Home / Browse projects / Nashik, Maharashtra / ROONGTA FUTUREX APARTMENT

Completed No litigation declared Commercial project

ROONGTA FUTUREX APARTMENT

By ROONGTA LANDMARKS LLP

RG-MH-13855 · RERA P51600029167 · Last updated on MahaRERA portal: 23 Nov 2024

Source: official MahaRERA filing

Red flags

  • 18 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 2 earlier projects delivered on promise

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Apr 2026Possession promisedregistration recorded completed
9 of 11Construction stages donefurthest along: Podiums (if any), 0%
18Complaints at MahaRERAon this registration
Jump to the 58 documents Report an error

ROONGTA FUTUREX APARTMENT is a Commercial project by ROONGTA LANDMARKS LLP in Nashik, Maharashtra, registered with MahaRERA as P51600029167 on 3 May 2021. The registration is recorded completed; possession was promised by 30 Apr 2026. 18 complaints are on record with the regulator.

At a glance

Project

  • NameROONGTA FUTUREX APARTMENT
  • TypeCommercial
  • Location
    • NASHIK
    • 422009
  • Pincode422009
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51600029167
  • ReraGenie IDRG-MH-13855

Builder

  • NameROONGTA LANDMARKS LLP
  • Entity typePartnership
  • PartnersAKHIL LALIT ROONGTA, NIKHIL LALIT ROONGTA, LALIT ROONGTA
  • Other registrations5 more →
  • Completed4 of 6
  • Past their filed date1
  • Declared earlier projects2 →

Key dates

this monthRegisteredMay 2021PromisedApr 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on3 May 2021
  • Promised completion30 Apr 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed58 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ROONGTA FUTUREX APARTMENTNA120000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 23 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

ROONGTA FUTUREX APARTMENT: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 23 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,481 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI14066.08
Proposed, not sanctioned14,038 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchINDIRA NAGAR NASHIK

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSAGAR KABRE
EngineerMR SHAILESH POPATRAO DHUMNE
Chartered AccountantANAND RATHI & ASSOCIATES CHARTERED ACCOUNTANT
Chartered AccountantPravin R. Rathi & Associates
PartnerRole in project
ROONGTA LANDMARKS LLP-

Complaints filed with MahaRERA18

Case no.ComplainantRespondentFiled
CC12502611ROONGTA LANDMARKS LLPVISHAL DILIPRAO NIMBALKAR AND SUJATA VISHAL NIMBALKAR28/07/2025
CC12503638ROONGTA LANDMARKS LLPANKIT DNYANESHWAR CHINCHOLE13/10/2025
SM12500119Ram GawaliROONGTA LANDMARKS LLP09/09/2025
SM12500120Ram GawaliROONGTA LANDMARKS LLP09/09/2025
CC12503963ROONGTA LANDMARKS LLPVINOD CHACKO12/11/2025
CC12504015ROONGTA LANDMARKS LLPLAXMIKANT HARIBHAU SHINDE AND PRAMILA LAXMIKANT SHINDE14/11/2025
CC12504048ROONGTA LANDMARKS LLPMRS ASHWINI SHANTA ATRE17/11/2025
CC12504054ROONGTA LANDMARKS LLPMR VENKAT NARAYAN DEOKAMBLE17/11/2025
CC12504051ROONGTA LANDMARKS LLPMR SACHIN BHAGWAN PORJE17/11/2025
CC12504105ROONGTA LANDMARKS LLPMRS SHITAL GAURAV KAMBLE AND MR GAURAV NATHU KAMBLE21/11/2025
CC12504109ROONGTA LANDMARKS LLPMR NIKHIL RAMESH SANGLE22/11/2025
CC12504110ROONGTA LANDMARKS LLPMR SAMADHAN PUNDLIK PATIL AND MRS VARSHA SAMADHAN PATIL22/11/2025
CC12504111ROONGTA LANDMARKS LLPMR SANJAY BALU MALUNJKAR22/11/2025
CC12600077ROONGTA LANDMARKS LLPMRS HARSHADA SURAJ BODKE AND MR SURAJ VALMIK BODKE05/01/2026
CC12600078ROONGTA LANDMARKS LLPMR SATISH PANDURANG PATIL05/01/2026
CC12504323ROONGTA LANDMARKS LLPMRS AISHWARYA BIHARILAL BAGADE06/12/2025
CC12600314ROONGTA LANDMARKS LLPMR HARIBHAU RAMNATH WELJALI16/01/2026
CC12600322ROONGTA LANDMARKS LLPMISS URMILA SOMNATH KAPASE ALIAS MRS URMILA ESHWAR JAIN17/01/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 13 Apr 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Apr 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Apr 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Apr 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 3 Nov 2023

Documents filed58

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 FUTUREX.pdf23 Nov 2024
Status of Formation of Legal Entity (Society/Co Op etc.)File: INDEX 2 DECLARATION.pdf3 May 2024
Status of ConveyanceFile: INDEX 2 DECLARATION.pdf3 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FUTUREX MAR 24.pdf1 May 2024
CERSAI detailsFile: CERSAI_FUTUREX.pdf27 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FUTUREX MAR 23.pdf25 Apr 2024
OtherFile: FUTUREX MAR 24.pdf25 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FUTUREX FORM 2 Q1.pdf13 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FUTUREX FORM 2 Q2.pdf13 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FUTUREX Q1 01072023.pdf4 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FUTUREX Q2 01102023.pdf4 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FUTUREX Q1.pdf13 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FUTUREX Q2.pdf13 Dec 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: FUTUREX completion.pdf3 Nov 2023
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 FUTUREX.pdf3 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FUTUREX.pdf30 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FUTUREX FORM 3 Q4_compressed.pdf24 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FUTUREX FORM 5 FY 22-23.pdf24 Oct 2023
Disclosure of sold/ booked inventoryFile: FUTUREX.pdf19 Oct 2023
Disclosure of sold/ booked inventoryFile: FUTUREX 30062023.pdf26 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FUTUREX.pdf15 May 2023
CERSAI detailsFile: CERSAI_FUTUREX.pdf26 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2A.pdf21 Apr 2023
Disclosure of sold/ booked inventoryFile: futurex sold 31032023.pdf21 Apr 2023
OtherFile: FUTUREX.pdf21 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FUTUREX_11zon.pdf21 Feb 2023
Disclosure of sold/ booked inventoryFile: FUTUREX SOLD UNSOLD 31122023.pdf1 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FUTUREX Q2_11zon.pdf31 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FUTUREX.pdf7 Nov 2022
Disclosure of sold/ booked inventoryFile: FUTUREX- SEP-22.pdf14 Oct 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FUTUREX FORM -3.pdf9 Aug 2022
Disclosure of sold/ booked inventoryFile: FUTUREX.pdf7 Jul 2022
Declaration about Commencement CertificateFile: FORM-D FUTUREX.pdf30 May 2022
CERSAI detailsFile: CERSAI_Search_Report_200238403681_For_Asset_Based_Search_30_05_2022_11_05_36_670.pdf30 May 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 FUTUREX F.pdf18 May 2022
Disclosure of sold/ booked inventoryFile: SOLD INVENTORY -FUTUREX-1.pdf7 Apr 2022
OtherFile: FORM-2A- FUTUREX.pdf7 Apr 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FUTUREX_compressed.pdf8 Jan 2022
Disclosure of sold/ booked inventoryFile: FUTUREX31122021.pdf5 Jan 2022
Disclosure of sold/ booked inventoryFile: FUTUREX.pdf7 Oct 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Futurex_0001_compressed.pdf7 Oct 2021
OtherFile: FORM -2 A FUTUREX -SEP-21.pdf5 Oct 2021
Disclosure of sold/ booked inventoryFile: FUTUREX.pdf15 Aug 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ROONGTA FUTUREX APARTMENT.pdf15 Aug 2021
OtherFile: FORM - 2A FUTUREX JUNE-21.pdf3 Aug 2021
Proforma of Allotment letterFile: DRAFT OF AGREEMENT OF SALE.pdf31 May 2021
Proforma of Allotment letterFile: FUTUREX-DRAFT.pdf29 Apr 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE ROONGTA FUTUREX.pdf14 Apr 2021
Building plan approvalFile: BUILDING PLAN of FUTUREX.pdf13 Apr 2021
Layout approvalFile: Layout futurex.pdf13 Apr 2021
Copy of the legal title reportFile: TITLE REPORT OF FUTUREX.pdf13 Apr 2021
Details of encumbrancesFile: SELF DECLARATION NON ENCUMBRANCE.pdf13 Apr 2021
Copy of Layout Approval (in case of layout)File: Layout futurex.pdf13 Apr 2021
Building Plan Approval / NA Order for plotted developmentFile: BUILDING PLAN of FUTUREX.pdf13 Apr 2021
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf13 Apr 2021
Declaration in FORM BFile: FORM - B FUTUREX.pdf13 Apr 2021
Proforma of Allotment letterFile: DECLARATION FOR PERFORMA OF ALLOTMENT.pdf13 Apr 2021
PAN CardFile: ROONGTA LANDMARKS LLP.pdf8 Apr 2021

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise
ProjectLocationFlatsRegisteredStatusPromisedDelivered
ROONGTA LIFESTYLE VILLASP51600030728NASHIK, Nashik42Sep 2021CompletedApr 2023Mar 2023
ROONGTA CENTRAL PARK APARTMENTP51600022518NAHSIK, Nashik194Sep 2019CompletedMar 2023Jan 2021

How this compares with Nashik

10%of Nashik projects moved their completion datethis one has not
19%of Nashik registrations have lapsed or been cancelledthis one is completed

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ROONGTA FUTUREX APARTMENT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NASHIK4,100+ in Nashik

2 kmROONGTA FUTUREX APARTMENCompleted 186Lapsed / revoked 40Other 103Dot size: filed unitsN

Filed coordinates, straight-line distance. 329 registered projects within 2 km.

Builder: ROONGTA LANDMARKS LLP

ROONGTA LANDMARKS LLP has 6 registrations on MahaRERA, including ROONGTA CENTRAL PARK APARTMENT and ROONGTA FUTUREX APARTMENT. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if ROONGTA FUTUREX APARTMENT is delayed beyond 30 Apr 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ROONGTA FUTUREX APARTMENT?

The registered promoter entity is ROONGTA LANDMARKS LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ROONGTA FUTUREX APARTMENT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against ROONGTA FUTUREX APARTMENT?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for ROONGTA FUTUREX APARTMENT?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ROONGTA FUTUREX APARTMENT?

The professionals named in the filing: Architect: SAGAR KABRE; Engineer: MR SHAILESH POPATRAO DHUMNE; Chartered Accountant: ANAND RATHI & ASSOCIATES CHARTERED ACCOUNTANT; Chartered Accountant: Pravin R. Rathi & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ROONGTA FUTUREX APARTMENT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ROONGTA FUTUREX APARTMENT. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ROONGTA FUTUREX APARTMENT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.