Home / Developers / SHREEJI CONSTRUCTION
SHREEJI CONSTRUCTION: RERA track record
Partnership ยท attribution by exact filing name, entity resolution in progress
SHREEJI CONSTRUCTION has 15 registrations in this build, including SHREEJI CENTRUM and Shreeji Atlantis Wing A. Its filings disclose 6 earlier MahaRERA projects: 1 of 1 past projects completed on time.
Projects in this build
| Project | Location | Units | Booked | Status |
|---|---|---|---|---|
| SHREEJI CENTRUM | Nashik, Maharashtra | - | - | Completed |
| Shreeji Atlantis Wing A | Mumbai Suburban, Maharashtra | - | - | Completed |
| Shreeji Aspire | Mumbai Suburban, Maharashtra | - | - | Completed |
| ROYAL SAMARPAN PHASE 1 | Mumbai Suburban, Maharashtra | - | - | Registration lapsed |
| PANDAV ENCLAVE | Nashik, Maharashtra | - | - | Completed |
| SHREEJI SQUARE | Mumbai Suburban, Maharashtra | - | - | De-registered |
| SHREEJI SKY RISE TOWER | Mumbai Suburban, Maharashtra | 237 | 67% | Registered |
| SHREEJII ICON | Thane, Maharashtra | - | - | Registration lapsed |
| Shreeji Atlantis Wing B | Mumbai Suburban, Maharashtra | 208 | 62% | Registered |
| Shreeji Eternity Wing - A, Shreeji Eternity Wing - B, Shreeji Eternity Wing - C | Mumbai Suburban, Maharashtra | 197 | 44% | Registered |
| Shreeji Eternity Wing - D | Mumbai Suburban, Maharashtra | 81 | 17% | Registered |
| Shreeji Bliss | Mumbai Suburban, Maharashtra | 112 | 21% | Registered |
| SHREEJI NAKSHTRA | Mumbai Suburban, Maharashtra | 215 | 15% | Registered |
| SHREEJI TRINITY | Mumbai Suburban, Maharashtra | - | - | Registered |
| SHREEJI AMBER | Mumbai Suburban, Maharashtra | - | - | Registered |
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| RAVI RENAISSANCE | 19 May 2020 | 19 May 2020 | On time |
| Shreeji Eternity Wing - A, Shreeji Eternity Wing - B, Shreeji Eternity Wing - C P51800054310 | 30 Jun 2027 | Not completed yet | Ongoing |
| Shreeji Bliss P51800076989 | 31 Jan 2028 | Not completed yet | Ongoing |
| Shreeji Eternity Wing - D P51800054233 | 30 Jun 2028 | Not completed yet | Ongoing |
| SHREEJI NAKSHTRA P51800079261 | 31 Aug 2028 | Not completed yet | Ongoing |
| SHREEJI TRINITY PM1180002502235 | 30 Jun 2030 | Not completed yet | Ongoing |
Frequently asked questions
How do I verify SHREEJI CONSTRUCTION as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with SHREEJI CONSTRUCTION?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.