ROYAL MEADOWS C 1 , C 2
RG-MH-60352 · RERA P51700008736 · Last updated on MahaRERA portal: 24 Nov 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- 3 complaints at MahaRERA
- Completion date moved by 63 months
- 4 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ROYAL MEADOWS C 1 , C 2 is a Residential / Group Housing project by SIDDHIVINAYAK DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as P51700008736 on 19 Aug 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 63 months from the original filing. 179 of the 188 units on this registration are recorded sold or booked, and 20 of 22 construction stages are filed complete. 3 complaints are on record with the regulator.
At a glance
Project
- NameROYAL MEADOWS C 1 , C 2
- TypeResidential / Group Housing
- Location
- SHAHAD
- Kalyan-Dombivali (M Corp.)
- Kalyan
- Thane
- 421301
- Pincode421301
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700008736
- ReraGenie IDRG-MH-60352
Builder
- NameSIDDHIVINAYAK DEVELOPERS
- Entity typePartnership
- PartnersJAIRAMDAS GIRDHARILAL CHHABRIA, GIRDHARILAL OTANMAL CHHABRIA, POOJA KISHORE CHUGH, JANKIBAI GIRDHARILAL CHHABRIA, MAHESH MANOHARLAL CHHABIRA, MANOHARLAL OTANDAS CHHABRIA, AMITA PURSHOTAM DINGREJA, MONISH PURSHOTAM DINGREJA, MONISH PURSHOTAM DINGREJA, JANKIBAI GIRDHARILAL CHHABRIA, MAHESH MANOHARLAL CHHABIRA, MANOHARLAL OTANDAS CHHABRIA and 4 more
- Other registrations45 more →
- Completed21 of 46
- No longer live7 lapsed, de-registered or revoked
- Declared earlier projects11 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on19 Aug 2017
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 1 Sep 2020)
- Buildings2 building records
- Documents filed50 files
Current status
Figures as on 24 Nov 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| C 1 - RIDDHI | NA | 18 | 16 | 94 | 0 | 94 |
| C - 2 SIDDHI | NA | 18 | 16 | 94 | 0 | 94 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 24 Nov 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
20 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Installation of Lifts, at 80%.
C 1 - RIDDHI98%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 80% |
C - 2 SIDDHI98%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 80% |
Progress on shared amenities15
As on 24 Nov 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 90% |
| Water Supply | Yes | 20% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 70% |
| Street Lighting | Yes | 90% |
| Community Buildings | Yes | 30% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 70% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed76
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| C 1 - RIDDHI | 38 | 38 |
| C - 2 SIDDHI | 38 | 38 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ARCHITECTS INC |
| Engineer | ATUL KHUDTARKAR & ASSOCIATES |
| Chartered Accountant | Mukesh Premchand Gurnani |
| Partner | Role in project |
|---|---|
| SIDDHIVINAYAK DEVELOPERS | - |
Extensions applied for4
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe have completed major construction work of our project “Royal Meadows C1,C2” bearing RERA Registration No. P51700008736 , but our project being located in mofussil area, we are facing many difficulties in procuring quality of material and manpower. Due to which our scheduled work is delayed. For the sake of completing it on the actual proposed date i.e. 01/09/2020 we cannot compromise in the quality of service. Hence we request you to grant us the revised date of completion as 31/08/2021 for our Project “Royal Meadows C1,C2” - being Registration No.P51700008736.
Reason as filed by the promoterThe project is under construction & we have completed more than 95% work on the project. However due to imposition of lockdown and consequently migration of labour and contractors we are facing difficulty in arranging the manpower to complete the project on time. Though while registering the project under RERA we were sure to complete the project on time i.e. on our proposed date, but due to this pandemic COVID - 19 it is getting delayed. Hence we request you to grant us the revised date of completion as 31/03/2023 for our Project - “Royal Meadows C1, C2” bearing Registration No. P51700008736.
Reason as filed by the promoterThe project is under construction & we have completed more than 90% work of the project. However due to imposition of lockdown and consequently migration of labour and contractors and scarcity of material, we are facing difficulty in arranging the manpower and Material to complete the project on time. Though while registering the project under RERA we were sure to complete the project on time i.e. on our proposed date, but due to the above said reasons only the completion of the project has been delayed. Hence we request your honour to kindly grant us the revised date of completion as 31/12/20
Reason as filed by the promoterThe delay in obtaining the final Occupancy Certificate (OC) is primarily due to the pending completion of the clubhouse, which forms an essential amenity within the project. While the main residential buildings have been completed and are fit for occupation, we have already received the Occupancy Certificate for building on 24/05/2023, and a Part Occupancy Certificate for additional completed components all common amenities, including the clubhouse was subsequently granted on 24/06/2025. In view of the above and to ensure continued compliance with RERA requirements, we have applied for an exte
Complaints filed with MahaRERA3
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000001345 | Deepak Tejwani | Anil Chabria | 11/01/2018 |
| CC006000000001644 | Deepak Tejwani | Mr Anil Chabria | 01/11/2017 |
| CC006000000397678 | Leo Thomson C | Siddhivinayak Developers | 02/10/2023 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 5 Jan 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 31 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 5 Jan 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 26 May 2023
Documents filed50
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 5 (FY 2021-2022)File: Form 5 FY 2021-22.pdf | 24 Nov 2025 |
| Form 5 (FY 2022-2023)File: Form 5 FY 2022-23.pdf | 24 Nov 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Signed Form 5 Siddhivinayak Developers.pdf | 2 Dec 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf | 15 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Siddhivinayak Developers 22-23.pdf | 15 Jan 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC.pdf | 26 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate.pdf | 25 Feb 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Part Completion.pdf | 25 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: RERA Audit 21-22.pdf | 18 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: C1.pdf | 16 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: C2.pdf | 16 Jan 2023 |
| Layout approvalFile: 1MYSCAN_20221230_0001.PDF | 5 Jan 2023 |
| Copy of Layout Approval (in case of layout)File: 1MYSCAN_20221230_0001.PDF | 5 Jan 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: OC SHAHAD.pdf | 5 Jan 2023 |
| Declaration about Commencement CertificateFile: Format D.pdf | 6 Sep 2022 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold List 06092022.pdf | 6 Sep 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Siddhivinayak Developers - 310320.pdf | 3 Sep 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Siddhivinayak Developers - 310321.pdf | 3 Sep 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 2020-21.pdf | 3 Sep 2022 |
| Layout approvalFile: Layout.pdf | 23 Sep 2021 |
| Copy of Layout Approval (in case of layout)File: Layout.pdf | 23 Sep 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: Revised Commencement Certificate-1-4.pdf | 23 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form - 5 - RERA Audit Siddhivinayak Developers.pdf | 25 May 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Siddhivinayak Developers - Form 5 2018-19.pdf | 4 Aug 2020 |
| Layout approvalFile: COMPRESSED Revised Plan Copy (1).pdf | 29 Jul 2019 |
| Copy of Layout Approval (in case of layout)File: COMPRESSED Revised Plan Copy (1).pdf | 29 Jul 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: COMPRESSED Revised CC.pdf | 29 Jul 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SIDHIVINAYAK ARCHITECT CERTIFICATE.pdf | 29 Jul 2019 |
| Certificates of CA (Form 5)File: SIDDHIVINAYAK.pdf | 19 Oct 2018 |
| Layout approvalFile: Revised Plan-ilovepdf-compressed.pdf | 21 Dec 2017 |
| Copy of Layout Approval (in case of layout)File: Revised Plan-ilovepdf-compressed.pdf | 21 Dec 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: Revised CC.pdf | 21 Dec 2017 |
| OtherFile: Fire NOC-ilovepdf-compressed.pdf | 21 Dec 2017 |
| Building plan approvalFile: Iod Shahad 3032007.pdf | 31 Jul 2017 |
| Building plan approvalFile: Iod Shahad 30320071.pdf | 31 Jul 2017 |
| Layout approvalFile: scan0185.pdf | 31 Jul 2017 |
| PAN CardFile: PAN CARD OF FIRM.pdf | 31 Jul 2017 |
| Copy of the legal title reportFile: TITLE CERTIFICATE-ilovepdf-compressed.pdf | 31 Jul 2017 |
| Details of encumbrancesFile: Encumbrances.pdf | 31 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: scan0185.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: Iod Shahad 30320071.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: Iod Shahad 3032007.pdf | 31 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: commencement certificate.pdf | 31 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: C C 2013.pdf | 31 Jul 2017 |
| Declaration in FORM BFile: AFFIDAVIT FINAL.pdf | 31 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT FINAL CERTIFICATE.pdf | 31 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FINAL ENG CERTIFICATIE.pdf | 31 Jul 2017 |
| Certificates of CA (Form 3)File: Siddhivinayak Developers (1).pdf | 31 Jul 2017 |
| Proforma of Allotment letterFile: FINAL ALLOTMENT.pdf | 31 Jul 2017 |
| Proforma of Allotment letterFile: SIDDHIVINAYAK SALE AGRREMENT.pdf | 31 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 45 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 50 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep ROYAL MEADOWS C 1 , C 2 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near SHAHAD7,600+ in Thane
PODDAR RIVIERA PHASE - I
Poddar Housing and Development Limited
Sinhagad by Bhagwati Haware - Wing - B
Bhagwati Haware Properties Supertech
Pratapgad by Bhagwati Haware - Wing - C
Bhagwati Haware Properties Supertech
Rajgad by Bhagwati Haware - Wing - D
Bhagwati Haware Properties Supertech
PODDAR RIVIERA PHASE - III
Poddar Housing and Development Limited
THARWANI PARKGLEN PHASE I
THARWANI REALTORS
See every Thane project, with the district possession charts
Builder: SIDDHIVINAYAK DEVELOPERS
SIDDHIVINAYAK DEVELOPERS has 46 registrations on MahaRERA, including VIJAY PLAZA - A and VIJAY PLAZA - B. Its filings disclose 11 earlier MahaRERA projects: declares 6 of 9 past projects completed on time. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that ROYAL MEADOWS C 1 , C 2 shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if ROYAL MEADOWS C 1 , C 2 is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ROYAL MEADOWS C 1 , C 2?
The registered promoter entity is SIDDHIVINAYAK DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ROYAL MEADOWS C 1 , C 2?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against ROYAL MEADOWS C 1 , C 2?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for ROYAL MEADOWS C 1 , C 2?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ROYAL MEADOWS C 1 , C 2?
The professionals named in the filing: Architect: ARCHITECTS INC; Engineer: ATUL KHUDTARKAR & ASSOCIATES; Chartered Accountant: Mukesh Premchand Gurnani. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ROYAL MEADOWS C 1 , C 2?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.