Quality Annex

By Quality Annex

RG-MH-66703 · RERA P51700018212 · Last updated on MahaRERA portal: 6 Jun 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Sep 2026Possession promisedregistration recorded completed
11 of 11Construction stages doneevery applicable stage filed complete
0Complaints at MahaRERAon this registration
Jump to the 89 documents Report an error

Quality Annex is a Residential / Group Housing project by Quality Annex in Thane, Maharashtra, registered with MahaRERA as P51700018212 on 15 Oct 2018. The registration is recorded completed; possession was promised by 30 Sep 2026.

At a glance

Project

  • NameQuality Annex
  • TypeResidential / Group Housing
  • Location
    • Survey No 201
    • Hissa No -6A
    • Shilphata
    • Thane (M Corp.)
    • Thane
    • 400612
  • Pincode400612
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700018212
  • ReraGenie IDRG-MH-66703

Builder

  • NameQuality Annex
  • Entity typePartnership
  • PartnersSirajuddin Ajeem Sayyed, Niyamat Ali Mohammed Nazir Shaikh, Arif Ali Azeez Mulani, Mohammed Humayun Shaikh, Nadeem Altaf Shaikh

Key dates

this monthRegisteredOct 2018PromisedSep 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on15 Oct 2018
  • Promised completion30 Sep 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed89 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Quality AnnexNA160000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 6 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

Quality Annex: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities17

As on 6 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
Solar Panel InstallationYes100%
DG InstallationYes100%

Parking filed57

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots57
Closed/Covered45
Open Space12

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,050 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Wasiuddin Mohibuddin KhanThane (M Corp.)Thane

Approvals and building plan

Permissible FSI3197.26
Proposed, not sanctioned1,732 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchD-9/10/25/26,Nasheman Industrial Complex, Mek Engineering Works, Mumbra -400612

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJoshi Deshaware Associates
EngineerSK Consultants & Engineers
Chartered AccountantRutuja Narsingh & Associates
PartnerRole in project
Quality Annex-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Oct 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Oct 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Jul 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Jan 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 6 Jun 2025

Documents filed89

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 89 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 2 Occupancy Certificate_ Completion Certificate_ Architect's certificate of completion for6 Jun 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 1 Occupancy Certificate_ Completion Certificate_ Architect's certificate of completion for20 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf15 Feb 2025
Certificates of CA (Form 3)File: 21 Certificates of CA (Form 3).pdf15 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 19 Certificates of Engineer (Form 2)(Mandatory for only ongoing project).pdf15 Feb 2025
Architect’s Certificate on Completion of Project (Form 4)File: QA.pdf31 Dec 2024
Architect’s Certificate on Completion of Project (Form 4)File: declaration (5)_merged (1).pdf24 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf16 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 18 Certificates of Engineer (Form 2)(Mandatory for only ongoing project).pdf16 Jul 2024
Certificates of CA (Form 3)File: 20 Certificates of CA (Form 3).pdf16 Jul 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Oc Niyamat Ali.pdf17 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Quality Annex as on September 2023.pdf30 Dec 2023
Certificates of CA (Form 3)File: Form 3 - Quality Annex as on September 2023.pdf30 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5- Quality Annex as on 31-03-2023.pdf16 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Quality Annex as on June 2023.pdf1 Aug 2023
Certificates of CA (Form 3)File: Form 3- Quality Annex as on 30-06-2023.pdf1 Aug 2023
Building plan approvalFile: S11-0013-09_compressed-1.pdf4 Jul 2023
Building plan approvalFile: S11-0013-09_compressed-2.pdf4 Jul 2023
Building plan approvalFile: S11-0013-09_compressed-3.pdf4 Jul 2023
Building plan approvalFile: S11-0013-09_compressed-4.pdf4 Jul 2023
Building plan approvalFile: S11-0013-09_compressed-5.pdf4 Jul 2023
Building Plan Approval (IOD)File: S11-0013-09_compressed-1.pdf4 Jul 2023
Building Plan Approval (IOD)File: S11-0013-09_compressed-2.pdf4 Jul 2023
Building Plan Approval (IOD)File: S11-0013-09_compressed-3.pdf4 Jul 2023
Building Plan Approval (IOD)File: S11-0013-09_compressed-4.pdf4 Jul 2023
Building Plan Approval (IOD)File: S11-0013-09_compressed-5.pdf4 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf21 Apr 2023
Certificates of CA (Form 3)File: New format- Form 3 Quality Annex.pdf21 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Quality Annex Dec 22 - Form 2.pdf11 Apr 2023
Certificates of CA (Form 3)File: Form 3- Quality Annex as on December 2022.pdf11 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 1 Annual Audit Report of Statutory CA (Form 5).pdf7 Apr 2023
Commencement Certificates / NA Order for plotted developmentFile: Quality Annex CC.pdf30 Jan 2023
Declaration about Commencement CertificateFile: Format D- Quality Annex.pdf30 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Quality Annex as on September 2022.pdf21 Dec 2022
Certificates of CA (Form 3)File: Form 3 Quality Annex 30th Sept 2022.pdf21 Dec 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Quality Annex.PDF15 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Certificate 257.pdf30 Sep 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Quality Annex- June 2022.pdf24 Aug 2022
Certificates of CA (Form 3)File: New format- Form 3 Quality Annex 30th June 22.pdf24 Aug 2022
Certificates of CA (Form 3)File: Form 3 Quality Annex 31st March 2022_compressed.pdf2 Jun 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Quality Annex 31st March 2022.pdf16 May 2022
CERSAI detailsFile: Quality Annex.pdf16 May 2022
Certificates of CA (Form 3)File: Form 3 Quality Annex 31st March 2022_11zon.pdf16 May 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Quality Annex_compressed.pdf7 Feb 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Quality Annex Dec 2021_compressed.pdf7 Feb 2022
Certificates of CA (Form 3)File: Form 3 Quality Annex 31st December 2021_compressed.pdf7 Feb 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Quality Annex Form 5 FY 2019-2020.pdf29 Nov 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Quality Annex Form 5 FY 2020-2021.pdf29 Nov 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Quality Annex Sept 2021.pdf15 Nov 2021
Certificates of CA (Form 3)File: Form 3 Quality Annex 30th September 2021.pdf15 Nov 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Quality Annex Mar 2021.pdf18 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Quality Annex June 2021.pdf18 Aug 2021
Certificates of CA (Form 3)File: Form 3 Quality Annex 31st Mar 2021.pdf18 Aug 2021
Certificates of CA (Form 3)File: Form 3 Quality Annex 30th June 2021.pdf18 Aug 2021
Declaration about Commencement CertificateFile: Quality Annex.pdf24 Jul 2021
Disclosure of sold/ booked inventoryFile: Quality Annex 29.pdf24 Jul 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Quality Annex Dec 2020.pdf13 May 2021
Certificates of CA (Form 3)File: Form 3 Quality Annex 31st Dec 2020.pdf13 May 2021
Commencement Certificates / NA Order for plotted developmentFile: CC certificate.pdf20 Feb 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Quality Annex 30th Jun 2020_compressed.pdf17 Aug 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Quality Annex 31st Mar 2020_compressed.pdf17 Aug 2020
Certificates of CA (Form 3)File: Form 3 Quality Annex 31st Mar 2020.pdf17 Aug 2020
Certificates of CA (Form 3)File: Form 3 Quality Annex 30th June 2020.pdf17 Aug 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form - 2 Quality Annex.pdf11 Feb 2020
Certificates of CA (Form 3)File: Form - 3 Quality Annex.pdf11 Feb 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 Quality Annex.pdf22 Nov 2019
Certificates of CA (Form 3)File: Form-3 Quality Annex_compressed.pdf22 Nov 2019
Annual Audit Report of Statutory CA (Form 5)File: Form 5 Quality Annex.pdf30 Sep 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Quality Annex.pdf27 Aug 2019
Certificates of CA (Form 3)File: FORM 3 Quality Annex_compressed.pdf27 Aug 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Quality Annex.pdf31 May 2019
Certificates of CA (Form 3)File: Form 3 - Quality Annex.pdf31 May 2019
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf11 Oct 2018
Certificates of CA (Form 3)File: Form 3.pdf11 Oct 2018
Building plan approvalFile: approval plan 1.pdf9 Oct 2018
Building plan approvalFile: Approval plan 2.pdf9 Oct 2018
Layout approvalFile: approval plan 1.pdf9 Oct 2018
Layout approvalFile: Approval plan 2.pdf9 Oct 2018
PAN CardFile: pan card quality.pdf9 Oct 2018
Copy of the legal title reportFile: title certificate quality.pdf9 Oct 2018

How this compares with Thane

24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Quality Annex on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Shilphata7,600+ in Thane

2 kmQuality AnnexCompleted 36Lapsed / revoked 17Other 51Dot size: filed unitsN

Filed coordinates, straight-line distance. 104 registered projects within 2 km.

Builder: Quality Annex

Quality Annex has 1 registration on MahaRERA, including Quality Annex. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Quality Annex is delayed beyond 30 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Quality Annex?

The registered promoter entity is Quality Annex, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Quality Annex?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Quality Annex?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Quality Annex?

The professionals named in the filing: Architect: Joshi Deshaware Associates; Engineer: SK Consultants & Engineers; Chartered Accountant: Rutuja Narsingh & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Quality Annex?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Quality Annex. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Quality Annex to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.