Home / Browse projects / Nashik, Maharashtra / ROONGTA SHOPPING HUB APARTMENT
ROONGTA SHOPPING HUB APARTMENT
RG-MH-13281 · RERA P51600024436 · Last updated on MahaRERA portal: 18 Nov 2024
Source: official MahaRERA filing
Red flags
- 65 complaints at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
- All 9 earlier projects delivered on promise
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ROONGTA SHOPPING HUB APARTMENT is a Commercial project by ROONGTA HOMES LLP in Nashik, Maharashtra, registered with MahaRERA as P51600024436 on 13 Feb 2020. The registration is recorded completed; possession was promised by 30 Dec 2024. 65 complaints are on record with the regulator.
At a glance
Project
- NameROONGTA SHOPPING HUB APARTMENT
- TypeCommercial
- Location
- NASHIK
- 422009
- Pincode422009
- RERA no.P51600024436
- ReraGenie IDRG-MH-13281
Builder
- NameROONGTA HOMES LLP
- Entity typePartnership
- GSTIN27AAUFR4502Q2ZE
- GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- PartnersAKHIL LALIT ROONGTA, LALIT SATYANARAYAN ROONGTA, NIKHIL LALIT ROONGTA
- Other registrations25 more →
- Completed25 of 26
- Declared earlier projects9 →
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on13 Feb 2020
- Promised completion30 Dec 2024
- Revised completionNone
- Buildings1 building record
- Documents filed68 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| ROONGTA SHOPPING HUB APARTMENT | NA | 11 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 18 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
ROONGTA SHOPPING HUB APARTMENT: 82% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 18 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 100% |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | M/S KABRE CONSULTANTS |
| Engineer | AMOL YADAVRAO BHALERAO |
| Chartered Accountant | Anand Rathi & Associates Chartered Accountants |
| Chartered Accountant | M/s. Pravin R.Rathi & Associates, Chartered Accountants |
| Partner | Role in project |
|---|---|
| ROONGTA HOMES LLP | - |
Complaints filed with MahaRERA65
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12502444 | ROONGTA HOMES LLP | PRAFULL BHIMRAJ SAWANT | 17/07/2025 |
| CC12503636 | ROONGTA HOMES LLP | OMKAR DNYANESHWAR DEVARGAONKAR AND POONAM OMKAR DEVARGAONKAR | 13/10/2025 |
| CC12503637 | ROONGTA HOMES LLP | MR SHAMKANT CHUDAMAN PATIL AND MRS GAYATRI SHAMKANT PATIL | 13/10/2025 |
| CC12603161 | ROONGTA HOMES LLP | RAJENDRA SUDHAKAR GOSAVI | 27/05/2026 |
| CC12503859 | ROONGTA HOMES LLP | CHANDRASHEKHAR KRISHNA PATIL | 03/11/2025 |
| CC12503989 | ROONGTA HOMES LLP | SWAPNIL SUDAM KHAIRNAR | 12/11/2025 |
| CC12504003 | ROONGTA HOMES LLP | GOKUL GANPAT YEOLE | 13/11/2025 |
| CC12600088 | ROONGTA HOMES LLP | AJAY BHALCHANDRA WANI | 06/01/2026 |
| CC12600090 | ROONGTA HOMES LLP | PARAG VASANTRAO MORE | 06/01/2026 |
| CC12600089 | ROONGTA HOMES LLP | MR BHAURAO PUNDLINK SONAWANE AND MRS ANITA BHAURAO SONAWANE | 06/01/2026 |
| CC12600103 | ROONGTA HOMES LLP | VARSHADA BHUSHAN SONJE | 07/01/2026 |
| CC12600105 | ROONGTA HOMES LLP | MRS VIDYA DILIP GHODKE | 07/01/2026 |
| CC12600324 | ROONGTA HOMES LLP | MR NILESH KESHAV TRAMBAKE AND MR MOHAN PRABHAKAR KALE | 17/01/2026 |
| CC12600326 | ROONGTA HOMES LLP | SHILPA ASHOK PAGARE | 17/01/2026 |
| CC12600327 | ROONGTA HOMES LLP | Rameshwar Kachardas Jain | 17/01/2026 |
| CC12602723 | ROONGTA HOMES LLP | MRS SMITA SANDIPKUMAR BHOSALE | 10/05/2026 |
| CC12602727 | ROONGTA HOMES LLP | MRS JYOTI SWAPNIL NASIKKAR AND MR SWAPNIL ASHOK NASIKKAR | 10/05/2026 |
| CC12602728 | ROONGTA HOMES LLP | MR KIMAY BHALCHANDRA GORE AND MR UJWAL BHALCHANDRA GORE | 10/05/2026 |
| CC12602732 | ROONGTA HOMES LLP | MR ASHISH RAJNIKANT SHARMA | 10/05/2026 |
| CC12602835 | ROONGTA HOMES LLP | MR DAGADU ONKAR WANI AND MR BHUSHAN DAGADU WANI | 14/05/2026 |
| CC12602836 | ROONGTA HOMES LLP | MR ANIL BHARAT SALUNKE | 14/05/2026 |
| CC12602837 | ROONGTA HOMES LLP | MISS BAHAR RAFIK KAZI ALIAS MRS BAHAR MOHSIN SHAIKH | 14/05/2026 |
| CC12602832 | ROONGTA HOMES LLP | MR RAJENDRA BHAGWANT BAGUL | 14/05/2026 |
| CC12602834 | ROONGTA HOMES LLP | MR SANDEEP BALASAHEB BHARATE | 14/05/2026 |
| CC12602833 | ROONGTA HOMES LLP | MRS SAVITA DEEPAK PUND | 14/05/2026 |
| CC12603156 | ROONGTA HOMES LLP | MR ARUN DEVU KHAMBALKAR | 27/05/2026 |
| CC12603158 | ROONGTA HOMES LLP | MR ATUL BALNATH MALI AND MR BALNATH GANPAT MALI | 27/05/2026 |
| CC12603155 | ROONGTA HOMES LLP | MRS KUMUDINI THOMSON NAIK | 27/05/2026 |
| CC12603157 | ROONGTA HOMES LLP | MRS VAISHALI MOTILAL SONAWANE ALIAS MRS ANVITA SWAPNIL RAUT AND MR SWAPNIL SHRIKANT RAUT | 27/05/2026 |
| CC12603159 | ROONGTA HOMES LLP | MR SHADUL HABIBSAHEB SHAIKH | 27/05/2026 |
| CC12603165 | ROONGTA HOMES LLP | HARESH TUKARAM YEOLE | 27/05/2026 |
| CC12603167 | ROONGTA HOMES LLP | MR SUNIL SUKHDEV NARSINGE | 27/05/2026 |
| CC12603168 | ROONGTA HOMES LLP | JIGISHA MUKESH MAHAJAN | 27/05/2026 |
| CC12603169 | ROONGTA HOMES LLP | MR PRAKASH KHANDERAO AGHAV | 27/05/2026 |
| CC12603200 | ROONGTA HOMES LLP | SHAMRAO SHANKAR GAIDHANI | 28/05/2026 |
| CC12603201 | ROONGTA HOMES LLP | MAHESH RAVINDRA MANKE | 28/05/2026 |
| CC12603202 | ROONGTA HOMES LLP | VRUSHALI SHANTARAM SALVE | 28/05/2026 |
| CC12603756 | ROONGTA HOMES LLP | MR SAGAR BHIKAJI BHANGARE AND MRS RUTUJA SAGAR BHANGARE | 18/06/2026 |
| CC12603758 | ROONGTA HOMES LLP | YOGESH GANPAT SHELAR | 18/06/2026 |
| CC12603759 | ROONGTA HOMES LLP | SHANTARAM ANANDRAO AHIRE | 18/06/2026 |
| CC12603761 | ROONGTA HOMES LLP | MR IBRAHIM AHEMAD SAYYED AND MRS MAHEJABIN IBRAHIM SAYYED | 18/06/2026 |
| CC12603763 | ROONGTA HOMES LLP | MR RAJU JAGANNATH SARDAR AND MRS SUNITA RAJU SARDAR | 18/06/2026 |
| CC12603768 | ROONGTA HOMES LLP | MRADULA SUBHASH CHANDRA | 18/06/2026 |
| CC12603769 | ROONGTA HOMES LLP | MR PURUSHOTTAM PUNDALIK MORE AND MRS VAISHALI PURUSHOTTAM MORE | 18/06/2026 |
| CC12603774 | ROONGTA HOMES LLP | PRASHANT SURESH ASHTIKAR | 18/06/2026 |
| CC12603814 | ROONGTA HOMES LLP | SUMANBAI GULABSING GIRASE | 20/06/2026 |
| CC12603867 | ROONGTA HOMES LLP | AZIM KASAM MUJAWAR | 22/06/2026 |
| CC12603869 | ROONGTA HOMES LLP | DR SONALI BHAGWATRAO ABHANG ALIAS DR SONALI GOPAL UPADHYE (Allottee) | 22/06/2026 |
| CC12603866 | ROONGTA HOMES LLP | MUJIB HABIB PATHAN | 22/06/2026 |
