Home / Browse projects / Pune, Maharashtra / Rahul Downtown - Phase II

Registered No litigation declared Others project

Rahul Downtown - Phase II

By Paras Multispace LLP

RG-MH-34366 · RERA P52100050682 · Last updated on MahaRERA portal: 18 Jul 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 4 months
  • 1 extension taken
  • Rs 102.00 crore secured on the land, in favour of Axis Bank
  • The declared charge does not appear in the CERSAI report on the filing

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Apr 2027Possession promisedmoved 4 months from the original
21 of 42Construction stages doneacross 4 buildings; furthest along: Staircases, 90%
276 of 664Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 143 documents Report an error

Rahul Downtown - Phase II is a Others project by Paras Multispace LLP in Pune, Maharashtra, registered with MahaRERA as P52100050682 on 28 Apr 2023. Possession is promised by 30 Apr 2027. The completion date has moved by 4 months from the original filing. 388 of the 664 units on this registration are recorded sold or booked, and 21 of 42 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameRahul Downtown - Phase II
  • TypeOthers
  • Location
    • Next to Sai Paradise
    • Punawale
    • Mulshi
    • Pune
    • 411033
  • Pincode411033
  • RERA no.P52100050682
  • ReraGenie IDRG-MH-34366

Builder

  • NameParas Multispace LLP
  • Entity typePartnership
  • GSTIN27AAPFP4794B1ZV
  • PartnerSiddharth Raichand Kunkulol
  • Other registrations1 more →
  • Completed1 of 2

Key dates

this monthRegisteredApr 2023First promiseDec 2026Revised toApr 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on28 Apr 2023
  • Promised completion30 Apr 2027
  • Revised completionRevised to 30 Apr 2027 (originally 31 Dec 2026)
  • Buildings4 building records
  • Documents filed143 files

Current status

58%388 of 664 units booked
66.1%Work done, per cost certificate

Figures as on 18 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Bldg AA30272080208
Bldg BNA30272120212
Bldg CNA30272120212
Bldg AA16403232

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 18 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

21 of 42 construction stages are filed complete across 4 buildings. The stage furthest along is Staircases, at 90%.

Bldg A · wing A59%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises25%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks25%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bldg A · wing A181%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
Bldg B50%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises25%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks25%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bldg C45%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 18 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed1181

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1,181
Closed/Covered1,181
BuildingClosed/CoveredTotal
Bldg A A324324
Bldg A A1173173
Bldg B334334
Bldg C350350

Land and ownership3

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area27,649 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared present
Charge in favour ofAxis Bank
Secured amountRs 102.00 crore
CERSAI search filedYes
Declared on1 Jul 2025
LandownerVillageDistrict
Shri Sambhaji ShindePune (M Corp.)Pune
Shri Tanaji Keru ShindePune (M Corp.)Pune
Shri Rajendra Dnyanoba ShindePune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPCMC
Permissible FSI68554.96
Proposed, not sanctioned68,538 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch214-215 City Mall, Ganeshkhind, Pune 411007
Estimated costRs 241.93 cr
Cost incurredRs 160.00 cr
Work done66.14%
BuildingWingEstimatedIncurred
Bldg AARs 76.14 crRs 55.75 cr
Bldg CNARs 67.36 crRs 49.32 cr
Bldg BNARs 67.36 crRs 49.32 cr
-NARs 23.41 cr-
Bldg AA1Rs 7.66 crRs 5.61 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPandit Joshi & Associates
EngineerMr Suraj Sitaram Jadhav
Chartered AccountantK G Jhamvar & Co
Chartered AccountantSameer Rajanikant Birla
PartnerRole in project
Paras Multispace LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA14052620958Dec 2026 → Apr 2027

Reason as filed by the promoterRespected Sir/Madam, We, the promoters of Rahul Downtown - Phase II, registered with the Authority under Registration No. P52100050682, humbly submit this application seeking extension of project registration up to 30/04/2027 for completion of the balance construction work and procurement of the Occupancy Certificate. The present completion date is 31/12/2026. Considering unavoidable circumstances affecting construction activities, we request an extension of four months. The registered Agreement for Sale executed with the allottees also provides that in the event of reasonable circumstances be

