Home / Browse projects / Mumbai Suburban, Maharashtra / Rose Garden

Completed No litigation declared Residential / Group Housing project

Rose Garden

By Vinayaka Realtors and Developers

RG-MH-14418 · RERA P51800022587 · Last updated on MahaRERA portal: 6 Apr 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 27 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Mar 2026Possession promisedregistration recorded completed
9 of 9Construction stages doneevery applicable stage filed complete
25 of 25Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 75 documents Report an error

Rose Garden is a Residential / Group Housing project by Vinayaka Realtors and Developers in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800022587 on 9 Oct 2019. The registration is recorded completed; possession was promised by 31 Mar 2026. The completion date has moved by 27 months from the original filing. 0 of the 25 units on this registration are recorded sold or booked, and 9 of 9 construction stages are filed complete.

At a glance

Project

  • NameRose Garden
  • TypeResidential / Group Housing
  • Location
    • Marol Bazar Road
    • Marol
    • Andheri
    • Mumbai Suburban
    • 400059
  • Pincode400059
  • RERA no.P51800022587
  • ReraGenie IDRG-MH-14418

Builder

  • NameVinayaka Realtors and Developers
  • Entity typePartnership
  • PartnerVikrant Uday Kale
  • Other registrations3 more →
  • Completed2 of 4
  • No longer live2 lapsed, de-registered or revoked

Key dates

this monthRegisteredOct 2019First promiseDec 2023Revised toMar 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on9 Oct 2019
  • Promised completion31 Mar 2026
  • Revised completionRevised to 31 Mar 2026 (originally 30 Dec 2023)
  • Buildings1 building record
  • Documents filed75 files

Current status

0%0 of 25 units booked
100.0%Work done, per cost certificate

Figures as on 6 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Rose GardenNA5525025

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 6 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 9 construction stages are filed complete.

Rose Garden: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 6 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership8

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area539 sq m
Land owned byNot the promoter
Named landowners8
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on31 Mar 2026
LandownerVillageDistrict
Mrs.Thelma Miltond D' MelloAndheriMumbai Suburban
Mr Martin Francis D' MelloAndheriMumbai Suburban
MRS Doreen Francis D' MelloAndheriMumbai Suburban
Mr Sylvester Francis D MelloAndheriMumbai Suburban
Mr Raymond Francis D MelloAndheriMumbai Suburban
Mrs Cynthia BrothwickAndheriMumbai Suburban
Mr Lenon Milton D MelloAndheriMumbai Suburban
Mrs Mishel Jude RODRIQUESAndheriMumbai Suburban

Approvals and building plan

Permissible FSI1043.75
Proposed, not sanctioned1,044 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBKC Naman Branch, Naman Chamber, C-32, Mumbai-400051
Estimated costRs 3.02 cr
Cost incurredRs 3.02 cr
Work done100.0%
BuildingWingEstimatedIncurred
Rose GardenNARs 2.65 crRs 2.65 cr
-NARs 37.10 lakhRs 37.10 lakh

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTejas Arun Chhadva
EngineerMs S V Patel & Associates
EngineerBUILD MATRIX
Chartered AccountantMS R K Khan & Co
Chartered AccountantJAIN ANIL JAIN
PartnerRole in project
Vinayaka Realtors and Developers-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800018250Dec 2023 → Dec 2024

Reason as filed by the promoterDUE TO FSI ISSUE THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME.

EXT51800025442Dec 2023 → Sep 2025

Reason as filed by the promoterThe project work is delayed due to approval and sanctioned from authorities . The project 90 % of the work is completed just few works is lined up in few months for approval.

EA13102518107Dec 2023 → Mar 2026

Reason as filed by the promoterWAITING FOR OC REST ALL WORK IS DONE AND APPLIED FOR ALL NOC BUT CFO NOC IS ABOUT TO COME .

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Sep 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Feb 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Feb 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 11 Nov 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed75

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupational CertificateFile: OC ROSE GARDEN (1).pdf6 Apr 2026
Withdrawal Update Form 1File: FORM 1 ARCHITECT CERTIFICATE DECEMBER.pdf26 Mar 2026
Withdrawal Update Form 2File: FORM 2 DECEMBER.pdf26 Mar 2026
Withdrawal Update Form 3File: FORM 3.pdf26 Mar 2026
Layout approvalFile: APPROVED PLAN ROSE GARDEN_compressed.pdf27 Feb 2026
Building plan approvalFile: APPROVED PLAN ROSE GARDEN_compressed.pdf27 Feb 2026
Form 5 (FY 2024-2025)File: FORM 5 ROSE GARDEN (1) (1) (1).pdf14 Nov 2025
Commencement certificateFile: COMMENCEMENT CERTIFICATE ROSE GARDEN.pdf11 Nov 2025
Withdrawal Update Form 1File: FORM 1.pdf13 Oct 2025
Withdrawal Update Form 1File: FORM 1.pdf13 Oct 2025
Withdrawal Update Form 2File: FORM 2.pdf13 Oct 2025
Withdrawal Update Form 2File: FORM 2 JUNE.pdf13 Oct 2025
Withdrawal Update Form 3File: FORM 3.pdf13 Oct 2025
Withdrawal Update Form 3File: FORM 3.pdf13 Oct 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold And Unsold Rose.pdf31 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ROSE GARDEN.pdf7 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ROSE (1).pdf7 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2 A CERTIFICATE.pdf7 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Rose Garden.pdf28 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate Rose garden.pdf30 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 VINAYAKA REALTORS AND DEVELOPERS.pdf30 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf30 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 vinayaka DEC 2023.pdf30 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: DocScanner 25-Dec-2023 3-42 pm.pdf5 Jan 2024
Layout approvalFile: Drawing (2) MAROL APPROVED PLAN (1)_1-1.pdf3 Jan 2024
Building plan approvalFile: Drawing (2) MAROL APPROVED PLAN (1)_2-end.pdf3 Jan 2024
Copy of Layout Approval (in case of layout)File: Drawing (2) MAROL APPROVED PLAN (1)_1-1.pdf3 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: Drawing (2) MAROL APPROVED PLAN (1)_2-end.pdf3 Jan 2024
Commencement Certificates / NA Order for plotted developmentFile: 2386429_FurtherCC_signed marol.pdf3 Jan 2024
Declaration in FORM BFile: FORM B (9).pdf2 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A - Site Supervisor Certificate_ 3_March 2023.pdf2 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: DocScanner 25-Dec-2023 1-36 pm.pdf2 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: DocScanner 25-Dec-2023 1-36 pm(1).pdf2 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: DocScanner 25-Dec-2023 1-37 pm.pdf2 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architecture (2).pdf29 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer (2).pdf29 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: rose garden form 5.pdf29 Dec 2023
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf5 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 (2).pdf5 Dec 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: SOLD UNSOLD.pdf5 Dec 2023
Declaration in FORM BFile: ilovepdf_merged (76)_compressed.pdf22 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1.pdf22 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2.pdf22 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3.pdf22 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4.pdf22 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 5.pdf22 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 6.pdf22 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7.pdf22 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 - 1.pdf22 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2-2.pdf22 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2- 3.pdf22 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A - 1.pdf22 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A -2.pdf22 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A - 3.pdf22 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 (2).pdf22 Nov 2023
Declaration about Commencement CertificateFile: declaration of cc.pdf21 Nov 2023
CERSAI detailsFile: cersai letter.pdf21 Nov 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: bank letter.pdf21 Nov 2023
Layout approvalFile: LAYOUT-min.pdf28 Sep 2019
Building plan approvalFile: LAYOUT-min.pdf28 Sep 2019
PAN CardFile: FIRM Pan card.pdf28 Sep 2019
Copy of the legal title reportFile: LEGAL TITLE DEED.pdf28 Sep 2019
Copy of the legal title reportFile: dgpa 1.pdf28 Sep 2019
Copy of the legal title reportFile: dgpa 2.pdf28 Sep 2019
Copy of the legal title reportFile: dgpa 3.pdf28 Sep 2019
Copy of the legal title reportFile: dgpa 4.pdf28 Sep 2019
Copy of the legal title reportFile: dgpa 5.pdf28 Sep 2019
Copy of the legal title reportFile: dgpa 6.pdf28 Sep 2019
Copy of Layout Approval (in case of layout)File: LAYOUT-min.pdf28 Sep 2019
Building Plan Approval / NA Order for plotted developmentFile: LAYOUT-min.pdf28 Sep 2019
Declaration in FORM BFile: Form - B (1).pdf28 Sep 2019
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca certificate.pdf28 Sep 2019
Proforma of Allotment letterFile: ATS.pdf28 Sep 2019
Details of encumbrancesFile: Details of Encumbrance.pdf27 Sep 2019
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf27 Sep 2019

How this compares with Mumbai Suburban

0%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 27 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Rose Garden on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Marol6,700+ in Mumbai Suburban

Builder: Vinayaka Realtors and Developers

VINAYAKA REALTORS AND DEVELOPERS has 4 registrations on MahaRERA, including SOLOMON RESIDENCY and Nandadeep Residency. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Rose Garden is delayed beyond 31 Mar 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Rose Garden?

The registered promoter entity is Vinayaka Realtors and Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Rose Garden?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Rose Garden?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Rose Garden?

The professionals named in the filing: Architect: Tejas Arun Chhadva; Engineer: Ms S V Patel & Associates; Engineer: BUILD MATRIX; Chartered Accountant: MS R K Khan & Co; Chartered Accountant: JAIN ANIL JAIN. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Rose Garden?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Rose Garden. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Rose Garden to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.