| CC12603868 | ROONGTA HOMES LLP | MRS ARCHANA RAJESH DONGRE AND MR RAJESH PUSHPARAJ DONGRE | 22/06/2026 |
| CC12603876 | ROONGTA HOMES LLP | MR SHANTARAM SHRAVAN SALVE AND MRS LATIKA SHANTARAM SALVE | 23/06/2026 |
| CC12603907 | ROONGTA HOMES LLP | MR SAGAR DEEPAK SASWADE AND MRS SAPNA SAGAR SASWADE | 24/06/2026 |
| CC12603909 | ROONGTA HOMES LLP | MR UJWAL NAMDEORAO WATGULE | 24/06/2026 |
| CC12603916 | ROONGTA HOMES LLP | RAMNATH BALAJI GOSAVI | 24/06/2026 |
| CC12604221 | ROONGTA HOMES LLP | SANGITA BHIMRAO SALVE | 06/07/2026 |
| CC12603967 | ROONGTA HOMES LLP | MRS APARNA CHANDRASHEKHKAR DHARMADHIKARI AND MR CHANDRASHEKHAR SHANTARAM DHARMADHIKARI | 26/06/2026 |
| CC12603965 | ROONGTA HOMES LLP | MR ARIF BASHIR MANIYAR | 26/06/2026 |
| CC12603966 | ROONGTA HOMES LLP | MR AKSHAY SANTOSH KALANTRI | 26/06/2026 |
| CC12603974 | ROONGTA HOMES LLP | MRS PRABHAVATI PRAKASH WANI | 26/06/2026 |
| CC12603973 | ROONGTA HOMES LLP | VINOD SHANKAR SALVE | 26/06/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 28 Jan 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 28 Jan 2020 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 28 Jan 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 28 Jan 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 3 Nov 2023
Documents filed68
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5-RSH-FY 24-25.pdf | 18 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5-RSH-FY 24-25.pdf | 18 Nov 2024 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: INDEX 2.pdf | 14 Jun 2024 |
| Status of ConveyanceFile: INDEX 2.pdf | 14 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A_RSH_FY 23-24.pdf | 1 May 2024 |
| CERSAI detailsFile: CERSAI_RSH.pdf | 27 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: RSH_March 23.pdf | 22 Apr 2024 |
| OtherFile: Form 2A_RSH_FY 23-24.pdf | 22 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RSH FORM 2 Q1.pdf | 13 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RSH FORM 2 Q2.pdf | 13 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RSH Q2 (1).pdf | 5 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RSH 01072023.pdf | 3 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Q1.pdf | 3 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Q2.pdf | 3 Jan 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: ROONGTA SHOPPING HUB COMPLETION.pdf | 3 Nov 2023 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 RSH.pdf | 3 Nov 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RSH.pdf | 30 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RSH FORM 3 Q4.pdf | 24 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: RSH FORM 5 FY 22-23.pdf | 24 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: RSH.pdf | 19 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: RHLLP HUB 30062023 F.pdf | 26 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RSH FORM 1.pdf | 15 May 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM -2A -RSH MAR -2021.pdf | 21 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM-2 A RSH - JUNE -2020.pdf | 21 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM -2A -M RSH SEP -2020.pdf | 21 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM -2A -RSH DEC-2020.pdf | 21 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2 A- RSH- MAR-22.pdf | 21 Apr 2023 |
