ROHAN NITARA - Phase B

By URBAN LIFE VENTURES

RG-MH-87964 · RERA PR1261012602175 · Last updated on MahaRERA portal: 24 Sep 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 10 cases

Clear

  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Sep 2030Possession promisedno revision filed
0 of 33Construction stages doneacross 3 buildings; furthest along: Excavation, 0%
277 of 277Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 6 documents Report an error

ROHAN NITARA - Phase B is a Residential / Group Housing project by URBAN LIFE VENTURES in Pune, Maharashtra, registered with MahaRERA as PR1261012602175 on 7 Oct 2026. Possession is promised by 30 Sep 2030. 0 of the 277 units on this registration are recorded sold or booked, and 0 of 33 construction stages are filed complete.

At a glance

Project

  • NameROHAN NITARA - Phase B
  • TypeResidential / Group Housing
  • Location
    • -
    • Nande
    • Mulshi
    • Pune
    • 412115
  • Pincode412115
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR1261012602175
  • ReraGenie IDRG-MH-87964

Builder

  • NameURBAN LIFE VENTURES
  • Entity typePartnership
  • GSTIN27AADFU1671L1ZV
  • PartnersAditya Anirudha Deshpande, Intellisense Realty LLP through its Partner Raunak Shetty, Rohan Builders & Developers Private Limited through its Director Ashwin Lunkad, Rohan Housing Private Limited through its Director Deepak Bhatewara
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

this monthRegisteredOct 2026PromisedSep 2030

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on7 Oct 2026
  • Promised completion30 Sep 2030
  • Revised completionNone
  • Buildings3 building records
  • Documents filed6 files

Current status

0%0 of 277 units booked

Figures as on 24 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing ANA181588088
Wing CNA18151030103
Wing DNA181586086

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 24 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Excavation, at 0%.

Wing A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing C0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing D0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 24 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNo0%
Water SupplyNo0%
Sewerage (Chamber, Lines, Septic Tank , STP)No0%
Storm Water DrainsNo0%
Landscaping & Tree PlantingNo0%
Street LightingNo0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNo0%
Solid Waste Management And DisposalNo0%
Water conservation /Rain water harvestingNo0%
Energy managemcntNo0%
Fire protection and fire safety requirementsNo0%
Electrical meter room, sub-station, receiving stationNo0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed549

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots549
Closed/Covered549
BuildingClosed/CoveredTotal
Wing A175175
Wing C204204
Wing D170170

Land and ownership55

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area48,567 sq m
Land owned byThe promoter, with other names on the file
Named landowners55
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on23 Sep 2026
LandownerVillageDistrict
Prashant Mohan Ranwade-Pune
Ashwini Prathamesh Shinde-Pune
Sambhaji Pandurang Ranwade-Pune
Mandakini Sambhaji Ranwade-Pune
Chandrashekhar Sambhaji Ranwade-Pune
Nikita Chandrashekhar Ranwade-Pune
Renuka Hanumanth Sarpatil-Pune
Indira Sadeep Kadam-Pune
Jayashree Tushar Deshmukh-Pune
Baban Govind Ranwade-Pune
Manisha Kisan Ranwade-Pune
Ganesh Kisan Ranwade-Pune
Komal Kisan Ranwade-Pune
Sandeep Baban Ranwade-Pune
Rohini Sandeep Ranwade-Pune
Prajwal Sandeep Ranwade-Pune
Payal Sandeep Ranwade-Pune
Vimal Arjun Ranwade-Pune
Arjun Mahadev Ranwade-Pune
Machendra Arjun Ranwade-Pune
Archana Machendra Ranwade-Pune
Dattatray Arjun Ranwade-Pune
Rupali Dattatray Ranwade-Pune
Ananda Arjun Ranwade-Pune
Vidhya Ananda Ranwade-Pune
Asha Santosh Shinde-Pune
Dattatray Kisan Matre-Pune
Rekha Dattatray Matre-Pune
Payal Dattatray Matre-Pune
Aditya Dattatray Matre-Pune
Alka Bapu Matre-Pune
Dhiraj Bapu Matre-Pune
Kalyani Bapu Matre-Pune
Suman Khandu Shinde-Pune
Muktabai Laxman Pawale-Pune
Vimal Vilas Chaudhari-Pune
Maruti Laxman Makar-Pune
Sunita Maruti Makar-Pune
Kumar Maruti Makar-Pune
Mayur Maruti Makar-Pune
Reshma Maruti Makar-Pune
Santosh Laxman Makar-Pune
Manish Santosh Makar-Pune
Sanket Santosh Makar-Pune
Pornima Santosh Makar-Pune
Mangal Bhausaheb kshirsagar-Pune
Anjana Dashrath Chavan-Pune
Chandrabhaga Laxman Makar-Pune
Bhanudas Shrihari Karanjawane-Pune
Vanita Bhanudas Karanjawane-Pune
Amruta Bhanudas Karanjawane-Pune
Shravani Bhanudas Karanjawane-Pune
Abhinav Bhanudas Karanjawane-Pune
Vaishali Rohidas Karanjawane-Pune
Ketan Rohidas Karanjawane-Pune

Approvals and building plan

Sanctioning authorityPune Metropolitan Region Development Authority, Pune
Permissible FSI21731.38
Proposed, not sanctioned21,731 sq m
Buildings approved4
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchICICI Bank Ltd., 1194/8, Ramchandra Sabhamandap, Ghole Road , Shivaji Nagar, Pune.411005

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectGNA Architects
EngineerPratik Deepak Bhatewara
Chartered AccountantPARESH R NAGAR AND COMPANY
PartnerRole in project
URBAN LIFE VENTURES-

Litigation declared10

CaseCourtStatus
84/2018Hon’ble Civil Judge, Senior Division, PuneOngoing
6291/2022Hon’ble High Court of Judicature at BombayOngoing
122/2022Hon’ble District Court, PuneOngoing
134/2026Hon’ble Civil Judge, Senior Division, PuneOngoing
388/2018Hon’ble Sub-Divisional Officer, MulshiOngoing
1070/2018Hon'ble Civil Judge Senior Division, PuneOngoing
HaNo/SR/155/271/2019/2019Tehsildar, MulshiOngoing
904/2013Hon'ble Civil Judge, Senior Division, PuneOngoing
334/2018Hon'ble Civil Judge, Senior Division, PuneOngoing
14646/2022High Court of Judicature at BombayOngoing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportNot on the file

    A lawyer's report on who owns the land and what is registered against it.

  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 Sep 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 Sep 2026
  4. Commencement CertificateNot on the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Sep 2030

Documents filed6

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration and undertaking (Annexure A)File: Annexure A - Order No 50 (4).pdf24 Sep 2026
Layout approvalFile: Plan 2.pdf23 Sep 2026
Building plan approvalFile: Plan 1.pdf11 Sep 2026
Building plan approvalFile: Plan 3-4.pdf11 Sep 2026
Building plan approvalFile: Plan 5-6.pdf11 Sep 2026
Building plan approvalFile: Plan 7.pdf11 Sep 2026

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationRegisteredStatusPromisedDelivered
Urban Life Ventures Aapli SocietyP52100006249sahakar nagar, PuneAug 2017CompletedAug 2022Registered original: Mar 2020Aug 2022

How this compares with Pune

0%of this project is bookeddistrict median 30%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,800+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ROHAN NITARA - Phase B on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Nande13,800+ in Pune

2 kmROHAN NITARA - Phase BCompleted 12Lapsed / revoked 4Other 10Dot size: filed unitsN

Filed coordinates, straight-line distance. 26 registered projects within 2 km.

Builder: URBAN LIFE VENTURES

Urban Life Ventures has 2 registrations on MahaRERA, including Urban Life Ventures Aapli Society and ROHAN NITARA - Phase B. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if ROHAN NITARA - Phase B is delayed beyond 30 Sep 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ROHAN NITARA - Phase B?

The registered promoter entity is URBAN LIFE VENTURES, a partnership as per the filing. Its GSTIN 27AADFU1671L1ZV can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ROHAN NITARA - Phase B?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ROHAN NITARA - Phase B?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ROHAN NITARA - Phase B?

The professionals named in the filing: Architect: GNA Architects; Engineer: Pratik Deepak Bhatewara; Chartered Accountant: PARESH R NAGAR AND COMPANY. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ROHAN NITARA - Phase B?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ROHAN NITARA - Phase B. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ROHAN NITARA - Phase B to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.