ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / Rassaz Greens

Completed No litigation declared Others project

Rassaz Greens

By Rais Ahmad

RG-MH-20494 · RERA P51700008730 · Last updated on MahaRERA portal: 20 Jan 2023

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 1 earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2019Possession promisedregistration recorded completed
11 of 22Construction stages doneacross 2 buildings; furthest along: Excavation, 0%
0Complaints at MahaRERAon this registration
Jump to the 18 documents Report an error

Rassaz Greens is a Others project by Rais Ahmad in Thane, Maharashtra, registered with MahaRERA as P51700008730 on 19 Aug 2017. The registration is recorded completed; possession was promised by 31 Dec 2019.

At a glance

Project

  • NameRassaz Greens
  • TypeOthers
  • Location
    • Mira-Bhayandar (M Corp.)
    • Thane
    • 401107
  • Pincode401107
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700008730
  • ReraGenie IDRG-MH-20494

Builder

  • NameRais Ahmad
  • Entity typeIndividual
  • Managing DirectorRais Ahmad
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2017PromisedDec 2019Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on19 Aug 2017
  • Promised completion31 Dec 2019
  • Revised completionNone
  • Buildings2 building records
  • Documents filed18 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building ANA130000
BUILDING BNA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 20 Jan 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Excavation, at 0%.

Building A100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 Jan 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes80%
Open ParkingYes80%

Parking filed24

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots24
Closed/Covered3
Open Space21

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,371 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI10937.21
Proposed, not sanctioned3,162 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchJammu and Kashmir Bank, Jangid House, MTNL Road, Mira Road East, Thane 401107

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAvinash Mhatre & Associates
PartnerRole in project
Rais Ahmad-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 11 Apr 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 3 Jan 2023

Documents filed18

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Status of Formation of Legal Entity (Society/Co Op etc.)File: RASSAZ GREENS A CO OP HCL.pdf20 Jan 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupation Certificate RG A.pdf3 Jan 2023
Architect’s Certificate on Completion of Project (Form 4)File: IMG_0001.pdf25 Jun 2021
Declaration about Commencement CertificateFile: CC Type A.pdf23 Jun 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: CC Type A1.pdf23 Jun 2021
Commencement Certificates / NA Order for plotted developmentFile: comencement certificate .pdf11 Apr 2018
Copy of the legal title reportFile: title.pdf29 Jul 2017
Declaration in FORM BFile: Declaration Upload.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate.pdf29 Jul 2017
Certificates of CA (Form 3)File: CA Letter.pdf29 Jul 2017
Proforma of Allotment letterFile: A G R E E M E N T 1.pdf29 Jul 2017
Proforma of Allotment letterFile: Allotment Letter _draft_.pdf29 Jul 2017
Building plan approvalFile: iod.pdf25 Jul 2017
Layout approvalFile: LAYOUT AND BUILDING PLAN.pdf25 Jul 2017
Details of encumbrancesFile: details of encumbrance .pdf25 Jul 2017
Copy of Layout Approval (in case of layout)File: LAYOUT AND BUILDING PLAN.pdf25 Jul 2017
Building Plan Approval (IOD)File: iod.pdf25 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate.pdf25 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
RASSAZ CASTLEVillage Mogra. Taluka Andheri. Malpa Dongri 1. Andheri East. Mumbai 40006160CompletedJul 2011Jul 2011

How this compares with Thane

24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Rassaz Greens on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mira-Bhayandar (M Corp.)7,600+ in Thane

2 kmRassaz GreensCompleted 93Lapsed / revoked 72Other 110Dot size: filed unitsN

Filed coordinates, straight-line distance. 275 registered projects within 2 km.

Builder: Rais Ahmad

Rais Ahmad has 1 registration on MahaRERA, including Rassaz Greens. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Rassaz Greens is delayed beyond 31 Dec 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Rassaz Greens?

The registered promoter entity is Rais Ahmad, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Rassaz Greens?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Rassaz Greens?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Rassaz Greens?

The professionals named in the filing: Architect: Avinash Mhatre & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Rassaz Greens?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Rassaz Greens. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Rassaz Greens to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.