ReraGenieLog inGet a buyer report

Home / Browse projects / Nagpur, Maharashtra / Ratneshwar Enclave

Registration lapsed No litigation declared Residential / Group Housing project

Ratneshwar Enclave

By M/s Vanshika Developers & Promoters

RG-MH-00876 · RERA P50500024950 · Last updated on MahaRERA portal: 1 Sep 2022

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 52 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 12 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Jun 2022Possession promised52 months past this date
5 of 11Construction stages donefurthest along: Internal walls, 25%
1Complaints at MahaRERAon this registration
Jump to the 54 documents Report an error

Ratneshwar Enclave is a Residential / Group Housing project by M/s Vanshika Developers & Promoters in Nagpur, Maharashtra, registered with MahaRERA as P50500024950 on 12 Mar 2020. Possession was promised by 30 Jun 2022 and is now 52 months past that date. The completion date has moved by 12 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameRatneshwar Enclave
  • TypeResidential / Group Housing
  • Location
    • Bhende Layout
    • Nagpur (M Corp.)
    • Nagpur (Urban)
    • Nagpur
    • 440025
  • Pincode440025
  • RERA no.P50500024950
  • ReraGenie IDRG-MH-00876

Builder

  • NameM/s Vanshika Developers & Promoters
  • Entity typeOthers
  • Named personSonal Kalambe
  • Other registrations1 more →
  • No longer live2 lapsed, de-registered or revoked

Key dates

52 months past promisethis monthRegisteredMar 2020First promiseJun 2021Revised toJun 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on12 Mar 2020
  • Promised completion30 Jun 2022
  • Revised completionRevised to 30 Jun 2022 (originally 30 Jun 2021)
  • Buildings1 building record
  • Documents filed54 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing-ANA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 1 Sep 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 25%.

Wing-A: 48% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises25%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 1 Sep 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed5

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots5
Closed/Covered1
Open Space4

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area474 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI614.96
Proposed, not sanctioned615 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDhawale Plaza Ground Floor Sonaji Wadi Mahal Nagpur

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPravin S Godhe
EngineerP S Patankar & Associates
Chartered AccountantSuresh Vallabhneni & Co
PartnerRole in project
M/s Vanshika Developers & Promoters-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT50500010807Jun 2021 → Jun 2022

Reason as filed by the promoterLabour problem due to Covid-19

EXT50500010684Jun 2021 → Aug 2021

Reason as filed by the promoterlabour problem due to COVID 19

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC004000000030506Ratneshhwar EnclaveSonal Kalambe w/o Shahikant kalambe05/06/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Feb 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 11 Mar 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed54

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Ratneshwar 12062022.pdf1 Sep 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Ratneshwar 12062022.pdf1 Sep 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Ratneshwar 12062022.pdf1 Sep 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Ratneshwar 12062022.pdf1 Sep 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch-1.pdf26 Apr 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng-3.pdf26 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Eng-1.pdf26 Apr 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA-1.pdf26 Apr 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate Ratneshwar.pdf18 Jan 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2nd Engineer Certificate Ratneshwar Enclave (12-06-2020).pdf18 Jan 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3rd Engineer Certificate Ratneshwar Enclave (12-09-2020).pdf18 Jan 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4th Engineer Certificate Ratneshwar Enclave (12-12-2020).pdf18 Jan 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5th Engineer Certificate Ratneshwar Enclave (12-03-2021).pdf18 Jan 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 6th Engineer Certificate Ratneshwar Enclave (12-06-2021).pdf18 Jan 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 7th Engineer Certificate Ratneshwar Enclave (12-09-2021).pdf18 Jan 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 8th Engineer Certificate Ratneshwar Enclave (12-12-2021).pdf18 Jan 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Maha_Rera_CA_certificate 121221.pdf18 Jan 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 8th Engineer Certificate Ratneshwar Enclave (12-12-2021).pdf18 Jan 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ratneshwar 1.pdf20 Dec 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ratneshwar 2.pdf20 Dec 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ratneshwar 3.pdf20 Dec 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ratneshwar 4.pdf20 Dec 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ratneshwar 5.pdf20 Dec 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ratneshwar 6.pdf20 Dec 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ratneshwar 12-06-20_compressed.pdf20 Dec 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ratneshwar 12-09-20_compressed.pdf20 Dec 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ratneshwar 12-12-20_compressed.pdf20 Dec 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ratneshwar 12-03-21_compressed.pdf20 Dec 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ratneshwar 12-06-21_compressed.pdf20 Dec 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ratneshwar 12-09-21_compressed.pdf20 Dec 2021
Declaration about Commencement CertificateFile: Format D Circular 32.pdf16 Aug 2021
Disclosure of sold/ booked inventoryFile: Form under Circular 29.pdf16 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A FY20-21.pdf11 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5.pdf11 Aug 2021
Commencement Certificates / NA Order for plotted developmentFile: commencement certificate ratneshwar_0001_compressed.pdf11 Mar 2020
Declaration in FORM BFile: Form B ratneshwar_0001_compressed.pdf20 Feb 2020
Proforma of Allotment letterFile: ATS RATNESHWAR ENCLAVE.pdf20 Feb 2020
Copy of the legal title reportFile: serch report ratneshvar enclave (1) after compress.pdf4 Feb 2020
Details of encumbrancesFile: encumbrances letter ratneshwar enclave.pdf4 Feb 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects certificate ratneshwar.pdf4 Feb 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1st Engineer Certificate of Ratneshwar Enclave (30-08-2017).pdf4 Feb 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate_compressed (4).pdf4 Feb 2020
Proforma of Allotment letterFile: Allotment letter ratneshwar enclave.pdf28 Jan 2020
Layout approvalFile: RL vanshika pn 9.pdf22 Jul 2017
Layout approvalFile: RL vanshika pn 10.pdf22 Jul 2017
Building plan approvalFile: Vanshika Plan.pdf22 Jul 2017
Building plan approvalFile: Vanshika Plan 2.pdf22 Jul 2017
PAN CardFile: Pan Card Vanshika Developers.pdf22 Jul 2017
Copy of Layout Approval (in case of layout)File: RL vanshika pn 9.pdf22 Jul 2017
Copy of Layout Approval (in case of layout)File: RL vanshika pn 10.pdf22 Jul 2017
Building Plan Approval (IOD)File: Vanshika Plan.pdf22 Jul 2017
Building Plan Approval (IOD)File: Vanshika Plan 2.pdf22 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Building)permit.pdf22 Jul 2017
Declaration in FORM BFile: Form B Vanshika.pdf22 Jul 2017

How this compares with Nagpur

13%of Nagpur projects moved their completion datethis one moved by 12 months
22%of Nagpur registrations have lapsed or been cancelledthis one is among them

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Ratneshwar Enclave on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Bhende Layout2,800+ in Nagpur

Builder: M/s Vanshika Developers & Promoters

M/s Vanshika Developers & Promoters has 2 registrations on MahaRERA, including Ratneshwar Enclave and SONAL ENCLAVE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What does it mean that Ratneshwar Enclave shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Ratneshwar Enclave is delayed beyond 30 Jun 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Ratneshwar Enclave?

The registered promoter entity is M/s Vanshika Developers & Promoters, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Ratneshwar Enclave?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Ratneshwar Enclave?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Ratneshwar Enclave?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Ratneshwar Enclave?

The professionals named in the filing: Architect: Pravin S Godhe; Engineer: P S Patankar & Associates; Chartered Accountant: Suresh Vallabhneni & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Ratneshwar Enclave?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Ratneshwar Enclave. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Ratneshwar Enclave to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.