R7 - THE ALTIUS

By PARANJAPE SPACES AND SERVICES PVT LTD

RG-MH-19080 · RERA P52100078116 · Last updated on MahaRERA portal: 10 Nov 2025

Source: official MahaRERA filing

Red flags

  • Litigation declared, 3 cases

Clear

  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jan 2030Possession promisedno revision filed
0 of 11Construction stages donefurthest along: Excavation, 20%
78 of 138Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 61 documents Report an error

R7 - THE ALTIUS is a Residential / Group Housing project by PARANJAPE SPACES AND SERVICES PVT LTD in Pune, Maharashtra, registered with MahaRERA as P52100078116 on 25 Nov 2024. Possession is promised by 31 Jan 2030. 60 of the 138 units on this registration are recorded sold or booked, and 0 of 11 construction stages are filed complete.

At a glance

Project

  • NameR7 - THE ALTIUS
  • TypeResidential / Group Housing
  • Location
    • Hinjavadi
    • Hinjavadi (CT)
    • Mulshi
    • Pune
    • 411057
  • Pincode411057
  • RERA no.P52100078116
  • ReraGenie IDRG-MH-19080

Builder

  • NamePARANJAPE SPACES AND SERVICES PVT LTD
  • Entity typeCompany
  • DirectorsSACHIN BHALCHANDRA HIRAP, Pushkar Pramod Apte, Uttam Sambhaji Redkar
  • Other registrations3 more →

Key dates

this monthRegisteredNov 2024PromisedJan 2030

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on25 Nov 2024
  • Promised completion31 Jan 2030
  • Revised completionNone
  • Buildings1 building record
  • Documents filed61 files

Current status

43%60 of 138 units booked
10.9%Work done, per cost certificate

Figures as on 10 Nov 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
The AltiusNA39391308138

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 10 Nov 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 20%.

The Altius: 2% average across the applicable activities

ActivityProgress
Excavation20%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 10 Nov 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed830

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots830
Closed/Covered302
Open Space528

Land and ownership3

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,500 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on8 Sep 2025
LandownerVillageDistrict
Chatura PoojariPune (M Corp.)Pune
Balbir Singh GariaPune (M Corp.)Pune
Paranjape Schemes (Construction) LimitedPune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPune Metropolitan Region Development Authority, Pune
Permissible FSI23086.19
Proposed, not sanctioned23,086 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchLAUKIK APARTMENT SGROUND FLOOR,PLOT NO 3, CTS NO 870 BHANDARKAR ROAD PUNE MAHARASHTRA 411004
Estimated costRs 117.77 cr
Cost incurredRs 12.86 cr
Work done10.92%
BuildingWingEstimatedIncurred
The AltiusNARs 91.89 crRs 1.02 cr
-NARs 25.88 crRs 11.84 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANDEEP HARDIKAR & ASSOCIATES
EngineerDeepali Desai
EngineerSACHIN GITE
Chartered AccountantKapure & Kapure
Chartered AccountantMSKA & Associates
PartnerRole in project
PARANJAPE SPACES AND SERVICES PVT LTD-

Litigation declared3

CaseCourtStatus
9028/2017/2017Bombay High CourtMatter is kept for pre admission according to sitting list
9029/2017/2017Bombay High CourtMatter is kept for pre admission according to sitting list
WPST/6443/2016/2016Bombay High CourtMatter is kept for pre admission according to sitting list

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 13 Nov 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 7 Nov 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 7 Nov 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 Nov 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Jan 2030

Documents filed61

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2024-2025)File: Form 5_R47_Signed.pdf10 Nov 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- R7 Altius-Mar'25-uploaded.pdf28 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: R-7 The Altius.pdf11 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-Altius Dec'24 form 1 signedoff-uploaded.pdf1 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-Altius Dec'24 form 1 signedoff-uploaded.pdf1 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-R7- The Altius-Dec'24-uploaded.pdf16 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-R7- The Altius-Dec'24-uploaded.pdf16 Jan 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: 202411211030.pdf21 Nov 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: FORMAT B- Declaration by Bank-PSCL-CoPromoter-R7 The Altius.pdf21 Nov 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: FORMAT B- Declaration by Bank-PSCL-CoPromoter-R7 The Altius.pdf21 Nov 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: 202411211030.pdf21 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3_R7 Altius_181124_compressed.pdf18 Nov 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B Bank letterhead PSSPL.pdf18 Nov 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B Bank letterhead PSSPL.pdf18 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3_R7 Altius_181124_compressed.pdf18 Nov 2024
Other - FinanceFile: Declaration cum undertaking for no sale by Shopowners- for PSSPL.pdf15 Nov 2024
Copy of the legal title reportFile: LEGAL TITLE REPORT UPDATED 3.pdf13 Nov 2024
Other - LegalFile: Assigment Deed.pdf13 Nov 2024
Other - FinanceFile: Declrn of no sale by Landowner-Singh.pdf13 Nov 2024
Other - FinanceFile: Declrn of no sale by Landowner-Pujari.pdf13 Nov 2024
Other - FinanceFile: Declaration of no sale by landowner-Chauhan.pdf13 Nov 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Report-AFS- R7.pdf13 Nov 2024
Proforma of Agreement for saleFile: 1309 24 9 1 clean 28 10 24 AFS - ALTIUS R7.pdf13 Nov 2024
Building plan approvalFile: Plan 10.pdf7 Nov 2024
Building plan approvalFile: Plan 9.pdf7 Nov 2024
Building plan approvalFile: Plan 8.pdf7 Nov 2024
Building plan approvalFile: Plan 7.pdf7 Nov 2024
Building plan approvalFile: Plan 6.pdf7 Nov 2024
Building plan approvalFile: Plan 5.pdf7 Nov 2024
Building plan approvalFile: Plan 4.pdf7 Nov 2024
Building plan approvalFile: Plan 3.pdf7 Nov 2024
Building plan approvalFile: Plan 2.pdf7 Nov 2024
Layout approvalFile: Plan 1.pdf7 Nov 2024
Copy of Layout Approval (in case of layout)File: Plan 1.pdf7 Nov 2024
Building Plan Approval / NA Order for plotted developmentFile: Plan 10.pdf7 Nov 2024
Building Plan Approval / NA Order for plotted developmentFile: Plan 2.pdf7 Nov 2024
Building Plan Approval / NA Order for plotted developmentFile: Plan 3.pdf7 Nov 2024
Building Plan Approval / NA Order for plotted developmentFile: Plan 4.pdf7 Nov 2024
Building Plan Approval / NA Order for plotted developmentFile: Plan 5.pdf7 Nov 2024
Building Plan Approval / NA Order for plotted developmentFile: Plan 6.pdf7 Nov 2024
Building Plan Approval / NA Order for plotted developmentFile: Plan 7.pdf7 Nov 2024
Building Plan Approval / NA Order for plotted developmentFile: Plan 8.pdf7 Nov 2024
Building Plan Approval / NA Order for plotted developmentFile: Plan 9.pdf7 Nov 2024
Disclosure for secured/unsecured finance availed for the projectFile: 13 Declaration of Secured Unsecured Loans-R7 The altius.pdf7 Nov 2024
Proforma of Allotment letterFile: 11 Proforma-Allotment letter-R7 The Altius-as per Order 60.pdf6 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf6 Nov 2024
CERSAI detailsFile: CERSAI declaration.pdf6 Nov 2024
Deviation Report with respect to Allotment letterFile: 12 Deviation Report of Allotment Letter-R7 The Altius.pdf6 Nov 2024
Other - TechnicalFile: 23 Declaration cum Undertaking-PSSPL-R7 The Altius.pdf6 Nov 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A- Pushkar Apte-Disclosure of Interest-R7-The Altius.pdf6 Nov 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A -R7- The altius-PSSPL- Sachin hirap-Disclosure of Interest.pdf6 Nov 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A-Uttam Redkar-Disclosure of Interest-R7-The Altius.pdf6 Nov 2024
PAN CardFile: 1 PAN Card.pdf4 Nov 2024
Details of encumbrances concerned to FinanceFile: 10 Declaration -Encumbrances-R7-The Altius.pdf4 Nov 2024
Details of encumbrances concerned to FinanceFile: 6 Encumbrance - legal-R7-The Altius.pdf4 Nov 2024
Declaration in FORM BFile: 7 Form B-Promoter-R7 The Altius.pdf4 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 22 FORM 1-R7 The altius.pdf4 Nov 2024
Commencement Certificates / NA Order for plotted developmentFile: Commencement-sector R7 -22Oct'24.pdf4 Nov 2024
Declaration about Commencement CertificateFile: 5 Declaration for Commencement Certificate-R7-The Altius.pdf4 Nov 2024
Details of encumbrances concerned to LegalFile: 10 Declaration -Encumbrances-R7-The Altius.pdf4 Nov 2024
Details of encumbrances concerned to LegalFile: 6 Encumbrance - legal-R7-The Altius.pdf4 Nov 2024

How this compares with Pune

43%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep R7 - THE ALTIUS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Hinjavadi13,700+ in Pune

Builder: PARANJAPE SPACES AND SERVICES PVT LTD

PARANJAPE SPACES AND SERVICES PVT LTD has 4 registrations on MahaRERA, including R 47 -HIGHGARDENS and PARANJAPE ATHENA. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if R7 - THE ALTIUS is delayed beyond 31 Jan 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of R7 - THE ALTIUS?

The registered promoter entity is PARANJAPE SPACES AND SERVICES PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in R7 - THE ALTIUS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for R7 - THE ALTIUS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at R7 - THE ALTIUS?

The professionals named in the filing: Architect: SANDEEP HARDIKAR & ASSOCIATES; Engineer: Deepali Desai; Engineer: SACHIN GITE; Chartered Accountant: Kapure & Kapure; Chartered Accountant: MSKA & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in R7 - THE ALTIUS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About R7 - THE ALTIUS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save R7 - THE ALTIUS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.