Home / Browse projects / Pune, Maharashtra / RIO GREENS
RIO GREENS
RG-MH-09402 · RERA P52100010059 · Last updated on MahaRERA portal: 25 Jul 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 34 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
RIO GREENS is a Residential / Group Housing project by JAIN KUMAR DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100010059 on 23 Aug 2017. Possession was promised by 30 Dec 2023 and is now 34 months past that date. The completion date has moved by 12 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameRIO GREENS
- TypeResidential / Group Housing
- Location
- Kasarsai-Chandkhed
- Opp Indian Oil pump
- Kasarsai
- Mulshi
- Pune
- 410506
- Pincode410506
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100010059
- ReraGenie IDRG-MH-09402
Builder
- NameJAIN KUMAR DEVELOPERS
- Entity typePartnership
- PartnersARVINDKUMAR GANESHMAL JAIN, AKSHAY SANJAY GADIYA, DHIRAJ RANJITSINGH KUMAR, SIDDHARTH KEVALCHAND JAIN, NITIN RANJITSINGH KUMAR, ASHISH BHARAT JAIN
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on23 Aug 2017
- Promised completion30 Dec 2023
- Revised completionRevised to 30 Dec 2023 (originally 30 Dec 2022)
- Buildings1 building record
- Documents filed40 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| RIO GREENS | NA | 14 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 25 Jul 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
RIO GREENS: 82% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 25 Jul 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 100% |
Parking filed134
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership2
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| BALU TANAJI LANDE | Marunji | Pune |
| KALURAM TANAJI LANDE | Marunji | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | VRISHALI KAVALE |
| Engineer | GA Bhilare Consultants Pvt Ltd |
| Partner | Role in project |
|---|---|
| JAIN KUMAR DEVELOPERS | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter-COVID HIT THE SUPPLY NETWORK AS WELL AS THE FUNDS FROM CUSTOMERS. - SHORTAGE OF RESOURCES DURING AND POST COIVD PANDEMIC. -WORKERS MIGRATING TO NATIVE PLACE -PERMISSION DELAYS DUE TO LESS WORK FORCE DURING PANDEMIC -UNHEALTHY INFLATION OF PRICES OF RAW MATERIALS
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000340804 | Pallavi Laxman Veer | Jain Kumar Developers through its partner Mr. Siddharth Kevalchand Jain | 23/04/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 20 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 13 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 13 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 21 Sep 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 25 Jul 2024
Documents filed40
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC - RIO GREENS KASARSAI.pdf | 25 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 -- 30-9-23.pdf | 19 Oct 2023 |
| Certificates of CA (Form 3)File: Jain kumar deve.pdf | 19 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Jain Kumar Developers 21-22 (2).pdf | 27 Jan 2023 |
| Details of encumbrances concerned to FinanceFile: declation.pdf | 5 Nov 2022 |
| Details of encumbrances concerned to LegalFile: declation.pdf | 5 Nov 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2020 form 2a.pdf | 5 Nov 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2021 form 2 a.pdf | 5 Nov 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2022 form 2a.pdf | 5 Nov 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 2018-19_compressed.pdf | 5 Nov 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 2019-20_compressed.pdf | 5 Nov 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 2020-21_compressed.pdf | 5 Nov 2022 |
| Proforma of Agreement for saleFile: Agreement (1).pdf | 5 Nov 2022 |
| Proforma of Allotment letterFile: ilovepdf_merged (3).pdf | 5 Nov 2022 |
| Deviation Report with respect to Allotment letterFile: deviation decl.pdf | 5 Nov 2022 |
| Deviation Report with respect to model copy of AgreementFile: deviation decl.pdf | 5 Nov 2022 |
| Disclosure of sold/ booked inventoryFile: sold unsold inventory rio_compressed (1).pdf | 4 Nov 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200251063392_For_Asset_Based_Search_01_11_2022_12_51_50_951.pdf | 2 Nov 2022 |
| CERSAI detailsFile: 13 MBVA Certificate-1.pdf | 20 Oct 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: PMRDA 3RD SANCTION ORDER.pdf | 21 Sep 2022 |
| Declaration about Commencement CertificateFile: comm decl_compressed.pdf | 21 Sep 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT'S CERTIFICATE FEB 2022.pdf | 21 Sep 2022 |
| Certificates of CA (Form 3)File: Form 3 JKD_compressed (1).pdf | 21 Sep 2022 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: bank details pdf_compressed.pdf | 21 Sep 2022 |
| Certificates of CA (Form 5)File: Form 5 Jain Kumar developers.pdf | 8 Dec 2018 |
| Proforma of Allotment letterFile: ALLOTMENT LETTER AGREEMENT DRAFT.pdf | 30 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ENGINEERS CERTIFICATE.pdf | 28 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: PMRDA COMMENCEMENT CERTIFICATE.pdf | 27 Jul 2017 |
| Details of encumbrancesFile: NON ENCUMBRANCES CERTIFICATE.pdf | 25 Jul 2017 |
| Declaration in FORM BFile: PROMOTER FORM B.pdf | 25 Jul 2017 |
| PAN CardFile: JKD PAN.pdf | 23 Jul 2017 |
| Copy of the legal title reportFile: TITLE SEARCH 19-7-2017.pdf | 20 Jul 2017 |
| Certificates of CA (Form 3)File: FORM 3 - CA CERTIFIACTE.pdf | 20 Jul 2017 |
| Layout approvalFile: LAYOUTcompressed.pdf | 13 Jul 2017 |
| Building plan approvalFile: bld approval 2 compressed.pdf | 13 Jul 2017 |
| Building plan approvalFile: BUILDING APPROVAL-compressed.pdf | 13 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: LAYOUTcompressed.pdf | 13 Jul 2017 |
| Building Plan Approval (IOD)File: bld approval 2 compressed.pdf | 13 Jul 2017 |
| Building Plan Approval (IOD)File: BUILDING APPROVAL-compressed.pdf | 13 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Certificates of Architect (Form 1).pdf | 13 Jul 2017 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| ASHOKA ENCLAVE | Marunji Gaothan Marunji Next to Alard Institute Kasarsai Road Tal Mulshi Pune 411057 | 32 | Completed | May 2017 | Oct 2016 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 40 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep RIO GREENS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Opp Indian Oil pump13,700+ in Pune
Filed coordinates, straight-line distance. 8 registered projects within 2 km.
Everland
EVITA KRISALA TOWNSHIP LLP
EVERLYN
EVITA KRISALA TOWNSHIP LLP
ABHIMAAN HOMES PHASE 3
RISING PROPCON LLP
SURABHI CITY PHASE 1
Surabhi Group
ROHAN ANAND PHASE I
ROHAN BUILDERS & DEVELOPERS PRIVATE LIMITE
Urban Life Phase 1
Kakade Vtp Associates
Builder: JAIN KUMAR DEVELOPERS
JAIN KUMAR DEVELOPERS has 1 registration on MahaRERA, including RIO GREENS. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that RIO GREENS shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if RIO GREENS is delayed beyond 30 Dec 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of RIO GREENS?
The registered promoter entity is JAIN KUMAR DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in RIO GREENS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against RIO GREENS?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for RIO GREENS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at RIO GREENS?
The professionals named in the filing: Architect: VRISHALI KAVALE; Engineer: GA Bhilare Consultants Pvt Ltd. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in RIO GREENS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback