ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / REDEVELOPMENT OF PARIJAT BUILDING OF SANKSRITI NAGAR COOP HSG SOC LTD

Completed No litigation declared Residential / Group Housing project

REDEVELOPMENT OF PARIJAT BUILDING OF SANKSRITI NAGAR COOP HSG SOC LTD

By OJASS CONSTRUCTIONS

RG-MH-08090 · RERA P51700001851 · Last updated on MahaRERA portal: 24 Jan 2020

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 3 earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 4 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2021Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 22 documents Report an error

REDEVELOPMENT OF PARIJAT BUILDING OF SANKSRITI NAGAR COOP HSG SOC LTD is a Residential / Group Housing project by OJASS CONSTRUCTIONS in Thane, Maharashtra, registered with MahaRERA as P51700001851 on 29 Jul 2017. The registration is recorded completed; possession was promised by 19 Dec 2021.

At a glance

Project

  • NameREDEVELOPMENT OF PARIJAT BUILDING OF SANKSRITI NAGAR COOP HSG SOC LTD
  • TypeResidential / Group Housing
  • Location
    • PANCHPAKHADI
    • Thane (M Corp.)
    • Thane
    • 400602
  • Pincode400602
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700001851
  • ReraGenie IDRG-MH-08090

Builder

  • NameOJASS CONSTRUCTIONS
  • Entity typePartnership
  • GSTIN27AAEFO8137G1Z4
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersSAMEER AJIT GANU, SUMEDH M PATANKAR, SHUCHITA M PATANKAR
  • Other registrations4 more →
  • Completed4 of 5
  • Declared earlier projects4 →

Key dates

this monthRegisteredJul 2017PromisedDec 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on29 Jul 2017
  • Promised completion19 Dec 2021
  • Revised completionNone
  • Buildings1 building record
  • Documents filed22 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PARIJATNA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Jan 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

PARIJAT: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 24 Jan 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed62

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots62
Closed/Covered62

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,572 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI4283.52
Proposed, not sanctioned2,893 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch KUSUMANJALI, OPPOSITE DEODHAR HOSPITAL, NAUPADA, THANE, 400602

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMAKARAND PARANGE
PartnerRole in project
OJASS CONSTRUCTIONS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 3 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 24 Jan 2020

Documents filed22

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC- Parijat.pdf24 Jan 2020
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 -Parijat.pdf14 Jan 2020
Status of Formation of Legal Entity (Society/Co Op etc.)File: Parijat.pdf25 Sep 2019
Status of ConveyanceFile: Parijat.pdf25 Sep 2019
Certificates of CA (Form 5)File: FY 2017-18 MahaRERA Audit.pdf29 Sep 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate.pdf7 Jun 2018
Certificates of CA (Form 3)File: FORM 3 _ CA CERTIFICATE OJASS _ SIGNED.pdf7 Jun 2018
Certificates of CA (Form 3)File: Ojass Construction CA Certificate.pdf26 Jul 2017
Details of encumbrancesFile: Title Search Report.pdf25 Jul 2017
Details of encumbrancesFile: Declaration on encumbrances.pdf25 Jul 2017
Declaration in FORM BFile: Form B Decleration compressed.pdf25 Jul 2017
Proforma of Allotment letterFile: LETTER OF ALLOTMENT FORMAT.pdf20 Jul 2017
Proforma of Allotment letterFile: AGREEMENT FOR SALE Format.pdf20 Jul 2017
Building plan approvalFile: Parijat IOD.pdf3 Jul 2017
Layout approvalFile: LayoutPlan.pdf3 Jul 2017
PAN CardFile: Ojass Constructions PAN Card.pdf3 Jul 2017
Copy of the legal title reportFile: Title Search Report.pdf3 Jul 2017
Copy of Layout Approval (in case of layout)File: LayoutPlan.pdf3 Jul 2017
Building Plan Approval (IOD)File: Parijat IOD.pdf3 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf3 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1.pdf3 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2.pdf3 Jul 2017

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise
ProjectLocationRegisteredStatusPromisedDelivered
Mai Kripa Co. Op. Hsg. Soc.P51700033561RAGHUNATH NAGAR, ThaneFeb 2022CompletedMar 2024Aug 2023
YASHANAND CHSL OJASS CONSTRUCTIONSP51700019814CHARAI THANE WEST, ThaneMar 2019CompletedMar 2022Mar 2022
MAHASHWETA - OJASS CONSTRUCTIONSP51700016301CHARAI, ThaneMay 2018CompletedOct 2019Oct 2019

How this compares with Thane

24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep REDEVELOPMENT OF PARIJAT BUILDING OF SANKSRI on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PANCHPAKHADI7,600+ in Thane

2 kmREDEVELOPMENT OF PARIJATCompleted 103Lapsed / revoked 75Other 145Dot size: filed unitsN

Filed coordinates, straight-line distance. 323 registered projects within 2 km.

Builder: OJASS CONSTRUCTIONS

OJASS CONSTRUCTIONS has 5 registrations on MahaRERA, including REDEVELOPMENT OF PARIJAT BUILDING OF SANKSRITI NAGAR COOP HSG SOC LTD and MAHASHWETA - OJASS CONSTRUCTIONS. Its filings disclose 4 earlier MahaRERA projects: declares 4 of 4 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if REDEVELOPMENT OF PARIJAT BUILDING OF SANKSRITI NAGAR COOP HSG SOC LTD is delayed beyond 19 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of REDEVELOPMENT OF PARIJAT BUILDING OF SANKSRITI NAGAR COOP HSG SOC LTD?

The registered promoter entity is OJASS CONSTRUCTIONS, a partnership as per the filing. Its GSTIN 27AAEFO8137G1Z4 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in REDEVELOPMENT OF PARIJAT BUILDING OF SANKSRITI NAGAR COOP HSG SOC LTD?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for REDEVELOPMENT OF PARIJAT BUILDING OF SANKSRITI NAGAR COOP HSG SOC LTD?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at REDEVELOPMENT OF PARIJAT BUILDING OF SANKSRITI NAGAR COOP HSG SOC LTD?

The professionals named in the filing: Architect: MAKARAND PARANGE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in REDEVELOPMENT OF PARIJAT BUILDING OF SANKSRITI NAGAR COOP HSG SOC LTD?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About REDEVELOPMENT OF PARIJAT BUILDING OF SANKSRITI NAGAR COOP HSG SOC LTD. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save REDEVELOPMENT OF PARIJAT BUILDING OF SANKSRI to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.