Home / Browse projects / Mumbai Suburban, Maharashtra / ROYAL SAMARPAN PHASE 1

Registration lapsed No litigation declared Residential / Group Housing project

ROYAL SAMARPAN PHASE 1

By SHREEJI CONSTRUCTION

RG-MH-25839 · RERA P51800006923 · Last updated on MahaRERA portal: 15 Apr 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 46 months past the filed date
  • 3 complaints at MahaRERA
  • Completion date moved by 18 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2022Possession promised46 months past this date
11 of 11Construction stages doneevery applicable stage filed complete
3Complaints at MahaRERAon this registration
Jump to the 42 documents Report an error

ROYAL SAMARPAN PHASE 1 is a Residential / Group Housing project by SHREEJI CONSTRUCTION in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800006923 on 16 Aug 2017. Possession was promised by 30 Dec 2022 and is now 46 months past that date. The completion date has moved by 18 months from the original filing. 3 complaints are on record with the regulator.

At a glance

Project

  • NameROYAL SAMARPAN PHASE 1
  • TypeResidential / Group Housing
  • Location
    • M G CROSS LANE
    • KANDIVALI WEST
    • Borivali
    • Mumbai Suburban
    • 400067
  • Pincode400067
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800006923
  • ReraGenie IDRG-MH-25839

Builder

  • NameSHREEJI CONSTRUCTION
  • Entity typePartnership
  • PartnersDEVEN PREMJI SHAH, MEHUL PRAMOD SANGHAVI, PREMJI H SHAH
  • Other registrations14 more →
  • Completed4 of 15
  • No longer live3 lapsed, de-registered or revoked
  • Declared earlier projects6 →

Key dates

46 months past promisethis monthRegisteredAug 2017First promiseJun 2021Revised toDec 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on16 Aug 2017
  • Promised completion30 Dec 2022
  • Revised completionRevised to 30 Dec 2022 (originally 30 Jun 2021)
  • Buildings1 building record
  • Documents filed42 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ROYAL SAMARPAN B / C WINGNA260000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 15 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

ROYAL SAMARPAN B / C WING: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 15 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes60%
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes60%
Storm Water DrainsYes85%
Landscaping & Tree PlantingYes90%
Street LightingYes80%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed140

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots140
Closed/Covered122
Open Space18

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,635 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI10393.26
Proposed, not sanctioned6,693 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchUPPER GOVIND NAGAR MALAD EAST

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAAKAR ARCHITECTS AND CONSULTANTS
EngineerSACPL
PartnerRole in project
SHREEJI CONSTRUCTION-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800009654Jun 2021 → Jun 2022

Reason as filed by the promoter1. Project is Slum Rehabilitation Project, approved by the Slum Rehabilitation Authority, we were required to abide all the rules and regulation imposed by SRA, 2. Despite of sluggish market conditions and covid-19, The Hon’ble Authority may appreciate that the project is consisting of B & C wing is complete externally with 19 upper floors including flustering etc. 3. Some mitigating circumstances arise in project, non-availability of steel, cement, other building material, water or electric supply; any change in law, notifications and/or regulations levying any onerous condition on the Promot

Litigation declared5

CaseCourtStatus
1499/2010CITY CIVIL COURT DINDOSHIPENDING
857/2015CITY CIVIL COURT DINDOSHIPENDING
1244/2016CITY CIVIL COURT DINDOSHIPENDING
761/2011CITY CIVIL COURT DINDOSHIPENDING
L NO 10070/2023CITY CIVIL COURT DINDOSHIPENDING

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC006000000220749Himanshu MehtaM/s. Shreeji Construction & Ors.09/04/2022
CC006000000396866PRERANA SAJJAN BAJORIASHREEJI CONSTRUCTION29/07/2023
CC006000000396867PRERAK SAJJAN BAJORIASHREEJI CONSTRUCTION29/07/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 15 Jul 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Jul 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 Jun 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 15 Apr 2025

Documents filed42

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OCC Letter (royal samarpan).pdf15 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 VKJ.pdf5 Jan 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: rs.pdf9 Jul 2021
Proforma of Allotment letterFile: afl.pdf17 Oct 2020
Proforma of Allotment letterFile: AFS C_ DDSD.pdf14 Sep 2020
Details of encumbrancesFile: shreeji.pdf3 Sep 2020
Building plan approvalFile: iodf.pdf20 Jul 2020
Building Plan Approval (IOD)File: iodf.pdf20 Jul 2020
Commencement Certificates / NA Order for plotted developmentFile: FCCf.pdf23 Jun 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Royal5.pdf29 Jan 2020
Proforma of Allotment letterFile: Shreejirera.pdf20 Jul 2019
Copy of the legal title reportFile: kanga.pdf15 Jul 2019
Proforma of Allotment letterFile: Shreeji afs-converted.pdf22 May 2019
Building plan approvalFile: IOD.pdf30 Apr 2019
Building Plan Approval (IOD)File: IOD.pdf30 Apr 2019
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf30 Apr 2019
Proforma of Allotment letterFile: AFS RS.pdf14 Dec 2018
Certificates of CA (Form 5)File: Frorm 5- Royal Samarpan Phases-1.pdf10 Oct 2018
Copy of the legal title reportFile: Report.pdf18 Jul 2018
Proforma of Allotment letterFile: AFS-RS-18-07-2018.pdf18 Jul 2018
Building plan approvalFile: IOD RS.pdf7 Jul 2018
Building Plan Approval (IOD)File: IOD RS.pdf7 Jul 2018
Commencement Certificates / NA Order for plotted developmentFile: CCof RS.pdf7 Jul 2018
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf26 Mar 2018
Proforma of Allotment letterFile: AFS and Allotment Letter final.pdf3 Feb 2018
Proforma of Allotment letterFile: afs.pdf13 Oct 2017
Proforma of Allotment letterFile: Agreement for Sale (Royal Samarpan)-12-09-2017.pdf12 Sep 2017
Copy of the legal title reportFile: TITLE.pdf9 Sep 2017
Proforma of Allotment letterFile: Agreement for Sale (Royal Samarpan).pdf9 Sep 2017
Proforma of Allotment letterFile: Agreement for Sale (Royal Samarpan).pdf9 Sep 2017
Building plan approvalFile: IOD LETTER.pdf28 Jul 2017
Layout approvalFile: SAMARPAN LAYOUT.pdf28 Jul 2017
Copy of the legal title reportFile: SHREEJI TITLE REPORT.pdf28 Jul 2017
Details of encumbrancesFile: SHREEJI DETAILS OF ENCUMBERENCES FINAL.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: SAMARPAN LAYOUT.pdf28 Jul 2017
Building Plan Approval (IOD)File: IOD LETTER.pdf28 Jul 2017
Declaration in FORM BFile: Form B RS New.pdf28 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SHREEJEE ARCH.pdf28 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Shreeji Engg.pdf28 Jul 2017
Certificates of CA (Form 3)File: Samarpan CA.pdf28 Jul 2017
Proforma of Allotment letterFile: ROYAL SAMARPAN ALLOTMENT AND AFS.pdf28 Jul 2017
OtherFile: sc add layout.pdf28 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 18 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ROYAL SAMARPAN PHASE 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KANDIVALI WEST6,700+ in Mumbai Suburban

2 kmROYAL SAMARPAN PHASE 1Completed 95Lapsed / revoked 54Other 128Dot size: filed unitsN

Filed coordinates, straight-line distance. 277 registered projects within 2 km.

Builder: SHREEJI CONSTRUCTION

SHREEJI CONSTRUCTION has 15 registrations on MahaRERA, including SHREEJI CENTRUM and Shreeji Atlantis Wing A. Its filings disclose 6 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that ROYAL SAMARPAN PHASE 1 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if ROYAL SAMARPAN PHASE 1 is delayed beyond 30 Dec 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ROYAL SAMARPAN PHASE 1?

The registered promoter entity is SHREEJI CONSTRUCTION, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ROYAL SAMARPAN PHASE 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against ROYAL SAMARPAN PHASE 1?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for ROYAL SAMARPAN PHASE 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ROYAL SAMARPAN PHASE 1?

The professionals named in the filing: Architect: AAKAR ARCHITECTS AND CONSULTANTS; Engineer: SACPL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ROYAL SAMARPAN PHASE 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ROYAL SAMARPAN PHASE 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ROYAL SAMARPAN PHASE 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.