| CERSAI detailsFile: CERSAI_RSH.pdf | 21 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: rsh sold 31032023.pdf | 21 Apr 2023 |
| OtherFile: RSH.pdf | 21 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RSH-Q3.pdf | 25 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: RSH SOLD 31122023.pdf | 16 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RSH Q3.pdf | 11 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 20230221082421.pdf | 21 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 RSH 21-22.pdf | 12 Dec 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RSH FORM 3.pdf | 4 Dec 2022 |
| Disclosure of sold/ booked inventoryFile: RSH-SEP-22.pdf | 14 Oct 2022 |
| Disclosure of sold/ booked inventoryFile: SHOOPING HUB.pdf | 7 Jul 2022 |
| OtherFile: FORM 2 A- RSH- MAR-22.pdf | 9 Apr 2022 |
| Disclosure of sold/ booked inventoryFile: SOLD INVENTERY - RSH -MAR-22.pdf | 8 Apr 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: RSH FY 20-21.pdf | 21 Feb 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 20220109044238 (5).pdf | 9 Jan 2022 |
| Disclosure of sold/ booked inventoryFile: RSH_merged.pdf | 5 Jan 2022 |
| Disclosure of sold/ booked inventoryFile: RSH_compressed.pdf | 7 Oct 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RSH.pdf | 7 Oct 2021 |
| OtherFile: FORM- 2A RSH -SEP-21.pdf | 5 Oct 2021 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: declaration.pdf | 26 Aug 2021 |
| Disclosure of sold/ booked inventoryFile: RSH_compressed.pdf | 15 Aug 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ROONGTA SHOPPING HUB APARTMENT.pdf | 15 Aug 2021 |
| OtherFile: SHOPPING HUB- JUNE-21.pdf | 27 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM -5 RSH-19-20.pdf | 3 Apr 2021 |
| OtherFile: FORM -2A -M RSH SEP -2020.pdf | 3 Apr 2021 |
| OtherFile: FORM -2A -RSH DEC-2020.pdf | 3 Apr 2021 |
| OtherFile: FORM -2A -RSH MAR -2021.pdf | 3 Apr 2021 |
| OtherFile: FORM-2 A MEJESTIC - JUNE -2020.pdf | 22 Mar 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM-2 A RSH - MAR -2020.pdf | 24 Aug 2020 |
| Proforma of Allotment letterFile: BASIC DRAFT-RSH.pdf | 14 Mar 2020 |
| PAN CardFile: PANCARD.pdf | 9 Feb 2020 |
| Building plan approvalFile: building plans.pdf | 28 Jan 2020 |
| Layout approvalFile: layout.pdf | 28 Jan 2020 |
| Copy of the legal title reportFile: title.pdf | 28 Jan 2020 |
| Copy of Layout Approval (in case of layout)File: layout.pdf | 28 Jan 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: building plans.pdf | 28 Jan 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement.pdf | 28 Jan 2020 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERT.pdf | 28 Jan 2020 |
| Details of encumbrancesFile: NON ENCUMBRANCE.pdf | 27 Jan 2020 |
| Declaration in FORM BFile: FORM B.pdf | 27 Jan 2020 |
| Proforma of Allotment letterFile: PROFORMA ALLOTMENT.pdf | 27 Jan 2020 |
Promoter's earlier projects9
