTILAL JAIN & MRS. POONAM BHARAT JAIN | SHREE SUKHAKARTA DEVELOPERS PRIVATE LIMITED | 16/06/2019 |
| CC006000000089686 | MRS. RUXANA HANSOTIA AND MR. FREDY HANSOTIA | SHREE SUKHAKARTA DEVELOPERS PRIVATE LIMITED | 16/06/2019 |
| CC006000000110803 | MRS. SANGEETA BHUPESH JAIN AND MR. BHUPESH JAYANTILAL JAIN | SHREE SUKHAKARTA DEVELOPERS PRIVATE LIMITED | 17/09/2019 |
| CC006000000110805 | MR. DINESH JAIN, MRS HEMA DINESH JAIN, MR. MEHUL DINESH JAIN, MRS. SWEETY MEHUL JAIN | SHREE SUKHAKARTA DEVELOPERS PRIVATE LIMITED | 17/09/2019 |
| CC006000000054807 | SAURAV PURKAYASTHA | RUPAREL REALTY PRIVATE LIMITED ERSTWHILE KNOWN AS SHREE SUKHKARTA DEVELOPERS PRIVATE LIMITED | 07/06/2018 |
| CC006000000055883 | Eshaan Desai | Shree SukhakartaDevelopers Ltd | 21/08/2018 |
| CC006000000056091 | MAHENDRA JAIN | SHREE SUKHAKARTA DEVELOPES PVT. LTD | 08/10/2018 |
| CC006000000161289 | DHIRAJ JAIN | SHREE SUKHAKARTA DEVELOPERS PVT. LTD | 20/10/2019 |
| CC006000000089956 | ANITA SARMAH | Shree Sukhakarta Developers PVT LTD | 03/07/2019 |
| CC006000000100454 | MAHENDRA JAIN | Shree Sukhakarta Developers Pvt. Ltd | 08/08/2019 |
| CC006000000171501 | Takhatsinh Rana | Shree Sukhakarta Developers Pvt. Ltd. | 12/11/2019 |
| CC006000000192319 | Pushpa Rakesh Agarwal | Shree Sukhakarta Developers Private Limited | 27/01/2020 |
| CC006000000195542 | Pushpa Rakesh Agarwal | The Sukhakarta Developers Pvt. Limited | 19/01/2021 |
| CC006000000192612 | MOHD PRAVEZ PATEL | SHREE SUKHKARTA DEVELOPERS PVT LTD | 15/02/2020 |
| CC006000000192747 | MR. BHARAT KANTILAL JAIN AND MRS.POONAM BHARAT JAIN | SHREE SUKHAKARTA DEVELOPERS PRIVATE LIMITED | 13/03/2020 |
| CC006000000193029 | MRS. SANGEETA BHUPESH JAIN AND MR. BHUPESH JAYANTILAL JAIN | SHREE SUKHAKARTA DEVELOPERS PRIVATE LIMITED | 23/03/2020 |
| CC006000000193030 | MR. DINESH JAIN , MRS. HEMA DINESH JAIN, MR. MEHUL DINESH JAIN AND MRS. SWEETY MEHUL JAIN | SHREE SUKHAKARTA DEVELOPERS PRIVATE LIMITED | 23/03/2020 |
| CC006000000195686 | Aditya Gupta and Suparna Sethi | Shree Sukhtara Developers Pvt. Ltd. | 19/01/2021 |
| CC006000000196762 | Mrs.Maharukh Khushrow Patel and Ors | Shree Sukhakarta DEvelopers Private Limited | 11/11/2021 |
| CC006000000197616 | Amisha and Ketan Patel | Shree Sukhakarta Developers Private Limited through its Director Amit M. Ruparel&Parikshit M. Sharma | 22/07/2021 |
| CC006000000056540 | SUNIL AGARWAL | K.D. Lite Developers and Ruparel Estate Pvt. Ltd. and Shree Sukhakarta Developers Pvt. Ltd. | 12/10/2018 |
| CC006000000292459 | Paras Jaikumar Jain | M/S. SHREE SUKHAKARTA DEVELOPERS | 25/08/2022 |
| CC006000000292831 | SELVEL PUBLICITY AND CONSULTANTS PVT LTD | SHREE SUKHAKARTA DEVELOPERS PRIVATE LIMITED | 27/09/2022 |
| CC006000000303341 | HEMANT DHARMAJI KAMBLI | SHREE SUKHAKARTA DEVELOPERS PVT LIMITED | 16/11/2022 |
| CC006000000374961 | Jigar Kedia | Shree Sukhakarta Developers Pvt. Ltd. | 26/03/2023 |
| CC006000000375094 | Jigar Kedia | Shree Sukhakarta Developers Pvt. Ltd. | 04/04/2023 |
| CC006000000395588 | Sameer Anant Kanekar | Shree Sukhakarta Developers Pvt Ltd | 08/05/2023 |
| CC006000000396461 | KISHOR SAVLA | Shree Sukhakarta Developers Pvt. Ltd. | 28/06/2023 |
| CC006000000397541 | Mahrukh Khushrow Patel | Shree Sukhhakarta Developers Pvt. Ltd. | 20/09/2023 |
| CC12501392 | HT MEDIA LIMITED | SHREE SUKHAKARTA DEVELOPERS PVT.LTD. | 26/04/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 15 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 5 Feb 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 7 Feb 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 29 Jun 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 7 Sep 2021
Documents filed46
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Deviation Report with respect to Allotment letterFile: Deviation Report with respect to Allotment letter _Ariana_Final.pdf | 23 Oct 2024 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Report AFS -01-10-2024_Ariana_Final.pdf | 23 Oct 2024 |
| Proforma of Agreement for saleFile: 10 Proforma AFS_Ariana.pdf | 23 Oct 2024 |
| Details of encumbrances concerned to FinanceFile: 1 Shree Sukhkarta Developer Legal Financial Encumbrance_Ariana_Final.pdf | 22 Oct 2024 |
| Declaration in FORM BFile: Form B Affidavit cum Declaration Ruparel Ariana Final.pdf | 22 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Architect certificate - Ariana as on 30-09-24.pdf | 22 Oct 2024 |
| Declaration about Commencement CertificateFile: 2 Format D - Declaration aboubt CC - Ruparel Ariana Final.pdf | 22 Oct 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: 4 Format A - Declaration about RERA Designated Bank Accounts_Ariana_Final.pdf | 22 Oct 2024 |
| Details of encumbrances concerned to LegalFile: 1 Shree Sukhkarta Developer Legal Financial Encumbrance_Ariana_Final.pdf | 22 Oct 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: 3 Disclosure of Interest in other organisation Ruparel Ariana Final.pdf | 22 Oct 2024 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B - Letter from Kotak bank - Rera Designated bank accounts.pdf | 21 Oct 2024 |
| CERSAI detailsFile: CERSAI REPORT RUPAREL ARIANA.pdf | 4 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Ariana 2019-20.pdf | 24 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Ariana 2020-21.pdf | 24 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Ariana 2021-22.pdf | 24 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Ruparel Ariana March-2020.pdf | 20 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Ruparel Ariana March- 2021.pdf | 20 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Ruparel Ariana March-2022.pdf | 20 Jan 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Ariana-Part OC upto 45th Floor.pdf | 7 Sep 2021 |
| Proforma of Allotment letterFile: Ariana.pdf | 2 Aug 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: Ariana CC.pdf | 29 Jun 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Ariana.pdf | 2 Jan 2020 |
| Building plan approvalFile: Ariana Amended Ioa.pdf | 7 Feb 2019 |
| Building Plan Approval (IOD)File: Ariana Amended Ioa.pdf | 7 Feb 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: Ariana Amended CC 2019.pdf | 7 Feb 2019 |
| Layout approvalFile: Layout New.pdf | 5 Feb 2019 |
| Copy of Layout Approval (in case of layout)File: Layout New.pdf | 5 Feb 2019 |
| Certificates of CA (Form 5)File: Ariana.pdf | 31 Dec 2018 |
| Declaration in FORM BFile: Encumbrances - Oct 2018.pdf | 12 Oct 2018 |
| Declaration in FORM BFile: Form B Ariana-2018 Final.pdf | 8 Oct 2018 |
| Details of encumbrancesFile: form b Affidavit cum Declaration- 2018.pdf | 5 Oct 2018 |
| Declaration in FORM BFile: form b Affidavit cum Declaration- 2018.pdf | 5 Oct 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: Ariana CC.pdf | 7 Apr 2018 |
| Layout approvalFile: ARIANA Layout Plan.pdf | 29 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: ARIANA Layout Plan.pdf | 29 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EC Ariana.pdf | 29 Jul 2017 |
| Certificates of CA (Form 3)File: Ariana CA.pdf | 29 Jul 2017 |
| Details of encumbrancesFile: SSDPL Ariana.pdf | 28 Jul 2017 |
| Declaration in FORM BFile: Form B - Ariana.pdf | 28 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ariana.pdf | 28 Jul 2017 |
| Proforma of Allotment letterFile: Ruparel Ariana-RERA Agreeement.pdf | 23 Jul 2017 |
| Copy of the legal title reportFile: Title Certificate.pdf | 15 Jul 2017 |
| Building plan approvalFile: Ariana IOA.pdf | 9 Jul 2017 |
| PAN CardFile: SSDPL PAN.pdf | 9 Jul 2017 |
| Building Plan Approval (IOD)File: Ariana IOA.pdf | 9 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: Ariana CC.pdf | 9 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 6 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 46 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Ruparel Ariana on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Parel
Filed coordinates, straight-line distance. 16 registered projects within 2 km.
The Gateway
LH Residential Housing Private Limited
Lodha Sewri Project
Lodha Developers Limited
SOBHA Inizio
SOBHA LIMITED
THE CANVAS RESIDENCES - CANVAS 1, CANVAS 2, CA
COVENTRY PROPERTIES PRIVATE LIMITED
Avenue 15
Ramesh Barrel Supplying Co
AQUA BAY
CHAMUNDA INFRASTRUCTURE LIMITED
Builder: SHREE SUKHAKARTA DEVELOPERS PVT.LTD.
SHREE SUKHAKARTA DEVELOPERS PVT.LTD. has 3 registrations on MahaRERA, including Ruparel Ariana and Ruparel Elavia. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record.
Frequently asked questions
What does it mean that Ruparel Ariana shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Ruparel Ariana is delayed beyond 30 Dec 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Ruparel Ariana?
The registered promoter entity is SHREE SUKHAKARTA DEVELOPERS PVT.LTD., a company as per the filing. Its CIN U45200MH2013PTC245154 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Ruparel Ariana?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Ruparel Ariana?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Ruparel Ariana?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Ruparel Ariana?
The professionals named in the filing: Architect: Mr Rahul Kamathi Kamathi; Engineer: Sanjeev Sinha; Chartered Accountant: Sarveshwar Sharma; Chartered Accountant: Shereena Jacob. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Ruparel Ariana?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback