ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / REDEVELOPMENT OF TRIMURTI CO OPERATIVE HOUSING LTD WING A WING B WING C PHASE 1

Completed No litigation declared Others project

REDEVELOPMENT OF TRIMURTI CO OPERATIVE HOUSING LTD WING A WING B WING C PHASE 1

By GEETAI INVESTMENT

RG-MH-71520 · RERA P51700018300 · Last updated on MahaRERA portal: 28 Jan 2023

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Mar 2022Possession promisedregistration recorded completed
3 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 29 documents Report an error

REDEVELOPMENT OF TRIMURTI CO OPERATIVE HOUSING LTD WING A WING B WING C PHASE 1 is a Others project by GEETAI INVESTMENT in Thane, Maharashtra, registered with MahaRERA as P51700018300 on 22 Oct 2018. The registration is recorded completed; possession was promised by 30 Mar 2022.

At a glance

Project

  • NameREDEVELOPMENT OF TRIMURTI CO OPERATIVE HOUSING LTD WING A WING B WING C PHASE 1
  • TypeOthers
  • Location
    • KULGAON
    • BADLAPUR WEST
    • Badlapur (M Cl)
    • Ambarnath
    • Thane
    • 421503
  • Pincode421503
  • RERA no.P51700018300
  • ReraGenie IDRG-MH-71520

Builder

  • NameGEETAI INVESTMENT
  • Entity typePartnership
  • PartnersPRITAM NARAYAN PANVELKAR, ULHAS BHAVSING PATIL, MASHALLAH AZAZUDDIN CHAUHAN, MUNESH NANDKUMAR CHAMBAWANE, HARESH GORDHAN TANK, SURDAS DHARMA PATIL, PRASAD DATTARAY PATIL
  • Other registrations1 more →
  • Completed2 of 2

Key dates

this monthRegisteredOct 2018PromisedMar 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on22 Oct 2018
  • Promised completion30 Mar 2022
  • Revised completionNone
  • Buildings1 building record
  • Documents filed29 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TRIMURTI CO OPERATIVE HOUSING SOCIETY LTD WING A WING B WING C PHASE INA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 28 Jan 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

TRIMURTI CO OPERATIVE HOUSING SOCIETY LTD WING A WING B WING C PHASE I: 27% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 28 Jan 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed3

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots3
Closed/Covered3

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,847 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI3229.0
Proposed, not sanctioned2,491 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPANVELKAR PLAZA SHOP NO 16 TO 20 SAI SECTION STATION ROAD DIST THANE AMBERNATH

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectUR AND ASSOCIATES
EngineerATUL KUDTARKAR RCC CONSULTANT
PartnerRole in project
GEETAI INVESTMENT-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 13 Oct 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Oct 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Oct 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Oct 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 3 Mar 2022

Documents filed29

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Trimurti 21-22.pdf28 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: form 5 2020-21.pdf4 May 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Archi and eng.pdf3 Mar 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Archi and eng.pdf3 Mar 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: CC.pdf3 Mar 2022
Architect’s Certificate on Completion of Project (Form 4)File: form 4.pdf3 Mar 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate 31 march 2021-compressed.pdf25 Jun 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer certificate 31 march 2021.pdf25 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: trimurti audit048.pdf15 Jun 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect_compressed.pdf21 Nov 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer certificate-min.pdf21 Nov 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5.pdf14 Jan 2020
Certificates of CA (Form 3)File: FORM 3 MAIRA_compressed.pdf12 Nov 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf13 May 2019
Building plan approvalFile: copy of layout plan file.pdf13 Oct 2018
Layout approvalFile: copy of layout plan file.pdf13 Oct 2018
Copy of the legal title reportFile: title report.pdf13 Oct 2018
Details of encumbrancesFile: Encumbrances letter.pdf13 Oct 2018
Copy of Layout Approval (in case of layout)File: copy of layout plan file.pdf13 Oct 2018
Building Plan Approval (IOD)File: copy of layout plan file.pdf13 Oct 2018
Commencement Certificates / NA Order for plotted developmentFile: Commencemence_certificate file.pdf13 Oct 2018
Declaration in FORM BFile: FORM B DECLARATION-UPLOAD FILE.pdf13 Oct 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate (1).pdf13 Oct 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE- file.pdf13 Oct 2018
Certificates of CA (Form 3)File: FORM 3 CA CERTIFICATE.pdf13 Oct 2018
Certificates of CA (Form 3)File: annexure to form-3.pdf13 Oct 2018
Proforma of Allotment letterFile: allotement letter.pdf13 Oct 2018
Proforma of Allotment letterFile: letter of allotment.pdf13 Oct 2018
Proforma of Allotment letterFile: agreement for sale draft.pdf13 Oct 2018

How this compares with Thane

24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep REDEVELOPMENT OF TRIMURTI CO OPERATIVE HOUSI on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BADLAPUR WEST7,600+ in Thane

Builder: GEETAI INVESTMENT

GEETAI INVESTMENT has 2 registrations on MahaRERA, including REDEVELOPMENT OF TRIMURTI CO OPERATIVE HOUSING LTD WING A WING B WING C PHASE 1 and Redevelopment of Suyog Sahajeevan C.H.S. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if REDEVELOPMENT OF TRIMURTI CO OPERATIVE HOUSING LTD WING A WING B WING C PHASE 1 is delayed beyond 30 Mar 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of REDEVELOPMENT OF TRIMURTI CO OPERATIVE HOUSING LTD WING A WING B WING C PHASE 1?

The registered promoter entity is GEETAI INVESTMENT, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in REDEVELOPMENT OF TRIMURTI CO OPERATIVE HOUSING LTD WING A WING B WING C PHASE 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for REDEVELOPMENT OF TRIMURTI CO OPERATIVE HOUSING LTD WING A WING B WING C PHASE 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at REDEVELOPMENT OF TRIMURTI CO OPERATIVE HOUSING LTD WING A WING B WING C PHASE 1?

The professionals named in the filing: Architect: UR AND ASSOCIATES; Engineer: ATUL KUDTARKAR RCC CONSULTANT. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in REDEVELOPMENT OF TRIMURTI CO OPERATIVE HOUSING LTD WING A WING B WING C PHASE 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About REDEVELOPMENT OF TRIMURTI CO OPERATIVE HOUSING LTD WING A WING B WING C PHASE 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save REDEVELOPMENT OF TRIMURTI CO OPERATIVE HOUSI to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.