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| SHREE TIRUMALA GULMOHAR APARTMENT | Division Makhmalabad Shiwar NASHIK Taluka NASHIK Dist NASHIK | 156 | Completed | Apr 2022 | Aug 2020 |
| SHREE TIRUMALA PARAMOUNT APARTMENT | Taluka NASHIK Dist NASHIK-422009 | 173 | Completed | Jun 2021 | Feb 2020 |
| SHREE TIRUMALA REGENCY APARTMENT | Deepali Nagar NASHIK Taluka NASHIK Dist NASHIK 422009 | 50 | Completed | Dec 2020 | May 2020 |
| ROONGTA IMPERIA APARTMENT | NASHIK 422001 | 112 | Completed | Jul 2020 | Mar 2019 |
| ROONGTA HORIZON APARTMENT | NASHIK 422001 | 112 | Completed | Jul 2020 | Mar 2019 |
| SHREE TIRUMALA PLATINUM APARTMENT | COLLEGE ROAD NASHIK 422005 | 10 | Completed | May 2020 | Dec 2018 |
| SHREE TIRUMALA PARADISE APARTMENT | CHETANA NAGAR NASHIK 422009 | 28 | Completed | Sep 2019 | Nov 2018 |
| SHREE TIRUMALA HARINIWAS APARTMENT | SR.NO.78 PLOT NO.83 SATPUR NASHIK | 42 | Completed | Mar 2019 | May 2018 |
| SHREE TIRUMALA SWASTIK APARTMENT | INDIRA NAGAR NASHIK | 28 | Completed | Dec 2018 | Jun 2018 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nashik
Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.
Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 25 other registrations, which the RERA portal never shows together
- All 68 filed documents as one ZIP, foldered, with a manifest
Keep ROONGTA SHOPPING HUB APARTMENT on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NASHIK4,100+ in Nashik
STAR WORLD
DEEPAK KALYANJI CHANDE
VRAJ CENTRAL VISTA
DHAIRYA DEVELOPERS
ROONGTA TECHONE APARTMENT
SHREE TIRUMALA BUILDCON
VRAJ CAPITAL
KAPILAVASTU CREATORS
MAA BHAGWATI RESIDENCY APARTMENT
ROONGTA LANDMARKS LLP
THREE LEAVES PHASE ONE
DEEPAK INFRA AND HOMES PRIVATE LIMITED
See every Nashik project, with the district possession charts
Builder: ROONGTA HOMES LLP
ROONGTA HOMES LLP has 26 registrations on MahaRERA, including SHREE TIRUMALA SWASTIK APARTMENT and SHREE TIRUMALA PARADISE APARTMENT. Its filings disclose 9 earlier MahaRERA projects: declares 9 of 9 past projects completed on time. Read the full track record. See more projects on the Nashik district page.
Frequently asked questions
What are my rights if ROONGTA SHOPPING HUB APARTMENT is delayed beyond 30 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ROONGTA SHOPPING HUB APARTMENT?
The registered promoter entity is ROONGTA HOMES LLP, a partnership as per the filing. Its GSTIN 27AAUFR4502Q2ZE can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ROONGTA SHOPPING HUB APARTMENT?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against ROONGTA SHOPPING HUB APARTMENT?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for ROONGTA SHOPPING HUB APARTMENT?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ROONGTA SHOPPING HUB APARTMENT?
The professionals named in the filing: Architect: M/S KABRE CONSULTANTS; Engineer: AMOL YADAVRAO BHALERAO; Chartered Accountant: Anand Rathi & Associates Chartered Accountants; Chartered Accountant: M/s. Pravin R.Rathi & Associates, Chartered Accountants. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ROONGTA SHOPPING HUB APARTMENT?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback