RAJGAD RESIDENCY
RG-MH-98785 · RERA P52700016106 · Last updated on MahaRERA portal: 21 Oct 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 31 months past the filed date
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Satara registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
RAJGAD RESIDENCY is a Residential / Group Housing project by ADITI BUILDCON in Satara, Maharashtra, registered with MahaRERA as P52700016106 on 17 Apr 2018. Possession was promised by 29 Mar 2024 and is now 31 months past that date. The completion date has moved by 12 months from the original filing.
At a glance
Project
- NameRAJGAD RESIDENCY
- TypeResidential / Group Housing
- Location
- DEGAON ROAD
- MIDC
- Kodoli (CT)
- Satara
- 415003
- Pincode415003
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52700016106
- ReraGenie IDRG-MH-98785
Builder
- NameADITI BUILDCON
- Entity typePartnership
- PartnersADHIK BALKRISHNA JADHAV, ARCHANA RAHUL DESHAMUKHA, GHANSHYAM DAYARAM MATKAR, TEJAS DASHRATH JAGTAP, SANDEEP KRISHNAT CHAVAN
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on17 Apr 2018
- Promised completion29 Mar 2024
- Revised completionRevised to 29 Mar 2024 (originally 30 Mar 2023)
- Buildings2 building records
- Documents filed57 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING A WING C AND D | NA | 6 | 0 | 0 | 0 | 0 |
| BUILDING B - WING A AND B | NA | 7 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 21 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
18 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.
BUILDING A WING C AND D82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDING B - WING A AND B82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 21 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed2
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| BUILDING A WING C AND D | 1 | 1 |
| BUILDING B - WING A AND B | 1 | 1 |
Land and ownership2
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| VITTHAL RAMCHANDRA CHAVAN | Kodoli (CT) | Satara |
| SANDIP KRISHNAT CHAVAN | Kodoli (CT) | Satara |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | KIRAN MOHITE |
| Engineer | AJIT RAJPUT |
| Partner | Role in project |
|---|---|
| ADITI BUILDCON | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe have submitted application for completion of the project having name is Rajgad Residency to Collector office satara dated 16/02/2023. So we need addition time for receiving the completion certificate of the project from the authority. Kindly accept our project extension request.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Mar 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Mar 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 30 Mar 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 30 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 21 Oct 2024
Documents filed57
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate on Completion of Project (Form 4)File: form 4 complition.pdf | 21 Oct 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: complition Certificate 11.pdf | 21 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG.PDF | 21 Mar 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 878.pdf | 21 Mar 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Order 877.pdf | 21 Mar 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH MARCH.PDF | 12 Mar 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ARCH MARCH.PDF | 12 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A.PDF | 12 Mar 2024 |
| Certificates of CA (Form 3)File: CA MARCH 23.PDF | 12 Mar 2024 |
| Certificates of CA (Form 3)File: CA DEC 23.PDF | 12 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 22-23.PDF | 12 Mar 2024 |
| Declaration about Commencement CertificateFile: Format D - commencement certificate.pdf | 1 Mar 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: civil engineer certificate - june 21.pdf | 1 Mar 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: civil engineer certificate - sept 21.pdf | 1 Mar 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: civil engineer certificate - dec 21.pdf | 1 Mar 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: civil engineer certificate - march 22.pdf | 1 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: sold inventory Rera updation.pdf | 1 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 FY 21-22.pdf | 1 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: CA RERA certificate 1042017 to 31032018.pdf | 14 Nov 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: CA RERA Certificate 1042020 to 31032021.pdf | 14 Nov 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: CA RERA Certificate 1042021 to 31032022.pdf | 14 Nov 2022 |
| Proforma of Agreement for saleFile: PROFORMA OF Agreement to sale.pdf | 14 Nov 2022 |
| Proforma of Agreement for saleFile: PROFORMA of Agreement to sale compressed.pdf | 14 Nov 2022 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: society certificate.pdf | 14 Nov 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200248544628_For_Asset_Based_Search_30_09_2022_12_29_12_427.pdf | 30 Sep 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 C A CERTIFICATE 19-20.pdf | 26 Aug 2021 |
| Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMENT.pdf | 9 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: ENGG CERT 2A SEP 2019.pdf | 9 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: ENGG CERT 2A DEC 2019.pdf | 9 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: ENGG CERT 2A MAR 2020.pdf | 9 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ENGG CERT 2A JUN 2020.pdf | 9 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ENGG CERT 2A SEP 2020.pdf | 9 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ENGG CERT 2A SEP 2020.pdf | 9 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ENGG CERT 2A DEC 2020.pdf | 9 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ENGG CERT 2A MAR 2021.pdf | 9 Aug 2021 |
| Disclosure of sold/ booked inventoryFile: RERA BOOKED SOLD INVENTRY.pdf | 9 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: C_A_CERTIFICATE2.pdf | 5 Dec 2019 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: C_A_CERTIFICATE1.pdf | 5 Dec 2019 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: C_A_CERTIFICATE2.pdf | 5 Dec 2019 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: C_A_CERTIFICATE.pdf | 5 Dec 2019 |
| Declaration in FORM BFile: FORM B SANDIP.pdf | 17 Apr 2018 |
| Declaration in FORM BFile: FORM B VITTHAL.pdf | 17 Apr 2018 |
| Declaration in FORM BFile: FORM B SANDIP.pdf | 17 Apr 2018 |
| Declaration in FORM BFile: FORM B VITTHAL.pdf | 17 Apr 2018 |
| Building plan approvalFile: BUILDING PLAN1.pdf | 30 Mar 2018 |
| Layout approvalFile: BUILDING PLAN1.pdf | 30 Mar 2018 |
| Copy of the legal title reportFile: Search Report.pdf | 30 Mar 2018 |
| Details of encumbrancesFile: ENCUMBRANCE CERTIFICAGTE.pdf | 30 Mar 2018 |
| Copy of Layout Approval (in case of layout)File: BUILDING PLAN1.pdf | 30 Mar 2018 |
| Building Plan Approval (IOD)File: BUILDING PLAN1.pdf | 30 Mar 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: Order, Collector, Satara.pdf | 30 Mar 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 30 Mar 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer,s Certificate.pdf | 30 Mar 2018 |
| Certificates of CA (Form 3)File: C A Cert.pdf | 30 Mar 2018 |
| Proforma of Allotment letterFile: 000 ALLOTMENT LETTER RAJGAD RESIDENCY.pdf | 30 Mar 2018 |
| PAN CardFile: Pan Aditi Buildcon.pdf | 29 Mar 2018 |
| Declaration in FORM BFile: FORM B ADITI.pdf | 29 Mar 2018 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Satara
Computed across the 1,100+ Satara projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 57 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep RAJGAD RESIDENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MIDC1,100+ in Satara
Filed coordinates, straight-line distance. 49 registered projects within 2 km.
64 AVENUE
VISAVA BUILDCON LLP
NAIK PLAZA
CLASSIC CONSTRUCTIONS
99 AVENUE
RELIABLE VENTURE
MANGALMURTI COMPLEX
SANKALP DEVELOPERS
SHIVGAD RESIDENCY
ADITI BUILDERS
Mahagaon Hills
Vinod Chhaganmal Jain
See every Satara project, with the district possession charts
Builder: ADITI BUILDCON
ADITI BUILDCON has 1 registration on MahaRERA, including RAJGAD RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Satara district page.
Frequently asked questions
What does it mean that RAJGAD RESIDENCY shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if RAJGAD RESIDENCY is delayed beyond 29 Mar 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of RAJGAD RESIDENCY?
The registered promoter entity is ADITI BUILDCON, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in RAJGAD RESIDENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for RAJGAD RESIDENCY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at RAJGAD RESIDENCY?
The professionals named in the filing: Architect: KIRAN MOHITE; Engineer: AJIT RAJPUT. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in RAJGAD RESIDENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback