RIVER RESIDENCY DEVELOPERS: RERA track record

Others ยท attribution by exact filing name, entity resolution in progress

RIVER RESIDENCY DEVELOPERS has 3 registrations in this build, including RIVER RESIDENCY PHASE IV BUILDING N4 and RIVER RESIDENCY PHASE IV BUILDING S. Its filings disclose 7 earlier MahaRERA projects: 0 of 5 past projects completed on time. Litigation is declared on 2 of its registrations.

3Registrations in this build
7Past projects disclosed
+13 monthsMedian delivery slip
2Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
RIVER RESIDENCY PHASE IV BUILDING N4Pune, Maharashtra--Registered
RIVER RESIDENCY PHASE IV BUILDING SPune, Maharashtra--Registration lapsed
RR Business CentrePune, Maharashtra166%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
RIVER RESIDENCY PHASE I
26 Feb 201329 Mar 2014+13 months
RIVER RESIDENCY PHASE II
31 Jul 201426 Nov 2015+16 months
RIVER RESIDENCY PAHSE II
31 Jul 201426 Nov 2015+16 months
RIVER RESIDENCY PHASE III
31 Dec 201612 Jan 2017On time
RIVER RESIDENCY PAHSE III
31 Dec 201612 Jan 2017On time
RIVER RESIDENCY PHASE IV BUILDING S
P52100015059
4 Jan 2023Not completed yetOngoing
RIVER RESIDENCY PHASE IV BUILDING N4
P52100012745
28 Aug 2023Not completed yetOngoing

Frequently asked questions

How do I verify RIVER RESIDENCY DEVELOPERS as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with RIVER RESIDENCY DEVELOPERS?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

Does the declared litigation make RIVER RESIDENCY DEVELOPERS unsafe to buy from?

Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.