Reliable Greens
By Vijaykumar Omprakash Agarwal
RG-MH-34808 · RERA P52100053278 · Last updated on MahaRERA portal: 13 Aug 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 21 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Reliable Greens is a Residential / Group Housing project by Vijaykumar Omprakash Agarwal in Pune, Maharashtra, registered with MahaRERA as P52100053278 on 23 Oct 2023. Possession is promised by 31 Dec 2027. The completion date has moved by 21 months from the original filing. 0 of the 26 units on this registration are recorded sold or booked, and 10 of 33 construction stages are filed complete.
At a glance
Project
- NameReliable Greens
- TypeResidential / Group Housing
- Location
- Survey no-37/1/3
- Nangargaon
- Lonavala (M Cl)
- Mawal
- Pune
- 410401
- Pincode410401
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100053278
- ReraGenie IDRG-MH-34808
Builder
- NameVijaykumar Omprakash Agarwal
- Entity typeIndividual
- GSTIN27ACXPA8258P1ZL
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on23 Oct 2023
- Promised completion31 Dec 2027
- Revised completionRevised to 31 Dec 2027 (originally 31 Mar 2026)
- Buildings3 building records
- Documents filed97 files
Current status
Figures as on 13 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A Wing | NA | 3 | 2 | 9 | 0 | 9 |
| B Wing | NA | 3 | 2 | 2 | 0 | 2 |
| C Wing | NA | 3 | 2 | 15 | 0 | 15 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 13 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Staircases, at 75%.
A Wing41%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B Wing45%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 25% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 75% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
C Wing19%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 5% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 13 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed52
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| A Wing | 18 | 18 |
| B Wing | 4 | 4 |
| C Wing | 30 | 30 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| C Wing | NA | Rs 4.47 cr | Rs 41.59 lakh |
| A Wing | NA | Rs 2.68 cr | Rs 1.28 cr |
| - | NA | Rs 1.25 cr | Rs 15.66 lakh |
| B Wing | NA | Rs 59.62 lakh | Rs 27.56 lakh |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Sharwari |
| Engineer | APC ENGINEERS AND STRUCTURAL CONSULTANTS |
| Chartered Accountant | Sandeepkumar Jitendranath Ojha |
| Chartered Accountant | Hitesh Dama and Co |
| Partner | Role in project |
|---|---|
| Vijaykumar Omprakash Agarwal | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe Project was registered in the year 2023 but we only started construction from December 2024 onwards since we had to arrange funds for the construction, we have not taken any booking in the project as on date and hence consent of Allottees is not applicable and we intend to extend the period of construction till 31/12/2027. Request you to kindly approve the extension. Thanks and Regards.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 21 Aug 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 7 Jul 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 7 Jul 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 29 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed97
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 97 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form-1 30062026 signed.pdf | 13 Aug 2026 |
| Withdrawal Update Form 2File: Form-2 RCC.pdf | 13 Aug 2026 |
| Withdrawal Update Form 3File: FORM 3_CA - 30062026.pdf | 13 Aug 2026 |
| Withdrawal Update Form 1File: Form-1 30062026 signed.pdf | 7 Aug 2026 |
| Withdrawal Update Form 2File: Form-2 RCC.pdf | 7 Aug 2026 |
| Withdrawal Update Form 3File: FORM 3_CA - 30062026.pdf | 7 Aug 2026 |
| Withdrawal Update Form 1File: Form-1 31032026.pdf | 22 Apr 2026 |
| Withdrawal Update Form 2File: Form-2 31032026.pdf | 22 Apr 2026 |
| Withdrawal Update Form 3File: FORM 3_CA - 31032026.pdf | 22 Apr 2026 |
| Form 2A (FY 2025-2026)File: Form 2A 31032026.pdf | 11 Apr 2026 |
| Form 5 (FY 2025-2026)File: RELIABLE LIFESTYLE FORM 5-FY 25-26.pdf | 5 Apr 2026 |
| Withdrawal Update Form 1File: Form-1 Architect 31122025.pdf | 8 Feb 2026 |
| Withdrawal Update Form 2File: Form-2 RCC Consultant 31122025.pdf | 8 Feb 2026 |
| Withdrawal Update Form 3File: FORM 3_CA - 31122025.pdf | 8 Feb 2026 |
| Withdrawal Update Form 1File: Form-1 Architect 30092025.pdf | 13 Nov 2025 |
| Withdrawal Update Form 2File: Form-2 RCC certificate 30092025.pdf | 13 Nov 2025 |
| Withdrawal Update Form 3File: FORM 3_CA - 30092025 signed.pdf | 13 Nov 2025 |
| Withdrawal Update Form 1File: Form-1 merged 30062025.pdf | 30 Sep 2025 |
| Withdrawal Update Form 2File: Form-2 RCC 30062025.pdf | 30 Sep 2025 |
| Withdrawal Update Form 3File: FORM 3_CA - 30062025.pdf | 30 Sep 2025 |
| Form 5 (FY 2024-2025)File: Form 5 Reliable Lifestyle.pdf | 30 Sep 2025 |
| Form 5 (FY 2023-2024)File: Reliable_Lifestyle_Form_5.pdf | 30 Sep 2025 |
| Withdrawal Update Form 1File: Form-1 merged 31032025.pdf | 20 Aug 2025 |
| Withdrawal Update Form 1File: Form-1 merged 31032025.pdf | 20 Aug 2025 |
| Withdrawal Update Form 2File: Form-2 RCC.pdf | 20 Aug 2025 |
| Withdrawal Update Form 2File: Form-2 RCC.pdf | 20 Aug 2025 |
| Withdrawal Update Form 3File: CA_Certificate_compressed.pdf | 20 Aug 2025 |
| Withdrawal Update Form 3File: CA_Certificate_compressed.pdf | 20 Aug 2025 |
| Form 1File: Form-1 merged 31032025.pdf | 18 Aug 2025 |
