Registered No litigation declared Residential / Group Housing project

PYRAMID HORIZON

By PYRAMID CONSTRUCTION

RG-MH-06592 · RERA P51700054008 · Last updated on MahaRERA portal: 3 Jun 2026

Source: official MahaRERA filing

Red flags

  • Rs 15.00 crore secured on the land, in favour of LIC HOUSING FINANCE LTD

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedno revision filed
0 of 11Construction stages donefurthest along: Excavation, 0%
84 of 149Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 59 documents Report an error

PYRAMID HORIZON is a Residential / Group Housing project by PYRAMID CONSTRUCTION in Thane, Maharashtra, registered with MahaRERA as P51700054008 on 19 Dec 2023. Possession is promised by 31 Dec 2027. 65 of the 149 units on this registration are recorded sold or booked, and 0 of 11 construction stages are filed complete.

At a glance

Project

  • NamePYRAMID HORIZON
  • TypeResidential / Group Housing
  • Location
    • KANAKIA ROAD
    • MIRA ROAD EAST
    • Mira-Bhayandar (M Corp.)
    • Thane
    • 401107
  • Pincode401107
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700054008
  • ReraGenie IDRG-MH-06592

Builder

  • NamePYRAMID CONSTRUCTION
  • Entity typePartnership
  • PartnersDHANPATRAJ VIJAYRAJ BHANSALI, SIDDHARTH DEEPAK BOSMIYA

Key dates

this monthRegisteredDec 2023PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on19 Dec 2023
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed59 files

Current status

44%65 of 149 units booked

Figures as on 3 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
C-WINGNA22191490149

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 3 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.

C-WING: 0% average across the applicable activities

ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 3 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed73

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots73
Closed/Covered1
Open Space72

Land and ownership1

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area1,021 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared present
Charge in favour ofLIC HOUSING FINANCE LTD
Secured amountRs 15.00 crore
CERSAI search filedYes
Declared on8 May 2026
LandownerVillageDistrict
HEMENDRA BOSMIYAMira-Bhayandar (M Corp.)Thane

Approvals and building plan

Sanctioning authorityMIRA BHAYANDAR MUNICIPLE CORPORATION
Permissible FSI8943.86
Proposed, not sanctioned7,716 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVILE PARLE EAST

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTEJS CONSULTANTS
Engineerprotech consultants
Chartered AccountantRS DOSHI & ASSOCIATES
PartnerRole in project
PYRAMID CONSTRUCTION-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 12 Sep 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 Oct 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Aug 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Aug 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed59

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: architect certificate_0001.pdf3 Jun 2026
Form 2File: 587-Form 2 Engineer certificate-MARCH 26.pdf3 Jun 2026
Form 3File: form-3 (2).pdf3 Jun 2026
Disclosure of Sold and Booked InventoryFile: sold unsold-mar 26.pdf3 Jun 2026
Form 1File: form-1 (2)_compressed.pdf7 Apr 2026
Form 2File: 587-Form 2 Engineer certificate-DEC 25.pdf7 Apr 2026
Form 3File: form-3.pdf7 Apr 2026
Disclosure of Sold and Booked InventoryFile: sold unsold_compressed.pdf7 Apr 2026
Form 1File: architect-31-03-2025.pdf10 Dec 2025
Form 2File: 587-Form 2 Engineer certificate-31-03-2025-1.pdf10 Dec 2025
Disclosure of Sold and Booked InventoryFile: sold unsold-31-03-2025.pdf10 Dec 2025
Form 3File: form-3-31-03-2025_compressed.pdf10 Dec 2025
Form 1File: architect-30-06-2025.pdf10 Dec 2025
Form 2File: Engineers Certificate.pdf10 Dec 2025
Form 3File: form-3-30-06-2025.pdf10 Dec 2025
Disclosure of Sold and Booked InventoryFile: sold unsold-31-06-2025.pdf10 Dec 2025
Form 2File: 587-Form 2 Engineer certificate-sept 25-1.pdf10 Dec 2025
Form 3File: form-3-30-09-2025.pdf10 Dec 2025
Disclosure of Sold and Booked InventoryFile: sold unsold-31-09-2025.pdf10 Dec 2025
Form 1File: architect-30-06-2025.pdf10 Dec 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architects Certificate 15TH APR 2024.pdf24 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architects Certificate 24TH SEP 2024.pdf24 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate 17TH APR 2024.pdf24 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate Pyramid Const 30TH JUNE 2024.pdf24 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer certificate 15TH APR 2024.pdf24 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-Engineer Certificate 16TH SEP 2024.pdf24 Dec 2024
Other - TechnicalFile: document 1.pdf21 Nov 2023
Other - TechnicalFile: GROUND FLOOR PLAN-271-286.pdf21 Nov 2023
Other - TechnicalFile: FIRST FLOOR PLAN-271-286.pdf21 Nov 2023
Other - TechnicalFile: LAYOUT PLAN-271-286_compressed.pdf21 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1_compressed.pdf25 Oct 2023
Layout approvalFile: layout-16-9-2023_compressed.pdf12 Oct 2023
Copy of Layout Approval (in case of layout)File: layout-16-9-2023_compressed.pdf12 Oct 2023
Declaration in FORM BFile: FORM-B_compressed.pdf12 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 587-Wing_C_-Form_2_Engineer_Certificate-06-09-23.pdf12 Oct 2023
CERSAI detailsFile: CERSAI DEACLARATION.pdf15 Sep 2023
Other - LegalFile: convenyance-1.pdf13 Sep 2023
Other - LegalFile: convenyance-2.pdf13 Sep 2023
Copy of the legal title reportFile: mira road Maha rera Title report_compressed.pdf12 Sep 2023
Details of encumbrances concerned to FinanceFile: LEGAL ENCUMBRANCE.pdf11 Sep 2023
Details of encumbrances concerned to LegalFile: LEGAL ENCUMBRANCE.pdf11 Sep 2023
Declaration about Commencement CertificateFile: CC DECLARTAION.pdf11 Sep 2023
CERSAI detailsFile: CERSAI_Search_Report_200279973073_For_Asset_Based_Search_11_09_2023_15_43_26_344.pdf11 Sep 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: DECLARATION DHANPAT.pdf11 Sep 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: DECLARATION SIDDHARTH.pdf11 Sep 2023
Proforma of Allotment letterFile: Allotment Letter_compressed.pdf11 Sep 2023
Proforma of Agreement for saleFile: sale agreement.pdf11 Sep 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: SEPEARTE BANK ACCOUNT.pdf11 Sep 2023
Deviation Report with respect to Allotment letterFile: NO DEVIATION.pdf11 Sep 2023
Deviation Report with respect to model copy of AgreementFile: NO DEVIATION.pdf11 Sep 2023
Building plan approvalFile: C-WING PLAN-271-286.PDF25 Aug 2023
PAN CardFile: PAN CARD.pdf25 Aug 2023
Building Plan Approval / NA Order for plotted developmentFile: C-WING PLAN-271-286.PDF25 Aug 2023
Commencement Certificates / NA Order for plotted developmentFile: REVISED CC-271-286-02-06-2022.pdf25 Aug 2023
Commencement Certificates / NA Order for plotted developmentFile: REVISED CC-271-286-06-01-2023.pdf25 Aug 2023
Other - LegalFile: 3 Other - Legal.pdf25 Aug 2023
Other - LegalFile: 4 Other - Legal.pdf25 Aug 2023
Other - LegalFile: 5 Other - Legal.pdf25 Aug 2023
Other - LegalFile: 6 Other - Legal.pdf25 Aug 2023

How this compares with Thane

44%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PYRAMID HORIZON on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MIRA ROAD EAST7,600+ in Thane

2 kmPYRAMID HORIZONCompleted 84Lapsed / revoked 67Other 83Dot size: filed unitsN

Filed coordinates, straight-line distance. 234 registered projects within 2 km.

Builder: PYRAMID CONSTRUCTION

PYRAMID CONSTRUCTION has 1 registration on MahaRERA, including PYRAMID HORIZON. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if PYRAMID HORIZON is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PYRAMID HORIZON?

The registered promoter entity is PYRAMID CONSTRUCTION, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PYRAMID HORIZON?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PYRAMID HORIZON?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PYRAMID HORIZON?

The professionals named in the filing: Architect: TEJS CONSULTANTS; Engineer: protech consultants; Chartered Accountant: RS DOSHI & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PYRAMID HORIZON?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PYRAMID HORIZON. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PYRAMID HORIZON to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.