ReraGenieLog inGet a buyer report

Home / Browse projects / Ruparel Ariana

Registration lapsed Litigation declared Residential / Group Housing project

Ruparel Ariana

By SHREE SUKHAKARTA DEVELOPERS PVT.LTD.

RG-MH-09470 · RERA P51900003250 · Last updated on MahaRERA portal: 23 Oct 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 34 months past the filed date
  • Litigation declared, 1 case
  • 30 complaints at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Separate project account declared
  • Allotment letter follows the model form

6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Dec 2023Possession promised34 months past this date
2 of 22Construction stages doneacross 2 buildings; furthest along: Basement (if any), 95%
30Complaints at MahaRERAon this registration
Jump to the 46 documents Report an error

Ruparel Ariana is a Residential / Group Housing project by SHREE SUKHAKARTA DEVELOPERS PVT.LTD. in Parel, 400015, registered with MahaRERA as P51900003250 on 5 Aug 2017. Possession was promised by 30 Dec 2023 and is now 34 months past that date. The completion date has moved by 12 months from the original filing. 30 complaints are on record with the regulator.

At a glance

Project

  • NameRuparel Ariana
  • TypeResidential / Group Housing
  • Location
    • Jerbai Wadia Raod
    • Parel
    • 400015
  • Pincode400015
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900003250
  • ReraGenie IDRG-MH-09470

Builder

  • NameSHREE SUKHAKARTA DEVELOPERS PVT.LTD.
  • Entity typeCompany
  • CINU45200MH2013PTC245154
  • DirectorsAmit Ruparel, Parikshit Sharma, Pradeep Ahire
  • Other registrations2 more →
  • No longer live3 lapsed, de-registered or revoked

Key dates

34 months past promisethis monthRegisteredAug 2017First promiseDec 2022Revised toDec 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on5 Aug 2017
  • Promised completion30 Dec 2023
  • Revised completionRevised to 30 Dec 2023 (originally 30 Dec 2022)
  • Buildings2 building records
  • Documents filed46 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Ruparel Ariana Ph INA840000
Ruparel Ariana Ph IINA40000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 23 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 95%.

Ruparel Ariana Ph I86%
ActivityProgress
Excavation100%
Basement (if any)95%
Podiums (if any)95%
Plinth95%
Stilt Floor100%
Slabs of Super Structure89%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises89%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks89%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%
Ruparel Ariana Ph II0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 23 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes50%
Solid Waste Management And DisposalYes50%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed386

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots386
Closed/Covered386

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area12,644 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authoritySlum Rehabilitation Authority
Permissible FSI28234.35
Proposed, not sanctioned26,390 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchThane

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr Rahul Kamathi Kamathi
EngineerSanjeev Sinha
Chartered AccountantSarveshwar Sharma
Chartered AccountantShereena Jacob
PartnerRole in project
Shree Siddhivinayak Classic Construction pvt Ltd-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900013789Dec 2022 → Dec 2023

Reason as filed by the promoterWe, Shree Sukhakarta Developers Pvt. Ltd. (Promoters) would like to inform you that we have received height approval for our project Ruparel Ariana vide RERA Regn. No. P51900003250 on June 30, 2022. We had applied for the NOC from Ministry of Civil Aviation for the height the project on 04/02/2016. After verifying the plans documents and relevant details, we were granted initial NOC dated 07/06/2016 as per the GSR norms applicable for a height 211.76 mtr. Further on 29/12/2017 we again applied for the NOC to which were again granted interim NOC for height of 225.01mts. With changes in GSR norm

Litigation declared1

CaseCourtStatus
755/2015Bombay City Civil CourtDisposed

Complaints filed with MahaRERA30

Case no.ComplainantRespondentFiled
CC006000000089676MR. BHARAT KANTILAL JAIN & MRS. POONAM BHARAT JAINSHREE SUKHAKARTA DEVELOPERS PRIVATE LIMITED16/06/2019
CC006000000089686MRS. RUXANA HANSOTIA AND MR. FREDY HANSOTIASHREE SUKHAKARTA DEVELOPERS PRIVATE LIMITED16/06/2019
CC006000000110803MRS. SANGEETA BHUPESH JAIN AND MR. BHUPESH JAYANTILAL JAINSHREE SUKHAKARTA DEVELOPERS PRIVATE LIMITED17/09/2019
CC006000000110805MR. DINESH JAIN, MRS HEMA DINESH JAIN, MR. MEHUL DINESH JAIN, MRS. SWEETY MEHUL JAINSHREE SUKHAKARTA DEVELOPERS PRIVATE LIMITED17/09/2019
CC006000000054807SAURAV PURKAYASTHARUPAREL REALTY PRIVATE LIMITED ERSTWHILE KNOWN AS SHREE SUKHKARTA DEVELOPERS PRIVATE LIMITED07/06/2018
CC006000000055883Eshaan DesaiShree SukhakartaDevelopers Ltd21/08/2018
CC006000000056091MAHENDRA JAINSHREE SUKHAKARTA DEVELOPES PVT. LTD08/10/2018
CC006000000161289DHIRAJ JAINSHREE SUKHAKARTA DEVELOPERS PVT. LTD20/10/2019
CC006000000089956ANITA SARMAHShree Sukhakarta Developers PVT LTD03/07/2019
CC006000000100454MAHENDRA JAINShree Sukhakarta Developers Pvt. Ltd08/08/2019
CC006000000171501Takhatsinh RanaShree Sukhakarta Developers Pvt. Ltd.12/11/2019
CC006000000192319Pushpa Rakesh AgarwalShree Sukhakarta Developers Private Limited27/01/2020
CC006000000195542Pushpa Rakesh AgarwalThe Sukhakarta Developers Pvt. Limited19/01/2021
CC006000000192612MOHD PRAVEZ PATELSHREE SUKHKARTA DEVELOPERS PVT LTD15/02/2020
CC006000000192747MR. BHARAT KANTILAL JAIN AND MRS.POONAM BHARAT JAINSHREE SUKHAKARTA DEVELOPERS PRIVATE LIMITED13/03/2020
CC006000000193029MRS. SANGEETA BHUPESH JAIN AND MR. BHUPESH JAYANTILAL JAINSHREE SUKHAKARTA DEVELOPERS PRIVATE LIMITED23/03/2020
CC006000000193030MR. DINESH JAIN , MRS. HEMA DINESH JAIN, MR. MEHUL DINESH JAIN AND MRS. SWEETY MEHUL JAINSHREE SUKHAKARTA DEVELOPERS PRIVATE LIMITED23/03/2020
CC006000000195686Aditya Gupta and Suparna SethiShree Sukhtara Developers Pvt. Ltd.19/01/2021
CC006000000196762Mrs.Maharukh Khushrow Patel and OrsShree Sukhakarta DEvelopers Private Limited11/11/2021
CC006000000197616Amisha and Ketan PatelShree Sukhakarta Developers Private Limited through its Director Amit M. Ruparel&Parikshit M. Sharma22/07/2021
CC006000000056540SUNIL AGARWALK.D. Lite Developers and Ruparel Estate Pvt. Ltd. and Shree Sukhakarta Developers Pvt. Ltd.12/10/2018
CC006000000292459Paras Jaikumar JainM/S. SHREE SUKHAKARTA DEVELOPERS25/08/2022
CC006000000292831SELVEL PUBLICITY AND CONSULTANTS PVT LTDSHREE SUKHAKARTA DEVELOPERS PRIVATE LIMITED27/09/2022
CC006000000303341HEMANT DHARMAJI KAMBLISHREE SUKHAKARTA DEVELOPERS PVT LIMITED16/11/2022
CC006000000374961Jigar KediaShree Sukhakarta Developers Pvt. Ltd.26/03/2023
CC006000000375094Jigar KediaShree Sukhakarta Developers Pvt. Ltd.04/04/2023
CC006000000395588Sameer Anant KanekarShree Sukhakarta Developers Pvt Ltd08/05/2023
CC006000000396461KISHOR SAVLAShree Sukhakarta Developers Pvt. Ltd.28/06/2023
CC006000000397541Mahrukh Khushrow PatelShree Sukhhakarta Developers Pvt. Ltd.20/09/2023
CC12501392HT MEDIA LIMITEDSHREE SUKHAKARTA DEVELOPERS PVT.LTD.26/04/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 15 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 5 Feb 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 7 Feb 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Jun 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 7 Sep 2021

Documents filed46

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Deviation Report with respect to Allotment letterFile: Deviation Report with respect to Allotment letter _Ariana_Final.pdf23 Oct 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Report AFS -01-10-2024_Ariana_Final.pdf23 Oct 2024
Proforma of Agreement for saleFile: 10 Proforma AFS_Ariana.pdf23 Oct 2024
Details of encumbrances concerned to FinanceFile: 1 Shree Sukhkarta Developer Legal Financial Encumbrance_Ariana_Final.pdf22 Oct 2024
Declaration in FORM BFile: Form B Affidavit cum Declaration Ruparel Ariana Final.pdf22 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Architect certificate - Ariana as on 30-09-24.pdf22 Oct 2024
Declaration about Commencement CertificateFile: 2 Format D - Declaration aboubt CC - Ruparel Ariana Final.pdf22 Oct 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: 4 Format A - Declaration about RERA Designated Bank Accounts_Ariana_Final.pdf22 Oct 2024
Details of encumbrances concerned to LegalFile: 1 Shree Sukhkarta Developer Legal Financial Encumbrance_Ariana_Final.pdf22 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: 3 Disclosure of Interest in other organisation Ruparel Ariana Final.pdf22 Oct 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B - Letter from Kotak bank - Rera Designated bank accounts.pdf21 Oct 2024
CERSAI detailsFile: CERSAI REPORT RUPAREL ARIANA.pdf4 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Ariana 2019-20.pdf24 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Ariana 2020-21.pdf24 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Ariana 2021-22.pdf24 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Ruparel Ariana March-2020.pdf20 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Ruparel Ariana March- 2021.pdf20 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Ruparel Ariana March-2022.pdf20 Jan 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Ariana-Part OC upto 45th Floor.pdf7 Sep 2021
Proforma of Allotment letterFile: Ariana.pdf2 Aug 2021
Commencement Certificates / NA Order for plotted developmentFile: Ariana CC.pdf29 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Ariana.pdf2 Jan 2020
Building plan approvalFile: Ariana Amended Ioa.pdf7 Feb 2019
Building Plan Approval (IOD)File: Ariana Amended Ioa.pdf7 Feb 2019
Commencement Certificates / NA Order for plotted developmentFile: Ariana Amended CC 2019.pdf7 Feb 2019
Layout approvalFile: Layout New.pdf5 Feb 2019
Copy of Layout Approval (in case of layout)File: Layout New.pdf5 Feb 2019
Certificates of CA (Form 5)File: Ariana.pdf31 Dec 2018
Declaration in FORM BFile: Encumbrances - Oct 2018.pdf12 Oct 2018
Declaration in FORM BFile: Form B Ariana-2018 Final.pdf8 Oct 2018
Details of encumbrancesFile: form b Affidavit cum Declaration- 2018.pdf5 Oct 2018
Declaration in FORM BFile: form b Affidavit cum Declaration- 2018.pdf5 Oct 2018
Commencement Certificates / NA Order for plotted developmentFile: Ariana CC.pdf7 Apr 2018
Layout approvalFile: ARIANA Layout Plan.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: ARIANA Layout Plan.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EC Ariana.pdf29 Jul 2017
Certificates of CA (Form 3)File: Ariana CA.pdf29 Jul 2017
Details of encumbrancesFile: SSDPL Ariana.pdf28 Jul 2017
Declaration in FORM BFile: Form B - Ariana.pdf28 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ariana.pdf28 Jul 2017
Proforma of Allotment letterFile: Ruparel Ariana-RERA Agreeement.pdf23 Jul 2017
Copy of the legal title reportFile: Title Certificate.pdf15 Jul 2017
Building plan approvalFile: Ariana IOA.pdf9 Jul 2017
PAN CardFile: SSDPL PAN.pdf9 Jul 2017
Building Plan Approval (IOD)File: Ariana IOA.pdf9 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Ariana CC.pdf9 Jul 2017

Keep Ruparel Ariana on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Parel

2 kmRuparel ArianaCompleted 5Lapsed / revoked 5Other 6Dot size: filed unitsN

Filed coordinates, straight-line distance. 16 registered projects within 2 km.

Builder: SHREE SUKHAKARTA DEVELOPERS PVT.LTD.

SHREE SUKHAKARTA DEVELOPERS PVT.LTD. has 3 registrations on MahaRERA, including Ruparel Ariana and Ruparel Elavia. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record.

Frequently asked questions

What does it mean that Ruparel Ariana shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Ruparel Ariana is delayed beyond 30 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Ruparel Ariana?

The registered promoter entity is SHREE SUKHAKARTA DEVELOPERS PVT.LTD., a company as per the filing. Its CIN U45200MH2013PTC245154 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Ruparel Ariana?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Ruparel Ariana?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Ruparel Ariana?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Ruparel Ariana?

The professionals named in the filing: Architect: Mr Rahul Kamathi Kamathi; Engineer: Sanjeev Sinha; Chartered Accountant: Sarveshwar Sharma; Chartered Accountant: Shereena Jacob. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Ruparel Ariana?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Ruparel Ariana. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Ruparel Ariana to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.