Home / Browse projects / Pune, Maharashtra / Royal Fortune

Registered No litigation declared Commercial project

Royal Fortune

By Vivan Landmark

RG-MH-95599 · RERA P52100018295 · Last updated on MahaRERA portal: 15 Mar 2024

Source: official MahaRERA filing

Red flags

  • Completion date moved by 73 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Oct 2026Possession promisedmoved 73 months from the original
9 of 11Construction stages donefurthest along: Installation of Lifts, 95%
6 of 30Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 39 documents Report an error

Royal Fortune is a Commercial project by Vivan Landmark in Pune, Maharashtra, registered with MahaRERA as P52100018295 on 22 Oct 2018. Possession is promised by 15 Oct 2026. The completion date has moved by 73 months from the original filing. 24 of the 30 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete.

At a glance

Project

  • NameRoyal Fortune
  • TypeCommercial
  • Location
    • Baner
    • Haveli
    • Pune
    • 411045
  • Pincode411045
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100018295
  • ReraGenie IDRG-MH-95599

Builder

  • NameVivan Landmark
  • Entity typePartnership
  • GSTIN27AANFV4026E1Z4
  • PartnersJinesh Mansukhlal Kakaria, BHARAT RASIKLAL SHAH

Key dates

this monthRegisteredOct 2018First promiseSep 2020Revised toOct 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on22 Oct 2018
  • Promised completion15 Oct 2026
  • Revised completionRevised to 15 Oct 2026 (originally 30 Sep 2020)
  • Buildings1 building record
  • Documents filed39 files

Current status

80%24 of 30 units booked

Figures as on 15 Mar 2024, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Royal FortuneNA7762430

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 15 Mar 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 95%.

Royal Fortune: 90% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 15 Mar 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes80%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed31

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots31
Closed/Covered31

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,445 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
Niraj Narendra SanklechaBanerPune
Bharat Rasiklal Shah-Pune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI1533.52
Proposed, not sanctioned1,534 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop No 3 4 5 6, Ground Floor, Guru Tej Bahadur Co Op Hsg Society, Aundh Road, Opp LIC Office, Khada

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRupesh Jamkhindikar
EngineerShishir Dhawade
EngineerNivcon Projects Pvt Ltd
Chartered AccountantN N Bagwan and Associates
Chartered AccountantK K S S & Associates
Chartered AccountantA H V & Associates
Chartered AccountantTushar S Shermale & Associates
PartnerRole in project
Vivan Landmark-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100009488Sep 2020 → Oct 2022

Reason as filed by the promoter(i) As the occurrence of unexpected global pandemic situation of COVID -19 has direct effect on the work due to shortage of material, labour & other necessary resources of project leads to the delay in completion of the project. (ii) This is to be stated that, the promoter has completed the project in full and applied for the completion of the project. However, with the approval of Unified Development Control and Promotion Regulation by Govt of Maharashtra promoter is eligible to get additional FSI for the under construction projects. Thus, promoter after discussion with the allottees decided

EXT52100008421Sep 2020 → Mar 2021

Reason as filed by the promoter(i) As the occurrence of unexpected global pandemic situation of COVID -19 has direct effect on the work due to shortage of material, labour & other necessary resources of project leads to the delay in completion of the project. (ii) COVID - 19 pandemic turns out with the lockdown situation because of which the Pune Municipal Corporation unable to give priority to issue completion certificate, the file for which has been already submitted in PMC Office. The acknowledgement of the said submission is enclosed along with this application. This is also one of the reason for delay in completion of

EA23072621853Sep 2020 → Oct 2026

Reason as filed by the promoterWe M/s. Vivan Landmark promoters of the project ROYAL FORTUNE hereby declarae that the said project is completed in all respects, for which promoters have already obtained full Occupation Certificate from planning authority dated 27/07/2023 and for all sold units possessions are handed over to all allottees till date. As on date project is lapsed status and OC date is beyond the project completion date form 4 validation as per order 24 cannot be carried out for obtaining completion status of the project. Hence we request Your Honor to please grant us a POST FACTO extension till 15-10-2026 for