| Form 2File: Form-2 RCC.pdf | 18 Aug 2025 |
| Form 3File: FORM 3_CA - 31032025.pdf | 18 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Quarterly declaration by Promoter.pdf | 18 Aug 2025 |
| Self-declaration of Quarterly ProgressFile: Quarterly declaration by Promoter.pdf | 18 Aug 2025 |
| Form 1File: Form-1 merged.pdf | 18 Aug 2025 |
| Form 2File: Engineer_Certificate 31032023.pdf | 18 Aug 2025 |
| Form 3File: FORM 3_CA - 31122023.pdf | 18 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Quarterly declaration by Promoter.pdf | 18 Aug 2025 |
| Form 1File: Architect Certificate All wings merged_compressed.pdf | 18 Aug 2025 |
| Form 2File: Engineer_Certificate.pdf | 18 Aug 2025 |
| Form 3File: FORM 3_CA - 31032024.pdf | 18 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Quarterly declaration by Promoter.pdf | 18 Aug 2025 |
| Form 1File: Architect certificates 30062024.pdf | 18 Aug 2025 |
| Form 2File: RCC Consultant 30062024.pdf | 18 Aug 2025 |
| Form 3File: Form 3 CA June 2024.pdf | 18 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Quarterly declaration by Promoter.pdf | 18 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Quarterly declaration by Promoter.pdf | 18 Aug 2025 |
| Form 1File: Form-1 Architect 31122024.pdf | 18 Aug 2025 |
| Form 2File: Engineer Certificate 31122024_compressed.pdf | 18 Aug 2025 |
| Form 3File: Form-3 Chartered Accountant's Certificate as on 31-12-2024.pdf | 18 Aug 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Chartered Accountant's Certificate as on 31-12-2024.pdf | 12 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Architect 31122024.pdf | 7 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate 31122024_compressed.pdf | 7 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Reliable_Lifestyle_Form_5.pdf | 28 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA.pdf | 24 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect merged.pdf | 18 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RCC Certificate.pdf | 18 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificates 30062024.pdf | 19 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA June 2024.pdf | 19 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RCC Consultant 30062024.pdf | 19 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RCC Consultant 30062024.pdf | 19 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate All wings merged_compressed.pdf | 18 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer_Certificate.pdf | 18 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_CA - 31032024.pdf | 18 Apr 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Renewal of CC 04032024.pdf | 29 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect A Wing 31032023.pdf | 29 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect B Wing 31032023.pdf | 29 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect C Wing 31032023.pdf | 29 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer_Certificate 31032023.pdf | 29 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_CA - 31122023.pdf | 29 Mar 2024 |
| Other - LegalFile: Index-II of Land.pdf | 29 Aug 2023 |
| Copy of the legal title reportFile: Legal Title report_compressed.pdf | 21 Aug 2023 |
| Details of encumbrances concerned to FinanceFile: No encumbrances merged.pdf | 8 Aug 2023 |
| Details of encumbrances concerned to LegalFile: No encumbrances merged.pdf | 8 Aug 2023 |
| Declaration about Commencement CertificateFile: Commencement certificate declaration.pdf | 8 Aug 2023 |
| CERSAI detailsFile: Declaration_for_CERSAI.pdf | 8 Aug 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest.pdf | 8 Aug 2023 |
| Proforma of Agreement for saleFile: Proforma of Agreement for Sale.pdf | 8 Aug 2023 |
| Deviation Report with respect to model copy of AgreementFile: Deviation_Report_for_Agreement_to_Sale.pdf | 8 Aug 2023 |
| Other - LegalFile: No_Encumbrance_Free_from_All_Encumbrances.pdf | 8 Aug 2023 |
| Other - FinanceFile: No_Encumbrances_Concerned_to_Finance.pdf | 8 Aug 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 97 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Reliable Greens on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Nangargaon13,700+ in Pune
Filed coordinates, straight-line distance. 25 registered projects within 2 km.
CANARY FARMS
CANARY FARMS
HRIDAAN HEIGHTS
R SQUARE BUILDERS AND DEVELOPERS
Amoda Reserve - South Park
Kalpataru Properties (Thane) Private Limit
Nakshatra Valley
Hariom Sai Developers
MANTRA DIVINE PHASE 2
MANTRA UNIVERSE PRIVATE LIMITED
EMERALD VILLAS
ASHWIN ARVIND SANGHVI
Builder: Vijaykumar Omprakash Agarwal
Vijaykumar Omprakash Agarwal has 1 registration on MahaRERA, including Reliable Greens. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Reliable Greens is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Reliable Greens?
The registered promoter entity is Vijaykumar Omprakash Agarwal, an individual as per the filing. Its GSTIN 27ACXPA8258P1ZL can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Reliable Greens?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Reliable Greens?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Reliable Greens?
The professionals named in the filing: Architect: Sharwari; Engineer: APC ENGINEERS AND STRUCTURAL CONSULTANTS; Chartered Accountant: Sandeepkumar Jitendranath Ojha; Chartered Accountant: Hitesh Dama and Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Reliable Greens?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback