Home / Browse projects / Thane, Maharashtra / ROYAL MEADOWS C 1 , C 2

Registration lapsed No litigation declared Residential / Group Housing project

ROYAL MEADOWS C 1 , C 2

By SIDDHIVINAYAK DEVELOPERS

RG-MH-60352 · RERA P51700008736 · Last updated on MahaRERA portal: 24 Nov 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • 3 complaints at MahaRERA
  • Completion date moved by 63 months
  • 4 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
20 of 22Construction stages doneacross 2 buildings; furthest along: Installation of Lifts, 80%
9 of 188Units unsoldnot recorded sold or booked
3Complaints at MahaRERAon this registration
Jump to the 50 documents Report an error

ROYAL MEADOWS C 1 , C 2 is a Residential / Group Housing project by SIDDHIVINAYAK DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as P51700008736 on 19 Aug 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 63 months from the original filing. 179 of the 188 units on this registration are recorded sold or booked, and 20 of 22 construction stages are filed complete. 3 complaints are on record with the regulator.

At a glance

Project

  • NameROYAL MEADOWS C 1 , C 2
  • TypeResidential / Group Housing
  • Location
    • SHAHAD
    • Kalyan-Dombivali (M Corp.)
    • Kalyan
    • Thane
    • 421301
  • Pincode421301
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700008736
  • ReraGenie IDRG-MH-60352

Builder

  • NameSIDDHIVINAYAK DEVELOPERS
  • Entity typePartnership
  • PartnersJAIRAMDAS GIRDHARILAL CHHABRIA, GIRDHARILAL OTANMAL CHHABRIA, POOJA KISHORE CHUGH, JANKIBAI GIRDHARILAL CHHABRIA, MAHESH MANOHARLAL CHHABIRA, MANOHARLAL OTANDAS CHHABRIA, AMITA PURSHOTAM DINGREJA, MONISH PURSHOTAM DINGREJA, MONISH PURSHOTAM DINGREJA, JANKIBAI GIRDHARILAL CHHABRIA, MAHESH MANOHARLAL CHHABIRA, MANOHARLAL OTANDAS CHHABRIA and 4 more
  • Other registrations45 more →
  • Completed21 of 46
  • No longer live7 lapsed, de-registered or revoked
  • Declared earlier projects11 →

Key dates

10 months past promisethis monthRegisteredAug 2017First promiseSep 2020Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on19 Aug 2017
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 1 Sep 2020)
  • Buildings2 building records
  • Documents filed50 files

Current status

95%179 of 188 units booked

Figures as on 24 Nov 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
C 1 - RIDDHINA181694094
C - 2 SIDDHINA181694094

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 24 Nov 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

20 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Installation of Lifts, at 80%.

C 1 - RIDDHI98%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
C - 2 SIDDHI98%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%

Progress on shared amenities15

As on 24 Nov 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes90%
Water SupplyYes20%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes70%
Street LightingYes90%
Community BuildingsYes30%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes70%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed76

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots76
Closed/Covered76
BuildingClosed/CoveredTotal
C 1 - RIDDHI3838
C - 2 SIDDHI3838

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,589 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityKalyan Dombivli Municipal Corporation
Permissible FSI10219.79
Proposed, not sanctioned4,553 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSURVEY NO 22, SHAHAD MOHANE ROAD, OPP PATIDAR BHAVAN SHAHAD KALYAN

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectARCHITECTS INC
EngineerATUL KHUDTARKAR & ASSOCIATES
Chartered AccountantMukesh Premchand Gurnani
PartnerRole in project
SIDDHIVINAYAK DEVELOPERS-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700003878Sep 2020 → Aug 2021

Reason as filed by the promoterWe have completed major construction work of our project “Royal Meadows C1,C2” bearing RERA Registration No. P51700008736 , but our project being located in mofussil area, we are facing many difficulties in procuring quality of material and manpower. Due to which our scheduled work is delayed. For the sake of completing it on the actual proposed date i.e. 01/09/2020 we cannot compromise in the quality of service. Hence we request you to grant us the revised date of completion as 31/08/2021 for our Project “Royal Meadows C1,C2” - being Registration No.P51700008736.

EXT51700013645Sep 2020 → Mar 2023

Reason as filed by the promoterThe project is under construction & we have completed more than 95% work on the project. However due to imposition of lockdown and consequently migration of labour and contractors we are facing difficulty in arranging the manpower to complete the project on time. Though while registering the project under RERA we were sure to complete the project on time i.e. on our proposed date, but due to this pandemic COVID - 19 it is getting delayed. Hence we request you to grant us the revised date of completion as 31/03/2023 for our Project - “Royal Meadows C1, C2” bearing Registration No. P51700008736.

EXT51700012486Sep 2020 → Dec 2022

Reason as filed by the promoterThe project is under construction & we have completed more than 90% work of the project. However due to imposition of lockdown and consequently migration of labour and contractors and scarcity of material, we are facing difficulty in arranging the manpower and Material to complete the project on time. Though while registering the project under RERA we were sure to complete the project on time i.e. on our proposed date, but due to the above said reasons only the completion of the project has been delayed. Hence we request your honour to kindly grant us the revised date of completion as 31/12/20

EA12072502063Sep 2020 → Dec 2025

Reason as filed by the promoterThe delay in obtaining the final Occupancy Certificate (OC) is primarily due to the pending completion of the clubhouse, which forms an essential amenity within the project. While the main residential buildings have been completed and are fit for occupation, we have already received the Occupancy Certificate for building on 24/05/2023, and a Part Occupancy Certificate for additional completed components all common amenities, including the clubhouse was subsequently granted on 24/06/2025. In view of the above and to ensure continued compliance with RERA requirements, we have applied for an exte

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC006000000001345Deepak TejwaniAnil Chabria11/01/2018
CC006000000001644Deepak TejwaniMr Anil Chabria01/11/2017
CC006000000397678Leo Thomson CSiddhivinayak Developers02/10/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 5 Jan 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 Jan 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 26 May 2023

Documents filed50

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2021-2022)File: Form 5 FY 2021-22.pdf24 Nov 2025
Form 5 (FY 2022-2023)File: Form 5 FY 2022-23.pdf24 Nov 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Signed Form 5 Siddhivinayak Developers.pdf2 Dec 2024
Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf15 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Siddhivinayak Developers 22-23.pdf15 Jan 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC.pdf26 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate.pdf25 Feb 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Part Completion.pdf25 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: RERA Audit 21-22.pdf18 Jan 2023
Disclosure of sold/ booked inventoryFile: C1.pdf16 Jan 2023
Disclosure of sold/ booked inventoryFile: C2.pdf16 Jan 2023
Layout approvalFile: 1MYSCAN_20221230_0001.PDF5 Jan 2023
Copy of Layout Approval (in case of layout)File: 1MYSCAN_20221230_0001.PDF5 Jan 2023
Commencement Certificates / NA Order for plotted developmentFile: OC SHAHAD.pdf5 Jan 2023
Declaration about Commencement CertificateFile: Format D.pdf6 Sep 2022
Disclosure of sold/ booked inventoryFile: Sold Unsold List 06092022.pdf6 Sep 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Siddhivinayak Developers - 310320.pdf3 Sep 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Siddhivinayak Developers - 310321.pdf3 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 2020-21.pdf3 Sep 2022
Layout approvalFile: Layout.pdf23 Sep 2021
Copy of Layout Approval (in case of layout)File: Layout.pdf23 Sep 2021
Commencement Certificates / NA Order for plotted developmentFile: Revised Commencement Certificate-1-4.pdf23 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form - 5 - RERA Audit Siddhivinayak Developers.pdf25 May 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Siddhivinayak Developers - Form 5 2018-19.pdf4 Aug 2020
Layout approvalFile: COMPRESSED Revised Plan Copy (1).pdf29 Jul 2019
Copy of Layout Approval (in case of layout)File: COMPRESSED Revised Plan Copy (1).pdf29 Jul 2019
Commencement Certificates / NA Order for plotted developmentFile: COMPRESSED Revised CC.pdf29 Jul 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SIDHIVINAYAK ARCHITECT CERTIFICATE.pdf29 Jul 2019
Certificates of CA (Form 5)File: SIDDHIVINAYAK.pdf19 Oct 2018
Layout approvalFile: Revised Plan-ilovepdf-compressed.pdf21 Dec 2017
Copy of Layout Approval (in case of layout)File: Revised Plan-ilovepdf-compressed.pdf21 Dec 2017
Commencement Certificates / NA Order for plotted developmentFile: Revised CC.pdf21 Dec 2017
OtherFile: Fire NOC-ilovepdf-compressed.pdf21 Dec 2017
Building plan approvalFile: Iod Shahad 3032007.pdf31 Jul 2017
Building plan approvalFile: Iod Shahad 30320071.pdf31 Jul 2017
Layout approvalFile: scan0185.pdf31 Jul 2017
PAN CardFile: PAN CARD OF FIRM.pdf31 Jul 2017
Copy of the legal title reportFile: TITLE CERTIFICATE-ilovepdf-compressed.pdf31 Jul 2017
Details of encumbrancesFile: Encumbrances.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: scan0185.pdf31 Jul 2017
Building Plan Approval (IOD)File: Iod Shahad 30320071.pdf31 Jul 2017
Building Plan Approval (IOD)File: Iod Shahad 3032007.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: commencement certificate.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: C C 2013.pdf31 Jul 2017
Declaration in FORM BFile: AFFIDAVIT FINAL.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT FINAL CERTIFICATE.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FINAL ENG CERTIFICATIE.pdf31 Jul 2017
Certificates of CA (Form 3)File: Siddhivinayak Developers (1).pdf31 Jul 2017
Proforma of Allotment letterFile: FINAL ALLOTMENT.pdf31 Jul 2017
Proforma of Allotment letterFile: SIDDHIVINAYAK SALE AGRREMENT.pdf31 Jul 2017

How this compares with Thane

95%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 63 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ROYAL MEADOWS C 1 , C 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SHAHAD7,600+ in Thane

Builder: SIDDHIVINAYAK DEVELOPERS

SIDDHIVINAYAK DEVELOPERS has 46 registrations on MahaRERA, including VIJAY PLAZA - A and VIJAY PLAZA - B. Its filings disclose 11 earlier MahaRERA projects: declares 6 of 9 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that ROYAL MEADOWS C 1 , C 2 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if ROYAL MEADOWS C 1 , C 2 is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ROYAL MEADOWS C 1 , C 2?

The registered promoter entity is SIDDHIVINAYAK DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ROYAL MEADOWS C 1 , C 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against ROYAL MEADOWS C 1 , C 2?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for ROYAL MEADOWS C 1 , C 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ROYAL MEADOWS C 1 , C 2?

The professionals named in the filing: Architect: ARCHITECTS INC; Engineer: ATUL KHUDTARKAR & ASSOCIATES; Chartered Accountant: Mukesh Premchand Gurnani. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ROYAL MEADOWS C 1 , C 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ROYAL MEADOWS C 1 , C 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ROYAL MEADOWS C 1 , C 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.