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 13 Oct 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Oct 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Oct 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Oct 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 12 Feb 2024

Documents filed39

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: RERA Form 2A - Engineer Certificate FY 19-20.pdf15 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: RERA Form 2A - Engineer Certificate FY 20-21.pdf15 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: RERA Form 2A - Engineer Certificate FY 21-22.pdf15 Mar 2024
Certificates of CA (Form 3)File: Updated form 3 on Letterhead_compressed.pdf15 Mar 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A (Niraj Sanklecha).pdf15 Mar 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A (Bharat Shah).pdf15 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 Vivan Landmark 17-18 (1).pdf15 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 Vivan Landmark 18-19 (1).pdf15 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 Vivan Landmark 19-20 (1).pdf15 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Vivan Landmark 20-21 (1).pdf15 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Vivan Landmark 21-22 (1).pdf15 Mar 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Seprate Bank Account Declaration.pdf15 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Form 1.pdf28 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate.pdf27 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Sign.pdf27 Feb 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE Sold Unsold.pdf27 Feb 2024
CERSAI detailsFile: CERSAI Declaration.pdf27 Feb 2024
Certificates of CA (Form 3)File: Form 3_compressed.pdf27 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Vivan Landmark Signed.pdf27 Feb 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Full Occupancy Certificate.pdf12 Feb 2024
Details of encumbrancesFile: Encumbrance Cert.pdf15 Oct 2018
Copy of the legal title reportFile: Search and Title.pdf13 Oct 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Cert-ilovepdf-compressed.pdf13 Oct 2018
Certificates of CA (Form 3)File: CA Certificate-ilovepdf-compressed.pdf13 Oct 2018
OtherFile: Building Plan.pdf13 Oct 2018
OtherFile: NA Order Certificate-ilovepdf-compressed.pdf13 Oct 2018
OtherFile: Index II Kharedi khat.pdf13 Oct 2018
OtherFile: Index II Road.pdf13 Oct 2018
OtherFile: 7_12 Extract.pdf13 Oct 2018
Building plan approvalFile: Building Plan.pdf6 Oct 2018
Layout approvalFile: Sanction Layout.pdf6 Oct 2018
PAN CardFile: Pan Card Vivan Landmark.pdf6 Oct 2018
Copy of Layout Approval (in case of layout)File: Sanction Layout.pdf6 Oct 2018
Building Plan Approval (IOD)File: Building Plan.pdf6 Oct 2018
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate-ilovepdf-compressed.pdf6 Oct 2018
Declaration in FORM BFile: Form B- Niraj Sanklecha-ilovepdf-compressed.pdf6 Oct 2018
Declaration in FORM BFile: Form B- Bharat Shah-ilovepdf-compressed.pdf6 Oct 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Vivan.pdf6 Oct 2018
Proforma of Allotment letterFile: S No 15 Baner Agreement Draft.pdf6 Oct 2018

How this compares with Pune

80%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 73 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Royal Fortune on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Baner13,700+ in Pune

2 kmRoyal FortuneCompleted 102Lapsed / revoked 32Other 133Dot size: filed unitsN

Filed coordinates, straight-line distance. 267 registered projects within 2 km.

Builder: Vivan Landmark

Vivan Landmark has 1 registration on MahaRERA, including Royal Fortune. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Royal Fortune is delayed beyond 15 Oct 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Royal Fortune?

The registered promoter entity is Vivan Landmark, a partnership as per the filing. Its GSTIN 27AANFV4026E1Z4 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Royal Fortune?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Royal Fortune?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Royal Fortune?

The professionals named in the filing: Architect: Rupesh Jamkhindikar; Engineer: Shishir Dhawade; Engineer: Nivcon Projects Pvt Ltd; Chartered Accountant: N N Bagwan and Associates; Chartered Accountant: K K S S & Associates; Chartered Accountant: A H V & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Royal Fortune?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Royal Fortune. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Royal Fortune to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.