ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / PURVANCHAL CHS LTD

Registration lapsed No litigation declared Others project

PURVANCHAL CHS LTD

By KAMALNATH UNIVERSAL PRIVATE LIMITED

RG-MH-50133 · RERA P51800005722 · Last updated on MahaRERA portal: 16 Apr 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 82 months past the filed date
  • 3 complaints at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2019Possession promised82 months past this date
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
3Complaints at MahaRERAon this registration
Jump to the 38 documents Report an error

PURVANCHAL CHS LTD is a Others project by KAMALNATH UNIVERSAL PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800005722 on 11 Aug 2017. Possession was promised by 31 Dec 2019 and is now 82 months past that date. The completion date has moved by 12 months from the original filing. 3 complaints are on record with the regulator.

At a glance

Project

  • NamePURVANCHAL CHS LTD
  • TypeOthers
  • Location
    • Kurla
    • Mumbai Suburban
    • 400081
  • Pincode400081
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800005722
  • ReraGenie IDRG-MH-50133

Builder

  • NameKAMALNATH UNIVERSAL PRIVATE LIMITED
  • Entity typeCompany
  • Managing DirectorsJAYWANT KASHINATH PATIL, BHALCHANDRA KASHINATH PATIL

Key dates

82 months past promisethis monthRegisteredAug 2017First promiseDec 2018Revised toDec 2019

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on11 Aug 2017
  • Promised completion31 Dec 2019
  • Revised completionRevised to 31 Dec 2019 (originally 31 Dec 2018)
  • Buildings1 building record
  • Documents filed38 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PURVANCHAL CHSLTDNA130000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 16 Apr 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

PURVANCHAL CHSLTD: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 16 Apr 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area517 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
PURVANCHAL CHS LTDKurlaMumbai Suburban

Approvals and building plan

Permissible FSI1034.94
Proposed, not sanctioned1,035 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPLOT NO 7 SECTOR 5-SANPADA NAVI MUMBAI 400705

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSanjay K Ayare
ArchitectRamesh Dalvi & Co
EngineerRajan Tipnis
PartnerRole in project
KAMALNATH UNIVERSAL PRIVATE LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800000956Dec 2018 → Dec 2019

Reason as filed by the promoterThe Secretary, Purvanchal CHS, Mulund, has addressed letter to the MCMG authorities dated 29/06/2012. The Municipal Commissioner, Mr.Ajay Mehta had submitted his report before the MSCDRC, Mumbai in view of the order passed by MSCDRC dated 14/06/2018, in which he had concluded that unless the Society grants the permission to the developer and the developer through architect submits the amended plan, corporation cannot grant occupation certificate. On 02/04/2018 the MSCDRC had directed the Municipal Commissioner shall hear the parties concerned including the purchasers. The Municipal Commissione

Litigation declared8

CaseCourtStatus
CC/217/SS/2015/2015Additional Magistrates Court MulundOn going
CC/218/SS/2015/2015Additional Magistrates Court MulundOn going
CC/219/SS/2015/2015Additional Magistrates Court MulundOn going
CC/220/SS/2015/2015Additional Magistrates Court MulundOn going
167/2013/2013State Consumer Disputes Redressal CommissionOn going
168/2013/2013State Consumer Disputes Redressal CommissionOn going
169/2013/2013State Consumer Disputes Redressal CommissionOn going
0/2017MRTP CourtOn going

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC006000000001149Shruti Nagraj JoshiKamalnath Universal Pvt. Ltd.01/11/2017
CC006000000001311Varsha Madhusudan dharapKAMALNATH UNIVARSAL PRIVATE LIMITED15/10/2017
CC006000000001558ARUN VASUDEO NATUKAMALNATH UNIVARSAL PVT LTD29/10/2017

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Dec 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed38

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: KUPL RERA CERTIFICATE 23-24.pdf16 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Updated Form 5.pdf12 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf5 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf5 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A.pdf5 Oct 2023
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD BOOKED INVENTORY.pdf5 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf5 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.pdf5 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf8 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 upto 23-01-2023 Engineer_new.pdf8 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A upto dec-22.pdf8 Feb 2023
Certificates of CA (Form 5)File: Form 5.pdf8 Feb 2023
Disclosure of sold/ booked inventoryFile: Disclosure.pdf5 Mar 2022
Certificates of CA (Form 3)File: Form 3.pdf25 Feb 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf24 Feb 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 upto 31st dec 21.pdf24 Feb 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A upto dec-21.pdf24 Feb 2022
Certificates of CA (Form 3)File: Form 3.pdf22 Sep 2021
Declaration about Commencement CertificateFile: KUPL-DECLARATION ABOUT COMMENCEMENT CERTIFICATE.pdf13 Sep 2021
Disclosure of sold/ booked inventoryFile: KUPL-DISCLOSURE OF SOLD, BOOKED INVENTORY.pdf13 Sep 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: Declaration.pdf26 Aug 2021
Certificates of CA (Form 3)File: FORM 3.pdf7 Jan 2019
Commencement Certificates / NA Order for plotted developmentFile: CC WITH PLAN-ilovepdf-compressed.pdf28 Dec 2018
Certificates of CA (Form 5)File: Form 5.pdf29 Nov 2018
Layout approvalFile: PLAN LAYOUT ONE-PAGE 1.pdf31 Jul 2017
Layout approvalFile: PLAN LAYOUT TWO-PAGE 2.pdf31 Jul 2017
Building plan approvalFile: IOD-COMPRESSED.pdf31 Jul 2017
PAN CardFile: PAN CARD OF THE COMPANY.pdf31 Jul 2017
Copy of the legal title reportFile: TITLE REPORT.pdf31 Jul 2017
Details of encumbrancesFile: DETAILS OF ENCUMBRANCES.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: PLAN LAYOUT ONE-PAGE 1.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: PLAN LAYOUT TWO-PAGE 2.pdf31 Jul 2017
Building Plan Approval (IOD)File: IOD-COMPRESSED.pdf31 Jul 2017
Declaration in FORM BFile: FORMB_DECLARATION.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2_COMPRESSED.pdf31 Jul 2017
Certificates of CA (Form 3)File: FORM 3-COMPRESSED.pdf31 Jul 2017
Proforma of Allotment letterFile: DECLARATION.pdf31 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 12 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PURVANCHAL CHS LTD on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kurla6,700+ in Mumbai Suburban

2 kmPURVANCHAL CHS LTDCompleted 85Lapsed / revoked 75Other 109Dot size: filed unitsN

Filed coordinates, straight-line distance. 269 registered projects within 2 km.

Builder: KAMALNATH UNIVERSAL PRIVATE LIMITED

KAMALNATH UNIVERSAL PRIVATE LIMITED has 1 registration on MahaRERA, including PURVANCHAL CHS LTD. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that PURVANCHAL CHS LTD shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if PURVANCHAL CHS LTD is delayed beyond 31 Dec 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PURVANCHAL CHS LTD?

The registered promoter entity is KAMALNATH UNIVERSAL PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PURVANCHAL CHS LTD?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against PURVANCHAL CHS LTD?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for PURVANCHAL CHS LTD?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PURVANCHAL CHS LTD?

The professionals named in the filing: Architect: Sanjay K Ayare; Architect: Ramesh Dalvi & Co; Engineer: Rajan Tipnis. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PURVANCHAL CHS LTD?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PURVANCHAL CHS LTD. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PURVANCHAL CHS LTD to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.