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
SM12600066Ram GawaliParas Multispace LLP22/01/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Mar 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Oct 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Oct 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Feb 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Apr 2027

Documents filed143

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 143 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 - Rahul Downtown II.pdf18 Jul 2026
Withdrawal Update Form 2File: Downtown Phase II Form 2.pdf18 Jul 2026
Withdrawal Update Form 3File: Downtown Phase II Form 3.pdf18 Jul 2026
Withdrawal Update Form 1File: Form 1 - Downtown II.pdf25 May 2026
Withdrawal Update Form 2File: Form 2 - Downtown II.pdf25 May 2026
Withdrawal Update Form 3File: Form 3 - Generated form RERA portal.pdf25 May 2026
Withdrawal Update Form 1File: Form 1 - Downtown II.pdf20 Apr 2026
Withdrawal Update Form 2File: Form 2 - Downtown II.pdf20 Apr 2026
Withdrawal Update Form 3File: Form 3 - Downtown II.pdf20 Apr 2026
Form 2A (FY 2025-2026)File: Form 2A - Downtown II.pdf1 Apr 2026
Withdrawal Update Form 1File: Form 1 - Rahul Downtown II.pdf14 Jan 2026
Withdrawal Update Form 2File: Form 2 - Downtown.pdf14 Jan 2026
Withdrawal Update Form 3File: Form 3 - Downtown.pdf14 Jan 2026
Withdrawal Update Form 1File: Rahul Downtown Form - 1.pdf18 Oct 2025
Withdrawal Update Form 1File: Rahul Downtown Form - 1.pdf18 Oct 2025
Withdrawal Update Form 2File: Form 2 - Downtown II.pdf18 Oct 2025
Withdrawal Update Form 2File: Form 2 - Downtown II.pdf18 Oct 2025
Withdrawal Update Form 3File: Form 3 - Paras Multispace.pdf18 Oct 2025
Withdrawal Update Form 3File: Form 3 - Paras Multispace.pdf18 Oct 2025
Layout approvalFile: Layout Plan.pdf13 Oct 2025
Building plan approvalFile: Basement 1 - Basement 2.pdf13 Oct 2025
Building plan approvalFile: Bldg A - First Floor.pdf13 Oct 2025
Building plan approvalFile: Bldg A - Ground Floor.pdf13 Oct 2025
Building plan approvalFile: Bldg A - Typical Floor.pdf13 Oct 2025
Building plan approvalFile: Bldg A1 - 2nd 3 rd Floor.pdf13 Oct 2025
Building plan approvalFile: Bldg B - Ground & First Floor.pdf13 Oct 2025
Building plan approvalFile: Bldg B - Typical Floor.pdf13 Oct 2025
Building plan approvalFile: Bldg C - Ground First.pdf13 Oct 2025
Building plan approvalFile: Bldg C - Typical Floor.pdf13 Oct 2025
Building plan approvalFile: Section A.pdf13 Oct 2025
Form 5 (FY 2024-2025)File: Rahul Downtown - II - Form 5.pdf30 Sep 2025
Withdrawal Update Form 1File: Form 1 - Downtown II.pdf20 Jul 2025
Withdrawal Update Form 1File: Form 1 - Downtown II.pdf20 Jul 2025
Withdrawal Update Form 2File: Form 2 - Downtown.pdf20 Jul 2025
Withdrawal Update Form 2File: Form 2 - Downtown.pdf20 Jul 2025
Withdrawal Update Form 3File: Form 3 Downtown.pdf20 Jul 2025
Withdrawal Update Form 3File: Form 3 Downtown.pdf20 Jul 2025
Layout approvalFile: Layout Plan.pdf5 Jul 2025
Form 2A (FY 2024-2025)File: 2A - Downtown II - 24-25.pdf27 Jun 2025
Form 2A (FY 2023-2024)File: Form 2A - Phase II - 2023-2024.pdf25 Jun 2025
Form 1File: Form 1 - 30-06-2023 --1.pdf20 Jun 2025
Form 2File: Form 2 - 30-06-2023 -- 1.pdf20 Jun 2025
Form 3File: Form 3_compressed.pdf20 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure - July 2023.pdf20 Jun 2025
Form 1File: Form 1 - Phase II -- 2.pdf20 Jun 2025
Form 2File: Form 2 - --2.pdf20 Jun 2025
Form 3File: Form 3 - Phase II.pdf20 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold -2.pdf20 Jun 2025
