ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / GANESH PARADISE PHASE 2

Registered No litigation declared Others project

GANESH PARADISE PHASE 2

By EKDANTA NEST LLP

RG-MH-23096 · RERA P52100032681 · Last updated on MahaRERA portal: 20 Aug 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 6 other registrations.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedno revision filed
6 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 25%
73 of 288Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 120 documents Report an error

GANESH PARADISE PHASE 2 is a Others project by EKDANTA NEST LLP in Pune, Maharashtra, registered with MahaRERA as P52100032681 on 24 Jan 2022. Possession is promised by 31 Dec 2026. 215 of the 288 units on this registration are recorded sold or booked, and 6 of 22 construction stages are filed complete.

At a glance

Project

  • NameGANESH PARADISE PHASE 2
  • TypeOthers
  • Location
    • GAT NO 1602(P) 1603 1604(P)
    • CHIKHALI PUNE
    • Chikhali
    • Haveli
    • Pune
    • 412114
  • Pincode412114
  • RERA no.P52100032681
  • ReraGenie IDRG-MH-23096

Builder

  • NameEKDANTA NEST LLP
  • Entity typePartnership
  • PartnersSATISH BASWANT PATIL, AKASH SATISH PATIL
  • Other registrations6 more →
  • Completed2 of 7
  • No longer live3 lapsed, de-registered or revoked

Key dates

this monthRegisteredJan 2022PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on24 Jan 2022
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings2 building records
  • Documents filed120 files

Current status

75%215 of 288 units booked

Figures as on 20 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
GANESH PARADISE B WINGNA24181440144
GANESH PARADISE C WINGNA25181440144

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 20 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 25%.

GANESH PARADISE B WING48%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure25%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
GANESH PARADISE C WING9%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed57

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots57
Closed/Covered51
Open Space6
BuildingClosed/CoveredOpen SpaceTotal
GANESH PARADISE B WING50353
GANESH PARADISE C WING134

Land and ownership5

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,835 sq m
Land owned byThe promoter, with other names on the file
Named landowners5
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on28 Jul 2026
LandownerVillageDistrict
NIVRUTTI SHANKAR BHANGAREChikhaliPune
DNYANESHWAR BHANGAREChikhaliPune
BALASAHEB BHANGAREChikhaliPune
BAJIRAO BHANGAREChikhaliPune
BALU BABAN BHANGAREChikhaliPune

Approvals and building plan

Sanctioning authorityPCMC
Permissible FSI25141.5
Proposed, not sanctioned25,142 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNEAR KALASAGAR HOTEL PIMPRI PUNE

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectANURADHA GOVARDHAN
EngineerGAJANAN CHITTE
EngineerAVINASH ANDENAPPA GADAVE
Chartered AccountantGAUTAM SHARMA SHARMA
Chartered AccountantR S NILANGE & CO
Chartered AccountantA NEGI & COMPANY
Chartered AccountantJAGNENDU J MORE
PartnerRole in project
EKDANTA NEST LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Jan 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Jan 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Jan 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Jan 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed120

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 120 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: FORM 1 MAR 2022.pdf20 Aug 2026
Form 2File: FORM 2 MARCH 2022.pdf20 Aug 2026
Form 3File: FORM 3 MAR 22.pdf20 Aug 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD BOOKED MAR 22.pdf20 Aug 2026
Form 1File: FORM 1 SEP 2025.pdf20 Aug 2026
Form 2File: FORM 2 SEP 2025.pdf20 Aug 2026
Form 3File: FORM 3 SEP 25.pdf20 Aug 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD BOOKED SEP 25.pdf20 Aug 2026
Form 5 (FY 2021-2022)File: Certificate Form 5 - MAR 22.pdf20 Aug 2026
Form 5 (FY 2022-2023)File: Certificate Form 5 - MAR 23.pdf20 Aug 2026
Form 1File: FORM 1 JUN 2022.pdf19 Aug 2026
Form 2File: FORM 2 JUNE 2022.pdf19 Aug 2026
Form 3File: FORM 3 JUN 22.pdf19 Aug 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD BOOKED JUN 22.pdf19 Aug 2026
Form 1File: FORM 1 SEP 2022.pdf19 Aug 2026
Form 2File: FORM 2 SEP 2022.pdf19 Aug 2026
Form 3File: FORM 3 SEP 22.pdf19 Aug 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD BOOKED SEP 22.pdf19 Aug 2026
Form 1File: FORM 1 DEC 2022.pdf19 Aug 2026
Form 2File: FORM 2 DEC 2022.pdf19 Aug 2026
Form 3File: FORM 3 DEC 22.pdf19 Aug 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD BOOKED DEC 22.pdf19 Aug 2026
Form 1File: FORM 1 MAR 2023.pdf19 Aug 2026
Form 2File: FORM 2 MARCH 2023.pdf19 Aug 2026
Form 3File: FORM 3 MAR 23.pdf19 Aug 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD BOOKED MAR 23.pdf19 Aug 2026
Form 1File: FORM 1 JUN 2023.pdf19 Aug 2026
Form 2File: FORM 2 JUNE 2023.pdf19 Aug 2026
Form 3File: FORM 3 JUN 23.pdf19 Aug 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD BOOKED JUN 23.pdf19 Aug 2026
Form 1File: FORM 1 SEP 2023.pdf19 Aug 2026
Form 2File: FORM 2 SEP 2023.pdf19 Aug 2026
Form 3File: FORM 3 SEP 23.pdf19 Aug 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD BOOKED SEP 23.pdf19 Aug 2026
Form 1File: FORM 1 DEC 2023.pdf19 Aug 2026
Form 2File: FORM 2 DEC 2023.pdf19 Aug 2026
Form 3File: FORM 3 DEC 23.pdf19 Aug 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD BOOKED DEC 23.pdf19 Aug 2026
Form 1File: FORM 1 MAR 2024.pdf19 Aug 2026
Form 2File: FORM 2 MARCH 2024.pdf19 Aug 2026
Form 3File: FORM 3 MAR 24.pdf19 Aug 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD BOOKED MAR 24.pdf19 Aug 2026
Form 1File: FORM 1 JUN 2024.pdf19 Aug 2026
Form 2File: FORM 2 JUNE 2024.pdf19 Aug 2026
Form 3File: FORM 3 JUN 24.pdf19 Aug 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD BOOKED JUN 24.pdf19 Aug 2026
Form 1File: FORM 1 SEP 2024.pdf19 Aug 2026
Form 2File: FORM 2 SEP 2024.pdf19 Aug 2026
Form 3File: FORM 3 SEP 24.pdf19 Aug 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD BOOKED SEP 24.pdf19 Aug 2026
Form 1File: FORM 1 DEC 2024.pdf19 Aug 2026
Form 2File: FORM 2 DEC 2024.pdf19 Aug 2026
Form 3File: FORM 3 DEC 24.pdf19 Aug 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD BOOKED DEC 24.pdf19 Aug 2026
Form 1File: FORM 1 MAR 2025.pdf19 Aug 2026
Form 2File: FORM 2 MARCH 2025.pdf19 Aug 2026
Form 3File: FORM 3 MAR 25.pdf19 Aug 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD BOOKED MAR 25.pdf19 Aug 2026
Form 1File: FORM 1 JUN 2025.pdf19 Aug 2026
Form 2File: FORM 2 JUNE 2025.pdf19 Aug 2026
Form 3File: FORM 3 JUN 25.pdf19 Aug 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD BOOKED JUN 25.pdf19 Aug 2026
Form 1File: FORM 1 DEC 2025.pdf19 Aug 2026
Form 2File: FORM 2 DEC 2025.pdf19 Aug 2026
Form 3File: FORM 3 DEC 25.pdf19 Aug 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD BOOKED DEC 25.pdf19 Aug 2026
Form 1File: FORM 1 MAR 2026.pdf19 Aug 2026
Form 2File: FORM 2 MARCH 2026.pdf19 Aug 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD BOOKED MAR 26.pdf19 Aug 2026
Form 3File: FORM 3 MAR 26_compressed.pdf19 Aug 2026
Form 1File: FORM 1 JUN 2026.pdf19 Aug 2026
Form 2File: FORM 2 JUNE 2026.pdf19 Aug 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD BOOKED JUN 26.pdf19 Aug 2026
Form 3File: FORM 3 JUN 26_compressed.pdf19 Aug 2026
Form 2A (FY 2021-2022)File: FORM 2A MARCH 2022_compressed.pdf19 Aug 2026
Form 2A (FY 2022-2023)File: FORM 2A MARCH 2023.pdf19 Aug 2026
Form 2A (FY 2023-2024)File: FORM 2A MARCH 2024_compressed.pdf19 Aug 2026
Form 2A (FY 2024-2025)File: FORM 2A MARCH 2025.pdf19 Aug 2026
Form 2A (FY 2025-2026)File: FORM 2A MARCH 2026.pdf19 Aug 2026
Form 5 (FY 2023-2024)File: FORM 5 - MAR 24.pdf19 Aug 2026

How this compares with Pune

75%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep GANESH PARADISE PHASE 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near CHIKHALI PUNE13,700+ in Pune

Builder: EKDANTA NEST LLP

EKDANTA NEST LLP has 7 registrations on MahaRERA, including GANESH ORCHID and URBAN FOREST A WING. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if GANESH PARADISE PHASE 2 is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GANESH PARADISE PHASE 2?

The registered promoter entity is EKDANTA NEST LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GANESH PARADISE PHASE 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for GANESH PARADISE PHASE 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GANESH PARADISE PHASE 2?

The professionals named in the filing: Architect: ANURADHA GOVARDHAN; Engineer: GAJANAN CHITTE; Engineer: AVINASH ANDENAPPA GADAVE; Chartered Accountant: GAUTAM SHARMA SHARMA; Chartered Accountant: R S NILANGE & CO; Chartered Accountant: A NEGI & COMPANY. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GANESH PARADISE PHASE 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GANESH PARADISE PHASE 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GANESH PARADISE PHASE 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.