Home / Browse projects / Pune, Maharashtra / ROSHAN MILESTONE WING E

Completed No litigation declared Residential / Group Housing project

ROSHAN MILESTONE WING E

By RAHUL BHAGWANDAS SANKLA

RG-MH-84514 · RERA P52100050418 · Last updated on MahaRERA portal: 13 Aug 2024

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 9 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedregistration recorded completed
4 of 11Construction stages donefurthest along: Basement (if any), 95%
0Complaints at MahaRERAon this registration
Jump to the 93 documents Report an error

ROSHAN MILESTONE WING E is a Residential / Group Housing project by RAHUL BHAGWANDAS SANKLA in Pune, Maharashtra, registered with MahaRERA as P52100050418 on 12 Apr 2023. The registration is recorded completed; possession was promised by 31 Dec 2028.

At a glance

Project

  • NameROSHAN MILESTONE WING E
  • TypeResidential / Group Housing
  • Location
    • SURVEY NO 105
    • TATHWADE
    • Mulshi
    • Pune
    • 411057
  • Pincode411057
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100050418
  • ReraGenie IDRG-MH-84514

Builder

  • NameRAHUL BHAGWANDAS SANKLA
  • Entity typeIndividual
  • Other registrations9 more →
  • Completed10 of 10
  • Declared earlier projects1 →

Key dates

this monthRegisteredApr 2023PromisedDec 2028Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on12 Apr 2023
  • Promised completion31 Dec 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed93 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ROSHAN MILESONE WING ENA170000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 13 Aug 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 95%.

ROSHAN MILESONE WING E: 96% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)95%
Podiums (if any)95%
Plinth95%
Stilt Floor95%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 13 Aug 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)Yes85%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes40%
Street LightingYes0%
Community BuildingsYes80%
Treatment And Disposal Of Sewage And Sullage WaterYes90%
Solid Waste Management And DisposalYes50%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes50%
Fire protection and fire safety requirementsYes95%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed84

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots84
Closed/Covered84

Land and ownership11

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area11,300 sq m
Land owned byThe promoter, with other names on the file
Named landowners11
LandownerVillageDistrict
KALURAM KISANRAO DORGEWadgaon BkPune
BHAVNA ATUL SANKLAPune (M Corp.)Pune
UMADEVI RAMMOHANAGRAWALPune (M Corp.)Pune
DR ANAND MARUTIRAO ATKAREGarkhedaAurangabad
MUKUNDRAJ ARJUNRAO KHONDEGarkhedaAurangabad
SAGAR BALASAHEB GAWALIPune (M Corp.)Pune
BHAVNA MUKUND SANT-Vadodara
BABASAHEB NANASAHEB NIKAMGarkhedaAurangabad
PANKAJ MURLIDHAR NIKUMBHPimpale SaudagarPune
KIRAN HIRALAL JAINPune (M Corp.)Pune
LALIT HIRALAL JAINPune (M Corp.)Pune

Approvals and building plan

Permissible FSI6884.69
Proposed, not sanctioned5,519 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchHINJEWADI, PUNE

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCubix Architects Associates
ArchitectPatil & Bugade Architects + Interior Designers
EngineerMAYUR SATISH DUDHEDIA
Chartered AccountantCA Akshay Gandhi
Chartered AccountantCA Swapnil Bhosale
PartnerRole in project
RAHUL BHAGWANDAS SANKLA-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Mar 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Aug 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Aug 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Aug 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 12 Aug 2024

Documents filed93

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 93 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Building plan approvalFile: 18 E Wing_2_11zon.pdf13 Aug 2024
Layout approvalFile: 1) Layout Plan_13_11zon.pdf13 Aug 2024
Building plan approvalFile: 16 E Wing_27_11zon.pdf13 Aug 2024
Building plan approvalFile: 17 E Wing_1_11zon.pdf13 Aug 2024
Copy of Layout Approval (in case of layout)File: 1) Layout Plan_13_11zon.pdf13 Aug 2024
Building Plan Approval / NA Order for plotted developmentFile: 16 E Wing_27_11zon.pdf13 Aug 2024
Building Plan Approval / NA Order for plotted developmentFile: 17 E Wing_1_11zon.pdf13 Aug 2024
Building Plan Approval / NA Order for plotted developmentFile: 18 E Wing_2_11zon.pdf13 Aug 2024
Commencement Certificates / NA Order for plotted developmentFile: 0) Commencement Certificate_12_11zon.pdf13 Aug 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion.pdf12 Aug 2024
Architect’s Certificate on Completion of Project (Form 4)File: E WING.pdf12 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Final Form 1.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Final Form 2.pdf20 Jul 2024
Disclosure of sold/ booked inventoryFile: Sold Circular.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3.pdf20 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A -E_0001.pdf3 May 2024
Disclosure of sold/ booked inventoryFile: Sold Circular WING E_0001.pdf25 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf19 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf19 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf19 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: JUN 23_0001.pdf27 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf22 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf22 Jan 2024
Disclosure of sold/ booked inventoryFile: Sold Circular.pdf22 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_compressed.pdf22 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: E.pdf20 Nov 2023
Disclosure of sold/ booked inventoryFile: SOLD CIRCULAR JUN 23.pdf8 Nov 2023
Disclosure of sold/ booked inventoryFile: SOLD CIRCULAR.pdf8 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf6 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf6 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 compress.pdf6 Nov 2023
Layout approvalFile: HPSCANNER6892_compressed.pdf28 Oct 2023
Building plan approvalFile: HPSCANNER6877_compressed.pdf28 Oct 2023
Building plan approvalFile: HPSCANNER6878.pdf28 Oct 2023
Building plan approvalFile: HPSCANNER6880_compressed.pdf28 Oct 2023
Copy of Layout Approval (in case of layout)File: HPSCANNER6892_compressed.pdf28 Oct 2023
Building Plan Approval / NA Order for plotted developmentFile: HPSCANNER6877_compressed.pdf28 Oct 2023
Building Plan Approval / NA Order for plotted developmentFile: HPSCANNER6878.pdf28 Oct 2023
Building Plan Approval / NA Order for plotted developmentFile: HPSCANNER6880_compressed.pdf28 Oct 2023
Commencement Certificates / NA Order for plotted developmentFile: 01_compressed (1).pdf28 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: E WING FORM NO 1 30 JUNE 2023_0001.pdf12 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: E WING FORM NO 2 30 JUNE 2023_0001.pdf12 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: compressed_E WING FORM NO 3 30 JUNE 2023_0001.pdf12 Sep 2023
Proforma of Agreement for saleFile: DAVIATION REPORT WING E.pdf9 May 2023
Proforma of Agreement for saleFile: WING E DRAFT AGREEMENT.pdf9 May 2023
Proforma of Agreement for saleFile: WING E DRAFT AGREEMENT.pdf9 May 2023
Deviation Report with respect to model copy of AgreementFile: DAVIATION REPORT WING E.pdf9 May 2023
Deviation Report with respect to model copy of AgreementFile: DAVIATION REPORT WING E.pdf9 May 2023
Deviation Report with respect to model copy of AgreementFile: DAVIATION REPORT WING E.pdf9 May 2023
Proforma of Agreement for saleFile: R M 1 DREAFT AGREEMENT.pdf22 Apr 2023
Deviation Report with respect to model copy of AgreementFile: DEVIATION REPORT.pdf22 Apr 2023
Copy of the legal title reportFile: Legal title Report (revised) 27 03 2023_compressed.pdf27 Mar 2023
Proforma of Agreement for saleFile: ilovepdf_merged.pdf27 Mar 2023
Other - LegalFile: Landowner Clarification Building E.pdf25 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA E WING FORM 3.pdf13 Mar 2023
Building plan approvalFile: scan 1-20.pdf17 Feb 2023
Layout approvalFile: scan 1-20.pdf17 Feb 2023
Details of encumbrances concerned to FinanceFile: SELF DECLARATION FINANCIAL ENCUMBRANCES (1).pdf17 Feb 2023
Details of encumbrances concerned to LegalFile: SELF DECLARATION FINANCIAL ENCUMBRANCES (1).pdf17 Feb 2023
Copy of Layout Approval (in case of layout)File: scan 1-20.pdf17 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: scan 1-20.pdf17 Feb 2023
Details of encumbrances concerned to FinanceFile: SELF DECLARATION LEGAL.pdf10 Jan 2023
Details of encumbrances concerned to LegalFile: SELF DECLARATION LEGAL.pdf10 Jan 2023
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf10 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: img002.pdf9 Jan 2023
Building plan approvalFile: NA Order_CompressPdf.pdf8 Jan 2023
Building plan approvalFile: Layout 1.pdf8 Jan 2023
Layout approvalFile: scan 1-20.pdf8 Jan 2023
Layout approvalFile: scan 2-20.pdf8 Jan 2023
Layout approvalFile: scan 3-20.pdf8 Jan 2023
Layout approvalFile: scan 4-20.pdf8 Jan 2023
Layout approvalFile: scan 13-20_E WING.pdf8 Jan 2023
Layout approvalFile: scan 14-20_E WING.pdf8 Jan 2023
PAN CardFile: 1 PAN Card.pdf8 Jan 2023
Details of encumbrances concerned to FinanceFile: Encumbrance wing E.pdf8 Jan 2023
Details of encumbrances concerned to LegalFile: Encumbrance wing E.pdf8 Jan 2023
Copy of Layout Approval (in case of layout)File: scan 1-20.pdf8 Jan 2023
Copy of Layout Approval (in case of layout)File: scan 2-20.pdf8 Jan 2023
Copy of Layout Approval (in case of layout)File: scan 3-20.pdf8 Jan 2023
Copy of Layout Approval (in case of layout)File: scan 4-20.pdf8 Jan 2023

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
ROSHAN ONE WING A AND WING DGAT NO 1 VARALE TALUKA KHED PUNE 410501176CompletedMay 2017Late, Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ROSHAN MILESTONE WING E on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near TATHWADE13,700+ in Pune

2 kmROSHAN MILESTONE WING ECompleted 90Lapsed / revoked 37Other 83Dot size: filed unitsN

Filed coordinates, straight-line distance. 210 registered projects within 2 km.

Builder: RAHUL BHAGWANDAS SANKLA

RAHUL BHAGWANDAS SANKLA has 10 registrations on MahaRERA, including ROSHAN ONE WING B and ROSHAN ONE WING C. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if ROSHAN MILESTONE WING E is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ROSHAN MILESTONE WING E?

The registered promoter entity is RAHUL BHAGWANDAS SANKLA, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ROSHAN MILESTONE WING E?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ROSHAN MILESTONE WING E?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ROSHAN MILESTONE WING E?

The professionals named in the filing: Architect: Cubix Architects Associates; Architect: Patil & Bugade Architects + Interior Designers; Engineer: MAYUR SATISH DUDHEDIA; Chartered Accountant: CA Akshay Gandhi; Chartered Accountant: CA Swapnil Bhosale. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ROSHAN MILESTONE WING E?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ROSHAN MILESTONE WING E. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ROSHAN MILESTONE WING E to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.