Home / Browse projects / Mumbai Suburban, Maharashtra / Redevelopment of Dadarkar Apartment CHSL

Registered No litigation declared Residential / Group Housing project

Redevelopment of Dadarkar Apartment CHSL

By Sankalp Structures Private Limited

RG-MH-30246 · RERA P51800030506 · Last updated on MahaRERA portal: 24 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 42 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedmoved 42 months from the original
3 of 11Construction stages donefurthest along: Stilt Floor, 90%
14 of 18Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 54 documents Report an error

Redevelopment of Dadarkar Apartment CHSL is a Residential / Group Housing project by Sankalp Structures Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800030506 on 30 Aug 2021. Possession is promised by 31 Mar 2027. The completion date has moved by 42 months from the original filing. 4 of the 18 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.

At a glance

Project

  • NameRedevelopment of Dadarkar Apartment CHSL
  • TypeResidential / Group Housing
  • Location
    • Liberty Garden Road
    • Malad West
    • Borivali
    • Mumbai Suburban
    • 400064
  • Pincode400064
  • RERA no.P51800030506
  • ReraGenie IDRG-MH-30246

Builder

  • NameSankalp Structures Private Limited
  • Entity typeCompany
  • DirectorsSANDESH KADAM, SAKHI KADAM

Key dates

this monthRegisteredAug 2021First promiseSep 2023Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on30 Aug 2021
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 30 Sep 2023)
  • Buildings1 building record
  • Documents filed54 files

Current status

22%4 of 18 units booked
72.1%Work done, per cost certificate

Figures as on 24 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Redevelopment of Dadarkar Apartment CHSLNA10918018

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 90%.

Redevelopment of Dadarkar Apartment CHSL: 37% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor90%
Slabs of Super Structure10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 24 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes20%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed14

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots14
Closed/Covered14

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area361 sq m
Land owned byNot the promoter
Named landowners1
LandownerVillageDistrict
Dadarkar Apartment Co. Op. Hsg. Soc. LtdBorivaliMumbai Suburban

Approvals and building plan

Sanctioning authorityMUNICIPAL CORPORATION OF GREATER MUMBAI
Permissible FSI1066.26
Proposed, not sanctioned1,066 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchFirst Floor, Manish Nagar Shopping Centre, Azad Nagar Po, Andheri-w, Mumbai, Pin- 400053
Estimated costRs 3.25 cr
Cost incurredRs 2.34 cr
Work done72.1%
BuildingWingEstimatedIncurred
Redevelopment of Dadarkar Apartment CHSLNARs 3.09 crRs 2.29 cr
-NARs 16.25 lakhRs 5.69 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKetan Vaidya Associates Vaidya
EngineerGirish Wadhwa
EngineerSK Consultant & Engineer
Chartered AccountantRUTUJA NARSINGH & ASSOCIATES
PartnerRole in project
Sankalp Structures Private Limited-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA16062501606Sep 2023 → May 2026

Reason as filed by the promoterWe apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work

EA14052620961Sep 2023 → Mar 2027

Reason as filed by the promoterWe, Sankalp Structures Private Limited, the promoter of the project Redevelopment of Dadarkar Apartment CHSL (Registration No. P51800030506) under MahaRERA, hereby submit our request for an extension of time for the completion of the project. We regret the delay in completion of the project. The primary reason for the delay was the requirement of road line demarcation and related variations, which resulted in a delay in obtaining the Commencement Certificate. These procedural and approval-related aspects required additional time to resolve. We would like to inform that all necessary approvals

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 Aug 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 May 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 May 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Jul 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed54

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: 260702- Rera Form 1- KVA-RD of Dadarkar Apartment CHSL.pdf24 Jul 2026
Withdrawal Update Form 2File: Form 2.pdf24 Jul 2026
Withdrawal Update Form 3File: Form 3.pdf24 Jul 2026
Layout approvalFile: Plan dated 18-06-2025-pages-1.pdf19 May 2026
Building plan approvalFile: Plan dated 18-06-2025-pages-2.pdf19 May 2026
Withdrawal Update Form 1File: Form 1 (4).pdf14 May 2026
Withdrawal Update Form 1File: Form 1 as on March 2026.pdf14 May 2026
Withdrawal Update Form 2File: Form 2 - Redevelopment of Dadarkar Apartment CHSL Dec 2025 (1).pdf14 May 2026
Withdrawal Update Form 2File: Form 2 as on March 2026.pdf14 May 2026
Withdrawal Update Form 3File: F 3 of Redevelopment of Dadarkar Dec-25 (1).pdf14 May 2026
Withdrawal Update Form 3File: Form 3 as on March 2026.pdf14 May 2026
Withdrawal Update Form 1File: Form 1 (4).pdf26 Mar 2026
Withdrawal Update Form 1File: Form 1 (4).pdf26 Mar 2026
Withdrawal Update Form 1File: Form 1 (4).pdf26 Mar 2026
Withdrawal Update Form 2File: Form 2 - Redevelopment of Dadarkar Apartment CHSL Dec 2025 (1).pdf26 Mar 2026
Withdrawal Update Form 2File: Form 2 - Redevelopment of Dadarkar Apartment CHSL Dec 2025 (1).pdf26 Mar 2026
Withdrawal Update Form 2File: Form 2 - Redevelopment of Dadarkar Apartment CHSL Dec 2025 (1).pdf26 Mar 2026
Withdrawal Update Form 3File: F 3 of Redevelopment of Dadarkar Dec-25 (1).pdf26 Mar 2026
Withdrawal Update Form 3File: F 3 of Redevelopment of Dadarkar Dec-25 (1).pdf26 Mar 2026
Withdrawal Update Form 3File: F 3 of Redevelopment of Dadarkar Dec-25 (1).pdf26 Mar 2026
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf16 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 March'25.pdf16 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 March'25.pdf16 Jun 2025
Disclosure of sold/ booked inventoryFile: Circular 29.pdf16 Jun 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A FY 23-24.pdf16 Jun 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)File: Form 5 FY 24-25.pdf16 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Dadarkar RERA Certificate.pdf19 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Ashish Ambekar Assurance Certificate.pdf19 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: from 3_compressed.pdf19 Jun 2023
CERSAI detailsFile: Redevelopment of Dadarkar Apartment CHSL.pdf24 Dec 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 as on March 2022.pdf5 Nov 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Redevelopment of Dadarkar Apartment CHSL as on March 2022.pdf5 Nov 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Site Supervisor 2A.pdf28 Feb 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Redevelopment of Dadarkar Apartment CHSL (1)_compressed.pdf25 Feb 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dadarkar sept 2021_compressed.pdf19 Feb 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dadarkar Dec 2021_compressed.pdf19 Feb 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Redevelopment of Dadarkar Apartment CHSL as on 30th September 2021.pdf19 Feb 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Redevelopment of Dadarkar Apartment CHSL as on 31st December 2021 (2)_compressed.pd19 Feb 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Redevelopment of Dadarkar Apartment CHSL_compressed (1).pdf21 Jan 2022
Declaration about Commencement CertificateFile: SANKALP 32.pdf17 Jan 2022
Disclosure of sold/ booked inventoryFile: SANKALP 29.pdf17 Jan 2022
Layout approvalFile: 00000000 (3).pdf25 Aug 2021
Building plan approvalFile: 00000000 (3).pdf25 Aug 2021
Copy of Layout Approval (in case of layout)File: 00000000 (3).pdf25 Aug 2021
Building Plan Approval / NA Order for plotted developmentFile: 00000000 (3).pdf25 Aug 2021
Declaration about Commencement CertificateFile: Declaration sankalp.pdf19 Aug 2021
Declaration in FORM BFile: Affidavit cum declaration.pdf19 Aug 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Redevelopment of Dadarkar Apartment CHSL.pdf18 Aug 2021
Proforma of Allotment letterFile: AFS-Dadarkar-Sankalp Structures_17082021.pdf18 Aug 2021
Proforma of Allotment letterFile: Allotment Letter_Dadarkar.pdf18 Aug 2021
Copy of the legal title reportFile: Title Sankalp Structures.pdf17 Aug 2021
PAN CardFile: PAN SSPL.pdf7 Jul 2021
Details of encumbrancesFile: Encumbrance.pdf7 Jul 2021
Commencement Certificates / NA Order for plotted developmentFile: 210602-_FirstCC_signed.pdf7 Jul 2021

How this compares with Mumbai Suburban

22%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 42 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Redevelopment of Dadarkar Apartment CHSL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Malad West6,700+ in Mumbai Suburban

Builder: Sankalp Structures Private Limited

Sankalp Structures Private Limited has 1 registration on MahaRERA, including Redevelopment of Dadarkar Apartment CHSL. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Redevelopment of Dadarkar Apartment CHSL is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Redevelopment of Dadarkar Apartment CHSL?

The registered promoter entity is Sankalp Structures Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Redevelopment of Dadarkar Apartment CHSL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Redevelopment of Dadarkar Apartment CHSL?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Redevelopment of Dadarkar Apartment CHSL?

The professionals named in the filing: Architect: Ketan Vaidya Associates Vaidya; Engineer: Girish Wadhwa; Engineer: SK Consultant & Engineer; Chartered Accountant: RUTUJA NARSINGH & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Redevelopment of Dadarkar Apartment CHSL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Redevelopment of Dadarkar Apartment CHSL. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Redevelopment of Dadarkar Apartment CHSL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.