Home / Developers / Pushkar Homes Private Limited
Pushkar Homes Private Limited: RERA track record
Company ยท attribution by exact filing name, entity resolution in progress
Pushkar Homes Private Limited has 6 registrations on MahaRERA, including Pushkar Orchid Greens Phase I and Pushkar Orchid Greens Phase II. Its filings disclose 14 earlier MahaRERA projects: declares 14 of 14 past projects completed on time.
Projects by this developer
Showing all 6 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| Pushkar GopalaP50500016636 | Zinga Bai Takli, Nagpur, 440030 | - | - | 5 Jun 2018 | Registration lapsed |
| Pushkar Govind and Narayan ApartmentP50500005009 | Zinga Bai Takli, Nagpur, 440030 | - | - | 9 Aug 2017 | Completed |
| PUSHKAR ONEP50500053884 | RAMDASPETH, Nagpur, 440010 | - | - | 8 Dec 2023 | Registered |
| Pushkar Orchid Greens Phase IP50500006050 | Borkhedi, Nagpur, 441108 | - | - | 14 Aug 2017 | Completed |
| Pushkar Orchid Greens Phase IIP50500005066 | Borkhedi, Nagpur, 441108 | - | - | 9 Aug 2017 | Registration lapsed |
| PUSHKAR SIGNATUREP50500009067 | Nagpur (M Corp.), Nagpur, 440015 | - | - | 19 Aug 2017 | Registration lapsed |
What this promoter declares as its own experience
Pushkar Homes Private Limited declares experience on 14 earlier projects. None of them carries a registration number we could match on MahaRERA, which is usual for work done before the register existed.
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Pushkar Residency | 30 Sep 2012 | 30 Sep 2012 | On time |
| Pushkar Blossoms | 30 Sep 2013 | 30 Sep 2013 | On time |
| Pushkar Spring Garden Plot No 3 | 31 Mar 2015 | 31 Mar 2015 | On time |
| Pushkar Garden Plot 4 | 31 Mar 2015 | 31 Mar 2015 | On time |
| Pushkar Gardens Plot No 10 | 31 Mar 2015 | 31 Mar 2015 | On time |
| Pushkar Garden Plot No 9 | 31 Aug 2015 | 31 Aug 2015 | On time |
| Pushkar Garden Plot No 6 and 7 | 30 Oct 2015 | 30 Oct 2015 | On time |
| Pushkar Gardens Plot No 20 | 31 Mar 2016 | 31 Mar 2016 | On time |
| Pushkar Gardens Plot No 8 | 30 Apr 2016 | 30 Apr 2016 | On time |
| Pushkar Gardens Plot No 18 | 31 Aug 2016 | 31 Aug 2016 | On time |
| Pushkar Maple | 30 Sep 2016 | 30 Sep 2016 | On time |
| Pushkar Garden Plot No 5 | 30 Apr 2017 | 30 Apr 2017 | On time |
Frequently asked questions
How do I verify Pushkar Homes Private Limited as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with Pushkar Homes Private Limited?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.
Report an errorShare feedbackData from official MahaRERA filings. How we handle corrections is on the about page.