Radhe Govind Commercial Complex
RG-MH-59258 · RERA P51700045967 · Last updated on MahaRERA portal: 31 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 36 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Radhe Govind Commercial Complex is a Commercial project by Shree Radha Construction in Thane, Maharashtra, registered with MahaRERA as P51700045967 on 15 Jun 2022. Possession is promised by 31 Dec 2026. The completion date has moved by 36 months from the original filing. 4 of the 40 units on this registration are recorded sold or booked, and 5 of 22 construction stages are filed complete.
At a glance
Project
- NameRadhe Govind Commercial Complex
- TypeCommercial
- Location
- Morivali
- Morivali Ambarnath
- Ambarnath (R)
- Ambarnath
- Thane
- 421501
- Pincode421501
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700045967
- ReraGenie IDRG-MH-59258
Builder
- NameShree Radha Construction
- Entity typePartnership
- PartnersRakesh Parshuram Dalal, Mahendra Govind Dalal, Rupesh Parshuram Dalal, Sharad Govind Dalal, Nachiket Ashok Dalal, Nandakumar Govinda Dalal, Mayuresh Ashok Dalal, Ravindra Govind Dalal
- Other registrations2 more →
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on15 Jun 2022
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2023)
- Buildings2 building records
- Documents filed53 files
Current status
Figures as on 31 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Wing A | NA | 8 | 0 | 0 | 10 | 10 |
| Wing B | NA | 8 | 8 | 0 | 30 | 30 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 31 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 85%.
Wing A20%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 25% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Wing B48%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 85% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 60% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 31 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed122
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| Wing A | 61 | 61 |
| Wing B | 61 | 61 |
Land and ownership26
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Radhabai Govind Dalal | Badlapur (M Cl) | Thane |
| Sandhya Parshuram Dalal | Badlapur (M Cl) | Thane |
| Rupesh Parshuram Dalal | Badlapur (M Cl) | Thane |
| Rachana Parshuram Dalal | Badlapur (M Cl) | Thane |
| Ashok Govind Dalal | Badlapur (M Cl) | Thane |
| Asha Ashok Dalal | Badlapur (M Cl) | Thane |
| Mayuresh Ashok Dalal | Badlapur (M Cl) | Thane |
| Shraddha Ashok Dalal | Badlapur (M Cl) | Thane |
| Nandkumar Govind Dalal | Badlapur (M Cl) | Thane |
| Rakesh Parshuram Dalal | Badlapur (M Cl) | Thane |
| Namrata Nandkumar Dalal | Badlapur (M Cl) | Thane |
| Nikhil Nandkumar Dalal | Badlapur (M Cl) | Thane |
| Janhvi Nandkumar Dalal | Badlapur (M Cl) | Thane |
| Ravindra Govind Dalal | Badlapur (M Cl) | Thane |
| Pratibha Ravindra Dalal | Badlapur (M Cl) | Thane |
| Mahendra Govind Dalal | Badlapur (M Cl) | Thane |
| Seema Mahendra Dalal | Badlapur (M Cl) | Thane |
| Sharad Govind Dalal | Badlapur (M Cl) | Thane |
| Ranjeet Sharad Dalal | Badlapur (M Cl) | Thane |
| Surekha Shantaram Aalashi | Badlapur (M Cl) | Thane |
| Vishakha Vilas Angre | Badlapur (M Cl) | Thane |
| Kshama Mohan Khismatrao | Badlapur (M Cl) | Thane |
| Ganesh Yashwant Sontakke | Badlapur (M Cl) | Thane |
| Mangesh Yashwant Sontakke | Badlapur (M Cl) | Thane |
| Umesh Yashwant Sontakke | Badlapur (M Cl) | Thane |
| Sudesh Yashwant Sontakke | Badlapur (M Cl) | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Wing A | NA | Rs 4.33 cr | Rs 2.38 cr |
| Wing B | NA | Rs 2.02 cr | Rs 1.82 cr |
| - | NA | Rs 42.28 lakh | - |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Satish Kanade |
| Engineer | Atul Kudtarkar |
| Chartered Accountant | Rutuja Narsingh and Associates |
| Chartered Accountant | SANKET HARILAL KHOLIYA |
| Partner | Role in project |
|---|---|
| Shree Radha Construction | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. As we have 0 Sold units, consents are not required for purpose of extension of RERA registration period of the said project
Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B.The project was delayed for reasons beyond our control on account of various reasons and more particularly on account non sold of the units, we have sold 4 units and rest will be unsold , we have taken the consent from the unit holders its required for the purpose of RERA Extension of the project
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 12 May 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 19 May 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 19 May 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 5 May 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed53
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 A and B wing Q4.pdf | 31 Jul 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 31 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 A and B wing Q4.pdf | 31 Jul 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 31 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 A and B wing Q4.pdf | 31 Jul 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 31 Jul 2026 |
| Withdrawal Update Form 1File: form 1 A and B wing Q3FY 25-26.pdf | 29 Jan 2026 |
| Withdrawal Update Form 2File: Form2 A and B wing Q3 FY 25-26.pdf | 29 Jan 2026 |
| Withdrawal Update Form 3File: Form 3 Radhe Govind Commercial Complex A and B Wing.pdf | 29 Jan 2026 |
| Withdrawal Update Form 1File: Form 1 Radhe comm complex A u0026 B wing.pdf | 6 Nov 2025 |
| Withdrawal Update Form 2File: form 2 Radhe comm complex A u0026B wing Q2.pdf | 6 Nov 2025 |
| Withdrawal Update Form 3File: Radhe govind commercial complex wing au0026b.pdf | 6 Nov 2025 |
| Form 1File: Q4 FY 24-25AandB wing Architect certificate.pdf | 16 Oct 2025 |
| Form 2File: Q4 FY 24-25 AandB wing Radhe Govind Commercial complex Form 2.pdf | 16 Oct 2025 |
| Form 3File: CA CERTIFICTE FORM 3.pdf | 16 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: March 25.pdf | 16 Oct 2025 |
| Withdrawal Update Form 1File: Q4 FY 24-25AandB wing Architect certificate.pdf | 16 Oct 2025 |
| Withdrawal Update Form 1File: au0026b wing form 1.pdf | 16 Oct 2025 |
| Withdrawal Update Form 2File: 1 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf | 16 Oct 2025 |
| Withdrawal Update Form 2File: Form 2 Engg certificate Au0026B Wing RadheGovind Commercial COmplex.pdf | 16 Oct 2025 |
| Withdrawal Update Form 3File: CA CERTIFICTE FORM 3.pdf | 16 Oct 2025 |
| Withdrawal Update Form 3File: Form 3 CA certificate Au0026B Wing RadheGovind Commercial COmplex.pdf | 16 Oct 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q4 FY 24-25AandB wing Architect certificate.pdf | 10 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Q4 FY 24-25 CA CERTIFICATE RADHE GOVIND COMM COMPLEX.pdf | 10 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q4 FY 24-25 AandB wing Radhe Govind Commercial complex Form 2.pdf | 10 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Radhe Govind Commercial Complex as on 30-06-2023.pdf | 25 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf | 25 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22-23 AB wing.pdf | 14 Aug 2023 |
| Declaration about Commencement CertificateFile: Format D A B wing.pdf | 9 Aug 2023 |
| Declaration in FORM BFile: Form B A B wing.pdf | 9 Aug 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate A B Wing.pdf | 9 Aug 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate A B WIng.pdf | 9 Aug 2023 |
| Disclosure of sold/ booked inventoryFile: CIRCULAR-29 A B wing.pdf | 9 Aug 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate A B Wing.pdf | 9 Aug 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate A B Wing.pdf | 9 Aug 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Merged Form 3 Radhe Govind.pdf | 25 May 2022 |
| Layout approvalFile: PAGE 1 (1)_11zon.pdf | 19 May 2022 |
| Building plan approvalFile: PAGE 2_11zon_11zon.pdf | 19 May 2022 |
| Building plan approvalFile: PAGE 3_11zon.pdf | 19 May 2022 |
| Building plan approvalFile: PAGE 4_11zon.pdf | 19 May 2022 |
| Copy of Layout Approval (in case of layout)File: PAGE 1 (1)_11zon.pdf | 19 May 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: PAGE 2_11zon_11zon.pdf | 19 May 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: PAGE 3_11zon.pdf | 19 May 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: PAGE 4_11zon.pdf | 19 May 2022 |
| Copy of the legal title reportFile: MahaRERA Title - Radhe.pdf | 12 May 2022 |
| Details of encumbrancesFile: Encumbrance.pdf | 12 May 2022 |
| Declaration about Commencement CertificateFile: CC Declaration Revised.pdf | 12 May 2022 |
| Declaration in FORM BFile: affidavit company (1).pdf | 12 May 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200237152124_For_Asset_Based_Search_11_05_2022_18_31_37_997.pdf | 12 May 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: cc 2022_compressed.pdf | 5 May 2022 |
| Proforma of Allotment letterFile: Allotment Letter.pdf | 5 May 2022 |
| Proforma of Allotment letterFile: Flat Sale Agreement Rera A and B wing.pdf | 27 Apr 2022 |
| PAN CardFile: pancard Shree radha Construction.pdf | 26 Apr 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 53 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Radhe Govind Commercial Complex on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Morivali Ambarnath7,600+ in Thane
Filed coordinates, straight-line distance. 174 registered projects within 2 km.
CHADHA RESIDENCY
CHADHA DEVELOPERS AND PROMOTERS
KRUSHNA VIHAR - PHASE I
KRUSHAN DHAM BUILDERS & DEVELOPERS
VISHWAJEET MYSPACE
GULABRAO BABURAO KARANJULE PATIL
KHATRI SPARSH
KHATRI REALTY
Tulsi Galaxy
Manas Associates
WALEKAR HOMES
WALEKAR & SON'S DEVELOPERS
See every Thane project, with the district possession charts
Builder: Shree Radha Construction
Shree Radha Construction has 3 registrations on MahaRERA, including Radhe Govind Commercial Complex and Radhe Govind Commercial Complex. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if Radhe Govind Commercial Complex is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Radhe Govind Commercial Complex?
The registered promoter entity is Shree Radha Construction, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Radhe Govind Commercial Complex?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Radhe Govind Commercial Complex?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Radhe Govind Commercial Complex?
The professionals named in the filing: Architect: Satish Kanade; Engineer: Atul Kudtarkar; Chartered Accountant: Rutuja Narsingh and Associates; Chartered Accountant: SANKET HARILAL KHOLIYA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Radhe Govind Commercial Complex?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback