Completed No litigation declared Residential / Group Housing project

Pushkar Orchid Greens Phase I

By Pushkar Homes Private Limited

RG-MH-01798 · RERA P50500006050 · Last updated on MahaRERA portal: 23 Jan 2020

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 14 earlier projects delivered on promise

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Jun 2018Possession promisedregistration recorded completed
41 of 77Construction stages doneacross 7 buildings; furthest along: Internal walls, 50%
1Complaints at MahaRERAon this registration
Jump to the 31 documents Report an error

Pushkar Orchid Greens Phase I is a Residential / Group Housing project by Pushkar Homes Private Limited in Nagpur, Maharashtra, registered with MahaRERA as P50500006050 on 14 Aug 2017. The registration is recorded completed; possession was promised by 30 Jun 2018. 1 complaint is on record with the regulator.

At a glance

Project

  • NamePushkar Orchid Greens Phase I
  • TypeResidential / Group Housing
  • Location
    • Borkhedi
    • Nagpur (Rural)
    • Nagpur
    • 441108
  • Pincode441108
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500006050
  • ReraGenie IDRG-MH-01798

Builder

  • NamePushkar Homes Private Limited
  • Entity typeCompany
  • Managing DirectorsVishal Rajeshkumar Agrawal, Kartik Balakrishnan Iyer, Neeraj Pravin Agrawal
  • Other registrations5 more →
  • Completed2 of 6
  • No longer live3 lapsed, de-registered or revoked
  • Declared earlier projects14 →

Key dates

this monthRegisteredAug 2017PromisedJun 2018Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on14 Aug 2017
  • Promised completion30 Jun 2018
  • Revised completionNone
  • Buildings7 building records
  • Documents filed31 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Orchid StudioNA30000
Morning DewNA60000
Morning MistNA60000
Silver CreastNA30000
Silver ShineNA30000
Prime RoseNA90000
Orchid VillaNA30000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building7

As on 23 Jan 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

41 of 77 construction stages are filed complete across 7 buildings. The stage furthest along is Internal walls, at 50%.

Orchid Studio64%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Morning Dew64%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.5%
Morning Mist64%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.5%
Silver Creast64%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Silver Shine64%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Prime Rose36%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Orchid Villa23%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 23 Jan 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes95%
Water SupplyYes95%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes95%
Storm Water DrainsYes95%
Landscaping & Tree PlantingYes75%
Street LightingYes80%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes50%

Parking filed92

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots92
Closed/Covered31
Open Space61
BuildingClosed/CoveredOpen SpaceTotal
Morning Dew7916
Morning Mist7916
Silver Creast01212
Silver Shine01212
Prime Rose171128
Orchid Villa088

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,825 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI4970.02
Proposed, not sanctioned4,970 sq m
Buildings approved7
Buildings sanctioned7

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchHIndustan Colony Wardha Road Nagpur

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectV K Associates
EngineerAAJ Engineer
PartnerRole in project
Pushkar Homes Private Limited-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC004000000010068Parag Ravindra LashkarePushkar Homes Pvt. Ltd.20/07/2018

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jul 2017
  4. Commencement CertificateNot on the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed31

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: orchid green p1.pdf23 Jan 2020
Architect’s Certificate on Completion of Project (Form 4)File: orchid green.pdf23 Jan 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: OG 1 Form 1-min-i.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: OG 1 form 2-i.pdf31 Jul 2017
Certificates of CA (Form 3)File: CA Certificate OG P-1-i.pdf31 Jul 2017
OtherFile: New Doc 40.pdf31 Jul 2017
Layout approvalFile: SITE PLAN.pdf30 Jul 2017
Building plan approvalFile: BLOCK C PRIME ROSE S 7 a.pdf30 Jul 2017
Building plan approvalFile: BLOCK C PRIME ROSE S 7 b.pdf30 Jul 2017
Building plan approvalFile: BLOCK C PRIME ROSE S 7c.pdf30 Jul 2017
Building plan approvalFile: TYPE -B- BLOCK-A-MORNING MIST MORNING DEW.pdf30 Jul 2017
Building plan approvalFile: TYPE-A-BLOCK-B SILVER CREAST SILVER SHINE.pdf30 Jul 2017
Building plan approvalFile: TYPE-B- BLOCK-B- SUN SHINE SUNRISE a.pdf30 Jul 2017
Building plan approvalFile: TYPE-B- BLOCK-B- SUN SHINE SUNRISE c.pdf30 Jul 2017
Building plan approvalFile: TYPE-B- BLOCK-B-SUN SHINE SUNRISE b.pdf30 Jul 2017
Building plan approvalFile: TYPE-C-BLOCK-A-ROW HOUSES ORCHID VILLA.pdf30 Jul 2017
PAN CardFile: PAN PHPL.pdf30 Jul 2017
Copy of the legal title reportFile: LEGAL_SEARCH_compressed.pdf30 Jul 2017
Details of encumbrancesFile: Encumbrance Certificate.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: SITE PLAN.pdf30 Jul 2017
Building Plan Approval (IOD)File: BLOCK C PRIME ROSE S 7 a.pdf30 Jul 2017
Building Plan Approval (IOD)File: BLOCK C PRIME ROSE S 7 b.pdf30 Jul 2017
Building Plan Approval (IOD)File: BLOCK C PRIME ROSE S 7c.pdf30 Jul 2017
Building Plan Approval (IOD)File: TYPE -B- BLOCK-A-MORNING MIST MORNING DEW.pdf30 Jul 2017
Building Plan Approval (IOD)File: TYPE-A-BLOCK-B SILVER CREAST SILVER SHINE.pdf30 Jul 2017
Building Plan Approval (IOD)File: TYPE-B- BLOCK-B- SUN SHINE SUNRISE a.pdf30 Jul 2017
Building Plan Approval (IOD)File: TYPE-B- BLOCK-B- SUN SHINE SUNRISE c.pdf30 Jul 2017
Building Plan Approval (IOD)File: TYPE-B- BLOCK-B-SUN SHINE SUNRISE b.pdf30 Jul 2017
Building Plan Approval (IOD)File: TYPE-C-BLOCK-A-ROW HOUSES ORCHID VILLA.pdf30 Jul 2017
Declaration in FORM BFile: AFFIDAVIT FORMB.pdf30 Jul 2017
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf30 Jul 2017

Promoter's earlier projects14

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

14 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Pushkar FlorencePlot No 19 Padole Layout Dev Nagar Nagpur5CompletedJun 2017Jun 2017
Pushkar Gardens Plot No 15Plot No 15 Khasra No 276 Wanadongari Tahsil Hingna Nagpur8CompletedApr 2017Apr 2017
Pushkar Garden Plot No 5Plot No 5 Khasra No 276 Wanadongari Tahsil Hingna Nagpur1CompletedApr 2017Apr 2017
Pushkar MaplePlot No 2 Kh No 29 Mouza Gadga Near Zenda Chowk Khare Town Dharampeth Nagpur6CompletedSep 2016Sep 2016
Pushkar Gardens Plot No 18Plot No 18 Khasra No 276 Wanadongari Tahsil Hingna Nagpur1CompletedAug 2016Aug 2016
Pushkar Gardens Plot No 8Plot No 8 Khasra No 276 Wanadongari Tahsil Hingna Nagpur1CompletedApr 2016Apr 2016
Pushkar Gardens Plot No 20Plot No 20 Khasra No 276 Wanadongari Tahsil Hingna Nagpur1CompletedMar 2016Mar 2016
Pushkar Garden Plot No 6 and 7Plot No 6 and 7 Khasra No 276 Wanadongari Tahsil Hingna Nagpur1CompletedOct 2015Oct 2015
Pushkar Garden Plot No 9Plot No 9 Khasra No 276 Wanadongari Tahsil Hingna Nagpur1CompletedAug 2015Aug 2015
Pushkar Spring Garden Plot No 3Plot No.3 Khasra No 276 Wanadongari Tahsil Hingna Nagpur1CompletedMar 2015Mar 2015
Pushkar Gardens Plot No 10Plot No 10 Khasra No 276 Wanadongari Tahsil Hingna Nagpur1CompletedMar 2015Mar 2015
Pushkar Garden Plot 4Plot No 4 Khasra No 276 Wanadongari Tahsil Hingna Nagpur1CompletedMar 2015Mar 2015
Pushkar BlossomsPlot No 33-A Ram Mandir Road Swawalambi Nagar Nagpur4CompletedSep 2013Sep 2013
Pushkar ResidencyPlot No 33 Surendra Nagar Nagpur8CompletedSep 2012Sep 2012

How this compares with Nagpur

13%of Nagpur projects moved their completion datethis one has not
22%of Nagpur registrations have lapsed or been cancelledthis one is completed

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Pushkar Orchid Greens Phase I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Borkhedi2,800+ in Nagpur

2 kmPushkar Orchid Greens PhCompleted 2Lapsed / revoked 1Dot size: filed unitsN

Filed coordinates, straight-line distance. 3 registered projects within 2 km.

Builder: Pushkar Homes Private Limited

Pushkar Homes Private Limited has 6 registrations on MahaRERA, including Pushkar Orchid Greens Phase I and Pushkar Orchid Greens Phase II. Its filings disclose 14 earlier MahaRERA projects: declares 14 of 14 past projects completed on time. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if Pushkar Orchid Greens Phase I is delayed beyond 30 Jun 2018?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Pushkar Orchid Greens Phase I?

The registered promoter entity is Pushkar Homes Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Pushkar Orchid Greens Phase I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Pushkar Orchid Greens Phase I?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Pushkar Orchid Greens Phase I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Pushkar Orchid Greens Phase I?

The professionals named in the filing: Architect: V K Associates; Engineer: AAJ Engineer. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Pushkar Orchid Greens Phase I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Pushkar Orchid Greens Phase I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Pushkar Orchid Greens Phase I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.