Registered No litigation declared Residential / Group Housing project

REDEVLOPMENT OF PANVELKAR EMPIRE WING A WING A-1 WING B

By Om Sai Shraddha Developers

RG-MH-28478 · RERA P51700026198 · Last updated on MahaRERA portal: 11 Aug 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 36 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedmoved 36 months from the original
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
109 of 210Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 89 documents Report an error

REDEVLOPMENT OF PANVELKAR EMPIRE WING A WING A-1 WING B is a Residential / Group Housing project by Om Sai Shraddha Developers in Thane, Maharashtra, registered with MahaRERA as P51700026198 on 29 Aug 2020. Possession is promised by 31 Mar 2027. The completion date has moved by 36 months from the original filing. 101 of the 210 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.

At a glance

Project

  • NameREDEVLOPMENT OF PANVELKAR EMPIRE WING A WING A-1 WING B
  • TypeResidential / Group Housing
  • Location
    • KOHOJ-KHUNTAVALI
    • AMBERNATH
    • Ambarnath (R)
    • Ambarnath
    • Thane
    • 421501
  • Pincode421501
  • RERA no.P51700026198
  • ReraGenie IDRG-MH-28478

Builder

  • NameOm Sai Shraddha Developers
  • Entity typePartnership
  • GSTIN27AAGFO3403M1Z6
  • PartnersDILIP MAHALE, MASHALLAH CHAUHAN, PRITAM PANVELKAR, VIJAY KAKADE, JAGDISH BANJAN, ULHAS PATIL, ZAHEER NOORI, RAHUL ANGRE, PARTH PASHTE, MUNESH CHAMBAWANE, ANMOL SONTAKKE, CHINMAYA CHOWDHARI and 2 more
  • Other registrations2 more →
  • No longer live2 lapsed, de-registered or revoked

Key dates

this monthRegisteredAug 2020First promiseMar 2024Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on29 Aug 2020
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 30 Mar 2024)
  • Buildings1 building record
  • Documents filed89 files

Current status

48%101 of 210 units booked
98.0%Work done, per cost certificate

Figures as on 11 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PANVELKAR EMPIRENA15152064210

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 11 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

PANVELKAR EMPIRE: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 11 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed18

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots18
Open Space18

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area5,370 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on11 Jun 2026

Approvals and building plan

Sanctioning authorityAmbernath Nagaparishad
Permissible FSI9509.09
Proposed, not sanctioned9,509 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 4 AND 5, PANVELKAR PRIDE, OPP SITAI SADAN, AMBERNATH-421501
Estimated costRs 42.16 cr
Cost incurredRs 41.32 cr
Work done98.0%
BuildingWingEstimatedIncurred
PANVELKAR EMPIRENARs 40.15 crRs 39.35 cr
-NARs 2.01 crRs 1.97 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVINOD S NAVARE
ArchitectVinod Navare
EngineerATUL KUDTARKAR RCC CONSULTANT
EngineerAtul Kudtarkar
Chartered AccountantS U RADHAKRISHNANI AND CO
Chartered AccountantSuresh Radhakrishnani
PartnerRole in project
Om Sai Shraddha Developers-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700019217Mar 2024 → Mar 2025

Reason as filed by the promoterInsufficient funds

EXT51700028274Mar 2024 → Mar 2026

Reason as filed by the promoterInsufficient funds

EA16062621378Mar 2024 → Mar 2027

Reason as filed by the promoterOur Proposed date of Completion was 31st March, 2026. Project is completed Upto 100% Construction wise and we have applied for building completion certificate to the concern Municipal Authority File No. ANP/NRV/BP/22-23/1228/9384/76/OCC (New) & Date. 28 April, 2026 ANP/NRV/BP/22-23/1228/9384/76. Therefore, the Registrar is not registering for the flat. So unfortunately we have to apply for Extension of Project. As we have to register the flat to the owner. It will take some time to receive it. We hereby request you please extend our completion date by 12 months so that we will get building com

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 15 Aug 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Aug 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Aug 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Aug 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed89

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 89 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: form 1 arc.pdf11 Aug 2026
Withdrawal Update Form 2File: engineer letter A.pdf11 Aug 2026
Withdrawal Update Form 3File: FORM 3 A.pdf11 Aug 2026
Form 2A (FY 2024-2025)File: form 2A 24-25.pdf16 Jun 2026
Withdrawal Update Form 1File: Architect Certificate A.pdf12 Jun 2026
Withdrawal Update Form 1File: Architect Certificate A.pdf12 Jun 2026
Withdrawal Update Form 2File: engineer letter A.pdf12 Jun 2026
Withdrawal Update Form 2File: engineer letter A.pdf12 Jun 2026
Withdrawal Update Form 3File: Form 3_11zon.pdf12 Jun 2026
Withdrawal Update Form 3File: Form 3_11zon.pdf12 Jun 2026
Form 1File: architect.pdf11 Jun 2026
Form 2File: eng.pdf11 Jun 2026
Form 3File: form 3 new_removed_merged_11zon.pdf11 Jun 2026
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD.pdf11 Jun 2026
Withdrawal Update Form 1File: Architects certificate A,A1 & B wing 30-06-24.pdf11 Jun 2026
Withdrawal Update Form 1File: architect.pdf11 Jun 2026
Withdrawal Update Form 2File: Engineer Certificate A,A1,B wing 30-6-24.pdf11 Jun 2026
Withdrawal Update Form 2File: eng.pdf11 Jun 2026
Withdrawal Update Form 3File: form 3 new_removed_merged_11zon.pdf11 Jun 2026
Withdrawal Update Form 3File: form 3 new_removed_merged_11zon.pdf11 Jun 2026
Form 5 (FY 2023-2024)File: Form 5 OSSD 2023-24.pdf11 Jun 2026
Form 5 (FY 2021-2022)File: empire audit.pdf11 Jun 2026
Form 5 (FY 2022-2023)File: Form 5 22-23.pdf25 May 2026
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD.pdf7 May 2026
Form 3File: form 3.pdf7 May 2026
Form 1File: architect.pdf7 May 2026
Form 2File: eng.pdf7 May 2026
Form 5 (FY 2024-2025)File: a wing audit 2425.pdf12 Mar 2026
Form 3File: form 3 a1.pdf3 Mar 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD PANVELKLAR EMPIRE.pdf3 Mar 2026
Form 1File: Architect Certificate Empire A.pdf3 Mar 2026
Form 2File: Engineer Letter A.pdf3 Mar 2026
Form 1File: Architect Letter.pdf12 Nov 2025
Form 2File: Engineer Letter.pdf12 Nov 2025
Form 3File: form 3.pdf12 Nov 2025
Disclosure of Sold and Booked InventoryFile: a sold unsold.pdf12 Nov 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 190625 om sai.pdf19 Jun 2025
Declaration in FORM BFile: FORM B declaration OSSD.pdf21 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 (3).pdf21 May 2025
Other - TechnicalFile: PERT certificate (1).pdf21 May 2025
Architect Certificate A A1 B29 Apr 2025
Engineers Certificate A A1 B29 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: OSSD 2A.pdf25 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf21 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate.pdf21 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 OSSD 2023-24.pdf15 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects certificate A A1 B Wing 30 9 24.pdf4 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate A A1 B Wing 30 9 24.pdf4 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects certificate A A1 B Wing.pdf24 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate A A1 B Wing.pdf24 Oct 2024
Declaration about Commencement CertificateFile: declaration abt commencement certificate A, A1 b.pdf22 Mar 2024
Declaration in FORM BFile: Form B_Notary Before ME.pdf22 Mar 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold list OSSD_22-3-2024_compressed (1).pdf22 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form-2A OSSD 22-23.pdf20 Mar 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold list OSSD_17-2-2024_11zon.pdf24 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: DIN 2024 ALL_11zon.pdf24 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects certificate 31-12-23 wing A A1 B.pdf14 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate 31-12-23.pdf14 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 A,A1,B wing 31 Dec 23.pdf14 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 22-23.pdf14 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects certificate 31-12-23 wing A A1 B.pdf12 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate 31-12-23.pdf12 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT LETTER.pdf3 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate OSSD - Form 2.pdf3 Oct 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank account details.pdf24 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate.pdf6 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer.pdf6 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: empire audit_compressed.pdf18 Nov 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: om sai shraddha.pdf20 Oct 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate 13-10-22.pdf20 Oct 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate dtd 31-7-2022.pdf27 Aug 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering Certificate 13-8-2022_compressed.pdf27 Aug 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 31-Mar-2022.pdf4 May 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's certificate 29-4-2022_compressed.pdf4 May 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS CERTIFICATE.pdf27 Oct 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Om Sai Shraddha Developers eng certificate_compressed.pdf27 Oct 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate new_compressed.pdf24 Aug 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_removed.pdf24 Aug 2020
Layout approvalFile: LAYOUT SCAN.pdf20 Aug 2020
Building plan approvalFile: LAYOUT SCAN.pdf20 Aug 2020

How this compares with Thane

48%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 36 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep REDEVLOPMENT OF PANVELKAR EMPIRE WING A WING on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near AMBERNATH7,600+ in Thane

Builder: Om Sai Shraddha Developers

OM SAI SHRADDHA DEVELOPERS has 3 registrations on MahaRERA, including SHANTI SADAN CHSL and REDEVLOPMENT OF PANVELKAR EMPIRE WING A WING A-1 WING B. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if REDEVLOPMENT OF PANVELKAR EMPIRE WING A WING A-1 WING B is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of REDEVLOPMENT OF PANVELKAR EMPIRE WING A WING A-1 WING B?

The registered promoter entity is Om Sai Shraddha Developers, a partnership as per the filing. Its GSTIN 27AAGFO3403M1Z6 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in REDEVLOPMENT OF PANVELKAR EMPIRE WING A WING A-1 WING B?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for REDEVLOPMENT OF PANVELKAR EMPIRE WING A WING A-1 WING B?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at REDEVLOPMENT OF PANVELKAR EMPIRE WING A WING A-1 WING B?

The professionals named in the filing: Architect: VINOD S NAVARE; Architect: Vinod Navare; Engineer: ATUL KUDTARKAR RCC CONSULTANT; Engineer: Atul Kudtarkar; Chartered Accountant: S U RADHAKRISHNANI AND CO; Chartered Accountant: Suresh Radhakrishnani. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in REDEVLOPMENT OF PANVELKAR EMPIRE WING A WING A-1 WING B?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About REDEVLOPMENT OF PANVELKAR EMPIRE WING A WING A-1 WING B. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save REDEVLOPMENT OF PANVELKAR EMPIRE WING A WING to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.