Red flags

  • Litigation declared, 7 cases
  • 2 complaints at MahaRERA
  • Completion date moved by 36 months
  • 1 extension taken

Clear

  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 36 months from the original
3 of 11Construction stages donefurthest along: Podiums (if any), 0%
15 of 16Units unsoldnot recorded sold or booked
2Complaints at MahaRERAon this registration
Jump to the 41 documents Report an error

RR Business Centre is a Commercial project by RIVER RESIDENCY DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100024063 on 17 Jan 2020. Possession is promised by 31 Dec 2027. The completion date has moved by 36 months from the original filing. 1 of the 16 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NameRR Business Centre
  • TypeCommercial
  • Location
    • DEHU ALANDI ROAD
    • MOSHI
    • Haveli
    • Pune
    • 412114
  • Pincode412114
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100024063
  • ReraGenie IDRG-MH-15305

Builder

  • NameRIVER RESIDENCY DEVELOPERS
  • Entity typeOthers
  • Named personsANAND NAVRATAN JAIN, ISHWAR CHANDULAL PARMAR, TRADE CENTRE DEVELOPERS AND BUILDERS PRIVATE LIMITED, ISHWAR CONSTRUCTIONS PRIVATE LIMITED
  • Other registrations2 more →
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects7 →

Key dates

this monthRegisteredJan 2020First promiseDec 2024Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on17 Jan 2020
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 30 Dec 2024)
  • Buildings1 building record
  • Documents filed41 files

Current status

6%1 of 16 units booked

Figures as on 30 May 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
RR BUSINESS CENTRENA2201616

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 30 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

RR BUSINESS CENTRE: 27% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities17

As on 30 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
Generator Backup for Lifts and common lightsYes0%
Fire Fighting systems CommonYes0%

Parking filed6

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots6
Closed/Covered6

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,000 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on28 May 2025
LandownerVillageDistrict
VIJAYALAXMI ALIAS VIJAYLAXMI DEVELOPERSMumbai CityMumbai City
DILIP MOTILAL CHORDIAPimpri Chinchawad (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI1631.54
Proposed, not sanctioned927 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch9-2 Kalpataru Gardens Boat Club Road Pune Maharashtra 411001

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVIKAS ACHALKAR MANOJ TATOOSKAR
EngineerPramod Bhalerao
Chartered AccountantRSMS & Associates
Chartered AccountantYogesh Mali
PartnerRole in project
RIVER RESIDENCY DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100024507Dec 2024 → Dec 2027

Reason as filed by the promoterWe are applying for Extension without Majority Consents Under Order No. 40

Litigation declared7

CaseCourtStatus
MA/31/2023 /2023District CourtOngoing
362/2023/2023EOWOngoing
33787/2023High CourtOngoing
2709138007402020/2022NCLTOngoing
1001/2022/2033/2022/2022JDROngoing
3786/13/23/2022/3219/2022Human RightsOngoing
60000000098/2023SARFAESIOngoing

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC005000000167507RIVER RESIDENCY OWNERS ASSOCIATIONRIVER RESIDENCY DEVELOPERS03/09/2022
CC005000000208214M/s Vijayalaxmi Developers & AnrRiver Residency Developers AOP01/02/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Jan 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Jan 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Jan 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Jan 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed41

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1 March -25.pdf30 May 2025
Form 2File: Form 2 March-25.pdf30 May 2025
Form 3File: FORM 3 RRBUS APR25.pdf30 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Art RRBUS sep 24 (1).pdf29 Oct 2024
Disclosure of sold/ booked inventoryFile: Cir 29 - Sept 2024 -RRBC.pdf21 Oct 2024
Details of encumbrances concerned to FinanceFile: Encumbrance Letter - Legal.pdf16 Oct 2024
Details of encumbrancesFile: Encumbrance Letter - FINANCE.pdf16 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RRBC Form 1 March 2024.pdf16 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RRBC Form 1 June 2024.pdf16 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 March 2024 RRbusiness.pdf16 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 RRBC SEP-24.pdf16 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dec 2023.pdf16 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 March 2024.pdf16 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 June 2024.pdf16 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sept 2024.pdf16 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A RRBC 2019-20.pdf16 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: RRBC Form 5 2020-21.pdf16 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A RRBC 2020-21.pdf16 Oct 2024
Declaration about Commencement CertificateFile: Format D.pdf16 Oct 2024
CERSAI detailsFile: Declaration of CERSAI.pdf16 Oct 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf16 Oct 2024
Details of encumbrances concerned to LegalFile: Encumbrance Letter - Legal.pdf16 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: RRBC Form 5 2021-22.pdf16 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A RRBC 2021-22.pdf16 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf16 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A RRBC 2022-23.pdf16 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: RRBC Form 5 2022-23.pdf16 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A RRBC 2023-24.pdf16 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RRBC Form 5 2023-24.pdf16 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: RR Business Form 5.pdf21 Sep 2022
Layout approvalFile: 4 RRBC Layout.pdf10 Jan 2020
Building plan approvalFile: 4 RRBC Layout.pdf10 Jan 2020
PAN CardFile: PAN CARD RR.pdf10 Jan 2020
Copy of the legal title reportFile: Legal Search title report_compressed.pdf10 Jan 2020
Details of encumbrancesFile: 3 Declaration_Encumbrance.pdf10 Jan 2020
Copy of Layout Approval (in case of layout)File: 4 RRBC Layout.pdf10 Jan 2020
Building Plan Approval / NA Order for plotted developmentFile: 4 RRBC Layout.pdf10 Jan 2020
Commencement Certificates / NA Order for plotted developmentFile: 6 RRBC_Commencement certificate.pdf10 Jan 2020
Declaration in FORM BFile: 7 Form B_compressed.pdf10 Jan 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 11 Form 3 RRBC_compressed.pdf10 Jan 2020
Proforma of Allotment letterFile: 14 Agreement to sale declaration.pdf10 Jan 2020

Promoter's earlier projects5

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered late2 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
RIVER RESIDENCY PHASE IV BUILDING N4P52100012745MOSHI, Pune94Sep 2017OngoingAug 2023Not delivered
RIVER RESIDENCY PHASE IV BUILDING SP52100015059MOSHI, Pune94Jan 2018OngoingJan 2023Not delivered
RIVER RESIDENCY PHASE IIIGAT NO 90 CHIKHALI TAL HAVELI DIST-PUNE466-CompletedDec 2016Late, Jan 2017
RIVER RESIDENCY PHASE IIGAT NO 90 CHIKHALI TAL HAVELI DIST-PUNE470-CompletedJul 2014Late, Nov 2015
RIVER RESIDENCY PHASE IGAT NO 90 CHIKHALI TAL HAVELI DIST-PUNE896-CompletedFeb 2013Late, Mar 2014

How this compares with Pune

6%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 36 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep RR Business Centre on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MOSHI13,700+ in Pune

2 kmRR Business CentreCompleted 61Lapsed / revoked 39Other 65Dot size: filed unitsN

Filed coordinates, straight-line distance. 165 registered projects within 2 km.

Builder: RIVER RESIDENCY DEVELOPERS

RIVER RESIDENCY DEVELOPERS has 3 registrations on MahaRERA, including RIVER RESIDENCY PHASE IV BUILDING N4 and RIVER RESIDENCY PHASE IV BUILDING S. Its filings disclose 7 earlier MahaRERA projects: declares 0 of 5 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if RR Business Centre is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of RR Business Centre?

The registered promoter entity is RIVER RESIDENCY DEVELOPERS, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in RR Business Centre?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against RR Business Centre?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for RR Business Centre?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at RR Business Centre?

The professionals named in the filing: Architect: VIKAS ACHALKAR MANOJ TATOOSKAR; Engineer: Pramod Bhalerao; Chartered Accountant: RSMS & Associates; Chartered Accountant: Yogesh Mali. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RR Business Centre?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RR Business Centre. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RR Business Centre to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.