Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 6 earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 4 other registrations.

See what the report covers Free either way: or have every new Solapur registration emailed to you, free during the pilot beta.
Jun 2026Possession promisedregistration recorded completed
30 of 33Construction stages doneacross 3 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 40 documents Report an error

Pujari C.T. is a Residential / Group Housing project by TIRUPATI CONSTRUCTION PROMOTERS & DEVELOPERS in Solapur, Maharashtra, registered with MahaRERA as P52600026823 on 28 Oct 2020. The registration is recorded completed; possession was promised by 30 Jun 2026.

At a glance

Project

  • NamePujari C.T.
  • TypeResidential / Group Housing
  • Location
    • Pandharpur Pune Road
    • Near Pandharpur College Chowk
    • Isbavi
    • Pandharpur
    • Solapur
    • 413304
  • Pincode413304
  • RERA no.P52600026823
  • ReraGenie IDRG-MH-16457

Builder

  • NameTIRUPATI CONSTRUCTION PROMOTERS & DEVELOPERS
  • Entity typePartnership
  • PartnerSHASHANK SHARAD NALBILWAR
  • Other registrations4 more →
  • Completed5 of 5
  • Declared earlier projects6 →

Key dates

this monthRegisteredOct 2020PromisedJun 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on28 Oct 2020
  • Promised completion30 Jun 2026
  • Revised completionNone
  • Buildings3 building records
  • Documents filed40 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building - D SiddhivinayakNA60000
Building - B AtharvNA60000
Building - E VedantaNA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 14 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

30 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Podiums (if any), at 0%.

Building - D Siddhivinayak91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building - B Atharv91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building - E Vedanta91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 14 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed44

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots44
Closed/Covered30
Open Space14
BuildingClosed/CoveredOpen SpaceTotal
Building - D Siddhivinayak18725
Building - B Atharv12719

Land and ownership3

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,047 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
LandownerVillageDistrict
Vinayak Trimbak PujariIsbaviSolapur
Bhalchandra Trimbak PujariIsbaviSolapur
Narsinh TrimbakPujariIsbaviSolapur

Approvals and building plan

Permissible FSI7712.2
Proposed, not sanctioned6,844 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNear ST Bus Stand Pandharpur

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKhamitkar & Associates
EngineerSanjay Jathade
Chartered AccountantAnkush P Kaulwar & Co
PartnerRole in project
TIRUPATI CONSTRUCTION PROMOTERS & DEVELOPERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Sep 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Aug 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Aug 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Feb 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 5 Feb 2025

Documents filed40

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf14 Feb 2025
Commencement Certificates / NA Order for plotted developmentFile: Letest CC .pdf14 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 2020-21.pdf14 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 2021-22.pdf14 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 2021-22 (1).pdf14 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 2022-23 (1).pdf14 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 2022-23.pdf14 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 2023-24 (1).pdf14 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 2023-24.pdf14 Feb 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Send Screen Shot PDF.pdf5 Feb 2025
Architect’s Certificate on Completion of Project (Form 4)File: Pujari ct Form 4.pdf4 Feb 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: PUJARI_C_T_FULL_OC.pdf19 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 2017-2018.pdf21 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 2018-2019.pdf21 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 2019-2020.pdf21 Apr 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: PUJARI_C_T_PART_OC.pdf6 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A.pdf22 Aug 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Annual Report 20-21.pdf22 Aug 2022
Declaration about Commencement CertificateFile: Format-D.pdf21 Aug 2022
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Inventory.pdf21 Aug 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate Extension.pdf24 Oct 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Pujari CT Form 3.pdf24 Oct 2020
Details of encumbrancesFile: Encumbrance Certificate.pdf2 Oct 2020
Declaration in FORM BFile: Form B.pdf1 Oct 2020
Proforma of Allotment letterFile: Agreement to Sale Pujari City RERA.pdf1 Oct 2020
Copy of the legal title reportFile: Search Report.pdf30 Sep 2020
Copy of the legal title reportFile: Search Report1.pdf30 Sep 2020
Proforma of Allotment letterFile: Allotment Letter Pujari CT.pdf15 Aug 2020
Building plan approvalFile: NA order Pujari CT.pdf14 Aug 2020
Building plan approvalFile: Saction Drawing 1.pdf14 Aug 2020
Building plan approvalFile: Sanction Drawing 2.pdf14 Aug 2020
Building plan approvalFile: Sanction Drawing 3.pdf14 Aug 2020
Layout approvalFile: Approval plan.pdf14 Aug 2020
Copy of Layout Approval (in case of layout)File: Approval plan.pdf14 Aug 2020
Building Plan Approval / NA Order for plotted developmentFile: NA order Pujari CT.pdf14 Aug 2020
Building Plan Approval / NA Order for plotted developmentFile: Saction Drawing 1.pdf14 Aug 2020
Building Plan Approval / NA Order for plotted developmentFile: Sanction Drawing 2.pdf14 Aug 2020
Building Plan Approval / NA Order for plotted developmentFile: Sanction Drawing 3.pdf14 Aug 2020
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate Pujari CT.pdf14 Aug 2020
PAN CardFile: PAN.pdf3 Aug 2020

Promoter's earlier projects6

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

6 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Shindeshahi Phase IISamata Nagar Isbavi Pandharpur48CompletedMay 2020Jan 2020
Shindeshahi Building A Building BSamata Nagar Isbavi Pandharpur40CompletedMar 2017Jan 2017
Tirupati Lad PlazaCollege Chowk pandharpur23CompletedMay 2016Apr 2016
PUJARI C T EkdantPUJARI CT NEAR COLLEGE CHOWK PANDHARPUR27CompletedFeb 2016Jan 2016
Sarthak ResidencyMalpe Chowk Isbavi Pandharpur18CompletedMay 2015Apr 2015
Tirupati Vilas ResidencySangola Road Pandharpur18CompletedDec 2014Dec 2014

How this compares with Solapur

15%of Solapur projects moved their completion datethis one has not
39%of Solapur registrations have lapsed or been cancelledthis one is completed

Computed across the 550+ Solapur projects on ReraGenie, from their own filings.

Keep Pujari C.T. on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Near Pandharpur College Chowk550+ in Solapur

Builder: TIRUPATI CONSTRUCTION PROMOTERS & DEVELOPERS

TIRUPATI CONSTRUCTION PROMOTERS & DEVELOPERS has 5 registrations on MahaRERA, including Shindeshahi PhaseII and Shri Audumbar Plaza. Its filings disclose 6 earlier MahaRERA projects: declares 6 of 6 past projects completed on time. Read the full track record. See more projects on the Solapur district page.

Frequently asked questions

What are my rights if Pujari C.T. is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Pujari C.T.?

The registered promoter entity is TIRUPATI CONSTRUCTION PROMOTERS & DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Pujari C.T.?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Pujari C.T.?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Pujari C.T.?

The professionals named in the filing: Architect: Khamitkar & Associates; Engineer: Sanjay Jathade; Chartered Accountant: Ankush P Kaulwar & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Pujari C.T.?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Pujari C.T.. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Pujari C.T. to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.