ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / PRUTHVI PURUSHOTTAM

Completed No litigation declared Others project

PRUTHVI PURUSHOTTAM

By PRUTHVI ENCLAVE LLP

RG-MH-04576 · RERA P51800022206 · Last updated on MahaRERA portal: 4 Oct 2022

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 3 other registrations.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2023Possession promisedregistration recorded completed
4 of 11Construction stages donefurthest along: Staircases, 40%
0Complaints at MahaRERAon this registration
Jump to the 52 documents Report an error

PRUTHVI PURUSHOTTAM is a Others project by PRUTHVI ENCLAVE LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800022206 on 5 Sep 2019. The registration is recorded completed; possession was promised by 30 Jun 2023.

At a glance

Project

  • NamePRUTHVI PURUSHOTTAM
  • TypeOthers
  • Location
    • PARK ROAD
    • VILE PARLE EAST
    • Andheri
    • Mumbai Suburban
    • 400057
  • Pincode400057
  • RERA no.P51800022206
  • ReraGenie IDRG-MH-04576

Builder

  • NamePRUTHVI ENCLAVE LLP
  • Entity typeCompany
  • Other registrations3 more →
  • Completed2 of 4
  • Declared earlier projects2 →

Key dates

this monthRegisteredSep 2019PromisedJun 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on5 Sep 2019
  • Promised completion30 Jun 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed52 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PRUTHVI PURUSHOTTAMNA110000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 4 Oct 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 40%.

PRUTHVI PURUSHOTTAM: 43% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 4 Oct 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed4

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots4
Open Space4

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area687 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
PURUSHOTTAM CHS LTDAndheriMumbai Suburban

Approvals and building plan

Permissible FSI1374.6
Proposed, not sanctioned1,372 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchHANUMAN ROAD VILE PARLE EAST MUMBAI 400057

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectANJ ENGINEERING CONSULTANTS LLP
EngineerSUHAS SAHADEV PALAV
Chartered AccountantASHVIN THUMAR
Chartered AccountantASHOK M SOLANKI & ASSOCIATE LLP
PartnerRole in project
PRUTHVI ENCLAVE LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 13 Aug 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Feb 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Sep 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Oct 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 22 Apr 2022

Documents filed52

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Pruthvi Enclave LLP ( Pruthvi Purushottam ) .PDF4 Oct 2022
Status of ConveyanceFile: Final Conveyance Deed Purushottam.pdf14 Jun 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OCC LETTER APPROVED.pdf22 Apr 2022
Architect’s Certificate on Completion of Project (Form 4)File: Signed Form 4Architect Certificate Purushottam.pdf22 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A PELLP Purushottam.pdf8 Apr 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Both Signed FORM 3 RERA Purushottam Q4 '22 Signed.pdf8 Apr 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Pruthvi Enclave FORM 3 CA Certificate Signed.pdf22 Jan 2022
Commencement Certificates / NA Order for plotted developmentFile: FULL CC (1_06_2021) Purushottam.pdf29 Oct 2021
Declaration about Commencement CertificateFile: Enclave LLP RERA Declaration about CC Final.pdf29 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Enclave LLP Form 2A Purushottam.pdf9 Oct 2021
Disclosure of sold/ booked inventoryFile: Enclave LLP Disclosure Sold Unsold Inventory.pdf9 Oct 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate Enclave LLP Purushottam.pdf9 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Pruthvi Enclave LLp -Purushottam form 5.PDF29 Sep 2021
Building plan approvalFile: AMENDED PLAN.PDF24 Sep 2021
Building Plan Approval / NA Order for plotted developmentFile: AMENDED PLAN.PDF24 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A QUALITY ASSURANCE CERTIFICATE PURUSHOTTAM.pdf23 Aug 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Enclave LLP Q4 FY20-21.pdf14 Aug 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Enclave LLP Q1 FY21-22.pdf14 Aug 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA-Purushottam -(Sept20) Signed.pdf18 Feb 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA-Purushottam-Final signed.pdf21 Dec 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5-Pruthvi Enclave.PDF4 Nov 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA-Purushottam-Final Signed.pdf31 Oct 2020
Building plan approvalFile: IOD-4 TO 8.pdf26 Feb 2020
Building plan approvalFile: IOD-4 TO 8.pdf26 Feb 2020
Building Plan Approval / NA Order for plotted developmentFile: IOD-4 TO 8.pdf26 Feb 2020
Building Plan Approval / NA Order for plotted developmentFile: IOD-4 TO 8.pdf26 Feb 2020
Building plan approvalFile: AMENDED IOD.pdf25 Feb 2020
Building plan approvalFile: AMENDED IOD-1.pdf25 Feb 2020
Layout approvalFile: IOD LETTER.pdf25 Feb 2020
Copy of Layout Approval (in case of layout)File: IOD LETTER.pdf25 Feb 2020
Building Plan Approval / NA Order for plotted developmentFile: AMENDED IOD.pdf25 Feb 2020
Building Plan Approval / NA Order for plotted developmentFile: AMENDED IOD-1.pdf25 Feb 2020
Building plan approvalFile: IOD LETTER - purushottam.pdf15 Feb 2020
Building Plan Approval / NA Order for plotted developmentFile: IOD LETTER - purushottam.pdf15 Feb 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineers Certificate of pruthvi Enclave LLP.pdf31 Jan 2020
Commencement Certificates / NA Order for plotted developmentFile: 2227248 FirstCC signed.pdf14 Aug 2019
Declaration in FORM BFile: PURUSHOTTAM RERA FROMB.pdf14 Aug 2019
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf14 Aug 2019
Layout approvalFile: IOD dtd12 03 2019.pdf13 Aug 2019
Building plan approvalFile: IOD Drawing1.pdf13 Aug 2019
Building plan approvalFile: IOD Drawing 2.pdf13 Aug 2019
Building plan approvalFile: IOD Drawing3.pdf13 Aug 2019
Building plan approvalFile: IOD Drawing4.pdf13 Aug 2019
PAN CardFile: ENCLAVE LLP NEW PANCARD BLACKWHITE.pdf13 Aug 2019
Copy of the legal title reportFile: PURUSHOTTAM TITLE CERTIFICATE.pdf13 Aug 2019
Details of encumbrancesFile: PURUSHOTTAM TITLE CERTIFICATE.pdf13 Aug 2019
Copy of Layout Approval (in case of layout)File: IOD dtd12 03 2019.pdf13 Aug 2019
Building Plan Approval / NA Order for plotted developmentFile: IOD Drawing1.pdf13 Aug 2019
Building Plan Approval / NA Order for plotted developmentFile: IOD Drawing 2.pdf13 Aug 2019
Building Plan Approval / NA Order for plotted developmentFile: IOD Drawing3.pdf13 Aug 2019
Building Plan Approval / NA Order for plotted developmentFile: IOD Drawing4.pdf13 Aug 2019
Proforma of Allotment letterFile: FINAL RERA AGREEMENT 5TH AUG 2019.pdf13 Aug 2019

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PRUTHVI PURUSHOTTAM on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VILE PARLE EAST6,700+ in Mumbai Suburban

Builder: PRUTHVI ENCLAVE LLP

Pruthvi Enclave LLP has 4 registrations on MahaRERA, including Sanniwas Premises Co-Operative Society Ltd. and PRUTHVI PURUSHOTTAM. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if PRUTHVI PURUSHOTTAM is delayed beyond 30 Jun 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PRUTHVI PURUSHOTTAM?

The registered promoter entity is PRUTHVI ENCLAVE LLP, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PRUTHVI PURUSHOTTAM?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PRUTHVI PURUSHOTTAM?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PRUTHVI PURUSHOTTAM?

The professionals named in the filing: Architect: ANJ ENGINEERING CONSULTANTS LLP; Engineer: SUHAS SAHADEV PALAV; Chartered Accountant: ASHVIN THUMAR; Chartered Accountant: ASHOK M SOLANKI & ASSOCIATE LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PRUTHVI PURUSHOTTAM?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PRUTHVI PURUSHOTTAM. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PRUTHVI PURUSHOTTAM to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.