Form 1File: Form 1 - 30-12-2023 - 3.pdf20 Jun 2025
Form 2File: Form 2 -.pdf20 Jun 2025
Form 3File: Form 3 - Phase II - 3_compressed.pdf20 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure - Phase II --3.pdf20 Jun 2025
Form 1File: Form 1 - Downtown II.pdf20 Jun 2025
Form 2File: Form 2 Ph II Downtown.pdf20 Jun 2025
Form 3File: Form 3 - Downtown II.pdf20 Jun 2025
Disclosure of Sold and Booked InventoryFile: downtown II - Sold Inventory.pdf20 Jun 2025
Form 1File: Form 1 - Downtown Phase II.pdf20 Jun 2025
Form 2File: Form 2 - Downtown II.pdf20 Jun 2025
Form 3File: Form 3 Downtown II.pdf20 Jun 2025
Disclosure of Sold and Booked InventoryFile: Sold Inventory Downtown II.pdf20 Jun 2025
Form 1File: Form 1 - Downtown II.pdf20 Jun 2025
Form 2File: Form 2 - Phase II.pdf20 Jun 2025
Form 3File: Form 3 - Downtown II.pdf20 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure - Downtown II.pdf20 Jun 2025
Form 1File: Form 1 - Downtown II.pdf20 Jun 2025
Form 2File: Form 2 - Downtown II.pdf20 Jun 2025
Form 3File: Form 3 - Downtown II.pdf20 Jun 2025
Disclosure of Sold and Booked InventoryFile: Downtown II - Disclosure of Sold.pdf20 Jun 2025
Form 1File: Form 1 Downtown - II.pdf20 Jun 2025
Form 2File: Phase-II Form 2.pdf20 Jun 2025
Form 3File: Phase II Form 3 Downtown.pdf20 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure - Downtown II.pdf20 Jun 2025
Form 5 (FY 2023-2024)File: Form 5 - Rahul Downtown Phase II.pdf14 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Phase II.pdf24 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Phase-II Form 2.pdf24 Apr 2025
Disclosure of sold/ booked inventoryFile: Rahul Downtown - II.pdf31 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Rahul Downtown - II.pdf29 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Downtown II.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Downtown II.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Downtown II - Disclosure of Sold.pdf6 Jan 2025

How this compares with Pune

58%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 4 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Rahul Downtown - Phase II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Punawale13,700+ in Pune

Builder: Paras Multispace LLP

Paras Multispace LLP has 2 registrations on MahaRERA, including Rahul Downtown - Phase I and Rahul Downtown - Phase II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Rahul Downtown - Phase II is delayed beyond 30 Apr 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Rahul Downtown - Phase II?

The registered promoter entity is Paras Multispace LLP, a partnership as per the filing. Its GSTIN 27AAPFP4794B1ZV can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Rahul Downtown - Phase II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Rahul Downtown - Phase II?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Rahul Downtown - Phase II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Rahul Downtown - Phase II?

The professionals named in the filing: Architect: Pandit Joshi & Associates; Engineer: Mr Suraj Sitaram Jadhav; Chartered Accountant: K G Jhamvar & Co; Chartered Accountant: Sameer Rajanikant Birla. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Rahul Downtown - Phase II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Rahul Downtown - Phase II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Rahul Downtown - Phase II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.