Rajyog Residency
RG-MH-24430 · RERA P52100012213 · Last updated on MahaRERA portal: 3 Jan 2023
Source: official MahaRERA filing
Red flags
- 1 complaint at MahaRERA
- Completion date moved by 54 months
- 5 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Rajyog Residency is a Others project by Rajyog Properties in Pune, Maharashtra, registered with MahaRERA as P52100012213 on 1 Sep 2017. The registration is recorded completed; possession was promised by 30 Mar 2023. The completion date has moved by 54 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameRajyog Residency
- TypeOthers
- Location
- Varulwadi
- Junnar
- Pune
- 410504
- Pincode410504
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100012213
- ReraGenie IDRG-MH-24430
Builder
- NameRajyog Properties
- Entity typePartnership
- PartnersKirti Aher, Hrishikesh Korde, Machindra Ghanghale
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on1 Sep 2017
- Promised completion30 Mar 2023
- Revised completionRevised to 30 Mar 2023 (originally 30 Sep 2018)
- Buildings2 building records
- Documents filed31 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A | NA | 9 | 0 | 0 | 0 | 0 |
| B | NA | 5 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 3 Jan 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 90%.
A58%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 85% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 60% |
| Sanitary Fittings within the flats / premises | 25% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 15% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 20% |
B81%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 60% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 75% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 70% |
Progress on shared amenities15
As on 3 Jan 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 10% |
| Water Supply | Yes | 70% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 10% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 20% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 10% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 25% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 10% |
Parking filed38
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| A | 1 | 30 | 31 |
| B | 1 | 6 | 7 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Rajyog Properties | Varulwadi | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Omkar Associates |
| Engineer | Kedar Associates |
| Partner | Role in project |
|---|---|
| Rajyog Properties | - |
Extensions applied for5
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterOn account of the Covid 19 impact, the construction process had slowed down. There was shortage of labour, material were delivered slowly and the entire financial situation was slowed down.
Reason as filed by the promoterCovid-19 impact had disturbed the supply chain and labour availability. and hence the project has been delayed. We are in the end stages of the project and aim to complete it within the specified completion date.
Reason as filed by the promoterApplication for Extension due to Covid-19 Pandemic lockdown and shortage of labour.
Reason as filed by the promoterThere were compelling circumstances because of which the completion formalities for the said project were not completed. The association of allottees have given their consent for the proposed completion date. We thus request you to kindly grant us the extension as proposed.
Reason as filed by the promoterSubject : Extension in the completion of the project : Rajyog Residency (MAHARERA No : P52100012213) We are into the process of completion of our project “Rajyog Residency” for which initially we had put in the completion date as 30th September, 2018. However due to certain conditions, enumerated below, the completion of the project was pushed further. We thus are applying for extension of the completion of the project for which we request you to take cognizance and grant the extension. 1. Quarries of neighboring areas from where we regularly and generally buy our supplies were sealed and no m
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12501948 | Sunita Ganesh maral | Rajyog Properties | 13/06/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 1 Aug 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 1 Aug 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 1 Aug 2017 - Commencement CertificateNot on the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
- Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed31
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A_2019-20.pdf | 3 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A_2020-21.pdf | 3 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A_2021-22.pdf | 3 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineer Quality.pdf | 3 Nov 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineer Quality.pdf | 3 Nov 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5_2017-18.pdf | 3 Nov 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5_2018-19.pdf | 3 Nov 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5_2019-20.pdf | 3 Nov 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5_2020-21.pdf | 3 Nov 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5_2021-22.pdf | 3 Nov 2022 |
| Declaration about Commencement CertificateFile: Commencement Declaration.pdf | 21 Jul 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer Quality.pdf | 21 Jul 2022 |
| Disclosure of sold/ booked inventoryFile: Sold_Unsold.pdf | 21 Jul 2022 |
| OtherFile: Consent letter of allottees.pdf | 21 Jul 2022 |
| Architect’s Certificate on Completion of Project (Form 4)File: Architect Certificate.pdf | 30 Sep 2019 |
| OtherFile: SITE ER LETTER.pdf | 30 Sep 2019 |
| OtherFile: Stability Certificate-1.pdf | 30 Sep 2019 |
| Layout approvalFile: RAJYOG PLAN.pdf | 1 Aug 2017 |
| Building plan approvalFile: Building Plan 1.pdf | 1 Aug 2017 |
| Building plan approvalFile: Building Plan 2.pdf | 1 Aug 2017 |
| Copy of the legal title reportFile: Legal title Report.pdf | 1 Aug 2017 |
| Details of encumbrancesFile: Encumbrance Letter.pdf | 1 Aug 2017 |
| Copy of Layout Approval (in case of layout)File: RAJYOG PLAN.pdf | 1 Aug 2017 |
| Building Plan Approval (IOD)File: Building Plan 1.pdf | 1 Aug 2017 |
| Building Plan Approval (IOD)File: Building Plan 2.pdf | 1 Aug 2017 |
| Declaration in FORM BFile: Declaration Form B.pdf | 1 Aug 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 1 Aug 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Rajyog_Engineer Certificate.pdf | 1 Aug 2017 |
| Certificates of CA (Form 3)File: CA Certificate_Rajyog.pdf | 1 Aug 2017 |
| Proforma of Allotment letterFile: Flat Agreement.pdf | 1 Aug 2017 |
| Proforma of Allotment letterFile: Allotment Letter.pdf | 1 Aug 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 31 filed documents as one ZIP, foldered, with a manifest
Keep Rajyog Residency on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Varulwadi13,700+ in Pune
Filed coordinates, straight-line distance. 20 registered projects within 2 km.
SUYOG SAMRAJYA
ASHIRWAD INFRASTRUCTURES
Vizion Bliss
VIZION CONSTRUCTION
Crystal Tower Phase 2
Jadhav Civil Project
Vaishnavi Vastu A and B
VAISHNAVI PROMOTERS AND DEVELOPERS
FLORINA RESIDENCY
DEEPALI BUILDCON
FLORINA PHASE II
DEEPALI BUILDCON
Builder: Rajyog Properties
Rajyog Properties has 1 registration on MahaRERA, including Rajyog Residency. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Rajyog Residency is delayed beyond 30 Mar 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Rajyog Residency?
The registered promoter entity is Rajyog Properties, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Rajyog Residency?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Rajyog Residency?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Rajyog Residency?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Rajyog Residency?
The professionals named in the filing: Architect: Omkar Associates; Engineer: Kedar Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Rajyog Residency?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback