Home / Browse projects / Mumbai Suburban, Maharashtra / Purnima
Purnima
RG-MH-05355 · RERA P51800051454 · Last updated on MahaRERA portal: 17 Mar 2026
Source: official MahaRERA filing
Red flags
- Completion date moved by 24 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Purnima is a Residential / Group Housing project by Ami Virag Shivpuri in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800051454 on 23 Jun 2023. The registration is recorded completed; possession was promised by 31 Dec 2026. The completion date has moved by 24 months from the original filing. 3 of the 9 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete.
At a glance
Project
- NamePurnima
- TypeResidential / Group Housing
- Location
- Vithal Bhai Road
- TPS VI
- Vileparle
- Andheri
- Mumbai Suburban
- 400056
- Pincode400056
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800051454
- ReraGenie IDRG-MH-05355
Builder
- NameAmi Virag Shivpuri
- Entity typeIndividual
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on23 Jun 2023
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2024)
- Buildings1 building record
- Documents filed71 files
Current status
Figures as on 17 Mar 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Wing-B | NA | 10 | 9 | 9 | 0 | 9 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 17 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.
Wing-B: 82% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 17 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed23
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership3
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Purnima Jayant Bhimani | Vileparle | Mumbai Suburban |
| Dipika Pratap Shroff | Vileparle | Mumbai Suburban |
| Ami Virag Shivpuri | Vileparle | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Wing-B | NA | Rs 5.81 cr | Rs 5.81 cr |
| - | NA | Rs 30.60 lakh | Rs 30.60 lakh |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Bhupendra Patrawala |
| Engineer | SK Consultants & Engineers |
| Chartered Accountant | Rutuja Narsingh & Associates |
| Chartered Accountant | NB Sayed & Associates |
| Partner | Role in project |
|---|---|
| Ami Virag Shivpuri | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.
Reason as filed by the promoterWe apologize for the delay in the completion of the project and the submission of this request. The extension is being sought solely due to procedural delays in obtaining the Occupation Certificate (OC). Despite the project being substantially completed, the pending procedural approvals have impacted the formal completion timeline. Given these circumstances, we kindly request an extension until 31-12-2026 to complete the project and fulfil all regulatory requirements.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 12 Jun 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 5 Mar 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 5 Mar 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 5 Mar 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed71
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 - Purnima as on Dec 2025.pdf | 17 Mar 2026 |
| Withdrawal Update Form 2File: Form 2 - Purnima as on Dec 2025.pdf | 17 Mar 2026 |
| Withdrawal Update Form 3File: Form 3 - Purnima as on Dec 2025.pdf | 17 Mar 2026 |
| Withdrawal Update Form 1File: Form 1 - Purnima as on June 2025.pdf | 21 Feb 2026 |
| Withdrawal Update Form 1File: Form 1 - Purnima as on Sept 2025.pdf | 21 Feb 2026 |
| Withdrawal Update Form 1File: Form 1 - Purnima as on Dec 2025.pdf | 21 Feb 2026 |
| Withdrawal Update Form 2File: Form 2 - Purnima as on June 2025.pdf | 21 Feb 2026 |
| Withdrawal Update Form 2File: Form 2 - Purnima as on Sept 2025.pdf | 21 Feb 2026 |
| Withdrawal Update Form 2File: Form 2 - Purnima as on Dec 2025.pdf | 21 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 - Purnima as on June 2025.pdf | 21 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 - Purnima as on Sept 2025.pdf | 21 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 - Purnima as on Dec 2025.pdf | 21 Feb 2026 |
| Layout approvalFile: Plan.pdf | 5 Mar 2025 |
| Building plan approvalFile: Plan.pdf | 5 Mar 2025 |
| Copy of Layout Approval (in case of layout)File: Plan.pdf | 5 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Purnima as on Sep 2024.pdf | 5 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Purnima as on Dec 2024.pdf | 5 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Purnima as on Sep 2024.pdf | 5 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Purnima as on Dec 2024.pdf | 5 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Purnima as on Sep 2024.pdf | 5 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Purnima as on Dec 2024.pdf | 5 Mar 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 5 Mar 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan.pdf | 5 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Purnima as on June 2024.pdf | 11 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Purnima as on June 2024.pdf | 11 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Purnima as on June 2024.pdf | 31 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Purnima as on March 2024.pdf | 22 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Purnima as on March -2024.pdf | 22 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Purnima as on March 2024.pdf | 16 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Purnima as on June 2023.pdf | 13 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Purnima as on Sep 2023.pdf | 13 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Purnima as on Dec 2023.pdf | 13 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Purnima as on June 2023.pdf | 13 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Purnima as on September 2023.pdf | 13 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Purnima as on December 2023.pdf | 13 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Purnima as on June-2023.pdf | 13 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Purnima as on September-2023.pdf | 13 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Purnima as on December 2023.pdf | 13 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate as on 30-06-2023.pdf | 11 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate as on 30-09-2023.pdf | 11 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate as on 31-12-2023.pdf | 11 Mar 2024 |
| Declaration in FORM BFile: Form B.pdf | 1 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 AMI.pdf | 1 Dec 2023 |
| Declaration in FORM BFile: Form B.pdf | 28 Nov 2023 |
| Declaration in FORM BFile: Form B Purnima .pdf | 28 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: Circular 29.pdf | 28 Nov 2023 |
| Copy of the legal title reportFile: Highlighted Revised Legal Title Report - Purnima_11zon.pdf | 12 Jun 2023 |
| Details of encumbrances concerned to FinanceFile: Encumbrance Letter - Finance.pdf | 12 Jun 2023 |
| Details of encumbrances concerned to FinanceFile: Encumbrance Letter - Legal.pdf | 12 Jun 2023 |
| Details of encumbrances concerned to LegalFile: Encumbrance Letter - Finance.pdf | 12 Jun 2023 |
| Details of encumbrances concerned to LegalFile: Encumbrance Letter - Legal.pdf | 12 Jun 2023 |
| CERSAI detailsFile: Declation of Cersai.pdf | 12 Jun 2023 |
| Other - LegalFile: ilovepdf_merged (3).pdf | 12 Jun 2023 |
| Other - FinanceFile: ilovepdf_merged (3).pdf | 12 Jun 2023 |
| Layout approvalFile: Layout Page 1.pdf | 2 May 2023 |
| Building plan approvalFile: Layout Page 1.pdf | 2 May 2023 |
| Building plan approvalFile: Layout Page 2.pdf | 2 May 2023 |
| Copy of Layout Approval (in case of layout)File: Layout Page 1.pdf | 2 May 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Layout Page 1.pdf | 2 May 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Layout Page 2.pdf | 2 May 2023 |
| Declaration in FORM BFile: Form B Ami.pdf | 28 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form - 3 compressed.pdf | 27 Apr 2023 |
| Declaration about Commencement CertificateFile: Format D.pdf | 26 Apr 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A - Ami.pdf | 26 Apr 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf | 26 Apr 2023 |
| Deviation Report with respect to Allotment letterFile: Deviation - Allotment.pdf | 26 Apr 2023 |
| Deviation Report with respect to model copy of AgreementFile: Deviation - AFS.pdf | 26 Apr 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 4 Apr 2023 |
| Proforma of Agreement for saleFile: AFS_Purnima_Ami Virag Shivpuri_03042023.pdf | 4 Apr 2023 |
| Proforma of Allotment letterFile: Allotment Letter_Deviation_Purnima_Ami Virag Shivpuri_03042023.pdf | 4 Apr 2023 |
| PAN CardFile: Ami Virag Shivpuri PAN.pdf | 3 Apr 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 71 filed documents as one ZIP, foldered, with a manifest
Keep Purnima on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near TPS VI6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 355 registered projects within 2 km.
CHANDAK VANSHAM
CHANDAK REALTORS PRIVATE LIMITED
AJOD ONE
AJOD REALTY LLP
GAUTAM DHAN
NEW INDIA CONSTRUCTIONS
AJMERA SHRINGAAR
H J CORPORATION
Imperial Landmark
Neminath and Disha Realtors
PINAL EVANA
Pinal Realty LLP
See every Mumbai Suburban project, with the district possession charts
Builder: Ami Virag Shivpuri
Ami Virag Shivpuri has 1 registration on MahaRERA, including Purnima. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if Purnima is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Purnima?
The registered promoter entity is Ami Virag Shivpuri, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Purnima?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Purnima?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Purnima?
The professionals named in the filing: Architect: Bhupendra Patrawala; Engineer: SK Consultants & Engineers; Chartered Accountant: Rutuja Narsingh & Associates; Chartered Accountant: NB Sayed & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Purnima?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback