Home / Browse projects / Thane, Maharashtra / PRIME BALAJI HEIGHT

Registration lapsed No litigation declared Residential / Group Housing project

PRIME BALAJI HEIGHT

By PRIME HOUSING

RG-MH-11544 · RERA P51700010278 · Last updated on MahaRERA portal: 17 Jul 2021

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 34 months past the filed date
  • 6 complaints at MahaRERA
  • Completion date moved by 48 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2023Possession promised34 months past this date
14 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 90%
6Complaints at MahaRERAon this registration
Jump to the 36 documents Report an error

PRIME BALAJI HEIGHT is a Residential / Group Housing project by PRIME HOUSING in Thane, Maharashtra, registered with MahaRERA as P51700010278 on 24 Aug 2017. Possession was promised by 30 Dec 2023 and is now 34 months past that date. The completion date has moved by 48 months from the original filing. 6 complaints are on record with the regulator.

At a glance

Project

  • NamePRIME BALAJI HEIGHT
  • TypeResidential / Group Housing
  • Location
    • Badlapur (M Cl)
    • Ambarnath
    • Thane
    • 421503
  • Pincode421503
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700010278
  • ReraGenie IDRG-MH-11544

Builder

  • NamePRIME HOUSING
  • Entity typePartnership
  • PartnersMANGESH VASANT WARULE, AVINASH DAGADU JAGDALE
  • Other registrations1 more →
  • No longer live2 lapsed, de-registered or revoked

Key dates

34 months past promisethis monthRegisteredAug 2017First promiseDec 2019Revised toDec 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on24 Aug 2017
  • Promised completion30 Dec 2023
  • Revised completionRevised to 30 Dec 2023 (originally 31 Dec 2019)
  • Buildings2 building records
  • Documents filed36 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WINGNA90000
B WINGNA110000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 17 Jul 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 90%.

A WING91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B WING68%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.40%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.40%

Progress on shared amenities15

As on 17 Jul 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes90%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes95%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes95%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes80%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes75%
Electrical meter room, sub-station, receiving stationYes80%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed25

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots25
Closed/Covered2
Open Space23
BuildingClosed/CoveredOpen SpaceTotal
A WING11516
B WING189

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,910 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
RADHABAI KRUSHNAJI PISEKARBadlapur (M Cl)Thane

Approvals and building plan

Permissible FSI3614.0
Proposed, not sanctioned3,614 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR, SATYA SIDDHI CHS,SHOP NO - 2 TO 7, PLOT NO - 19SECTOR - 11, KALAMBOLI, Mumbai, Maharas

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSACHIN VILAS SAHANE
PartnerRole in project
PRIME HOUSING-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700003697Dec 2019 → Dec 2020

Reason as filed by the promoterAs per the details mentioned at the time of registration of the project at the Maharera Website we have mentioned 31.12.2019 as the project completion date. However, we were not able to complete the construction work since there was flood in Badlapur in the month of July and August 2019 due to which one entire floor of the said project was submerged in water causing us a lot of issues. Hence, we would like to seek an extension period of one year for the completion of the said project ie. Till 31.12.2020.

EXT51700010495Dec 2019 → Jun 2023

Reason as filed by the promoterThe Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of the pandemic of Covid-19. We are on the verge of completing the construction work and are hopeful that once we receive project extension we shall obtain Occupancy Certificate from the Competent Authority and complete the project in all aspects. The project is comprising of 2 wings - A and B wing. A Wing has received the occupancy Certificate in the year 2017. B WIng comprises of 86 units, out of which 71 units are sold. We have received the consent of more

Complaints filed with MahaRERA6

Case no.ComplainantRespondentFiled
CC006000000192972Suresh Narayan DalviM/s Prime Housing18/03/2020
CC006000000195727Supriya Suresh DalviPrime Housing23/01/2021
CC006000000195728Supriya Suresh DalviPrime Housing23/01/2021
CC12400228Shayam Sundar Tilak JaiswalPRIME HOUSING25/09/2024
CC12400237DILIP KUMAR CHAUDHARYPRIME HOUSING26/09/2024
CC12602786Dhanshree Dhruvabal ChavanPRIME HOUSING13/05/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 Mar 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 15 Mar 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Jul 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed36

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Commencement Certificates / NA Order for plotted developmentFile: Prime - Cc.pdf17 Jul 2021
Disclosure of sold/ booked inventoryFile: Discloure of Sold or booked inventory_compressed.pdf17 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 Prime Housing FY 2019-2020210717_compressed.pdf17 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Prime Housing FY 2020-2120210717_compressed.pdf17 Jul 2021
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMENT CERTIFICATE.pdf16 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer's Certificate.pdf16 Jul 2021
Layout approvalFile: HPSCANNER1103-1-compressed-rotated.pdf15 Mar 2021
Layout approvalFile: HPSCANNER1102-1 (1)-rotated.pdf15 Mar 2021
Building plan approvalFile: HPSCANNER1103-1-compressed-rotated.pdf15 Mar 2021
Building plan approvalFile: HPSCANNER1102-1 (1)-rotated.pdf15 Mar 2021
Copy of Layout Approval (in case of layout)File: HPSCANNER1103-1-compressed-rotated.pdf15 Mar 2021
Copy of Layout Approval (in case of layout)File: HPSCANNER1102-1 (1)-rotated.pdf15 Mar 2021
Building Plan Approval (IOD)File: HPSCANNER1103-1-compressed-rotated.pdf15 Mar 2021
Building Plan Approval (IOD)File: HPSCANNER1102-1 (1)-rotated.pdf15 Mar 2021
Commencement Certificates / NA Order for plotted developmentFile: Prime Balaji Heights Revised CC.pdf15 Mar 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 17-18 final.pdf24 Dec 2019
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 18-19 final.pdf24 Dec 2019
Building plan approvalFile: layout A final.pdf31 Jul 2017
Layout approvalFile: layout A final.pdf31 Jul 2017
Building plan approvalFile: layout B final.pdf31 Jul 2017
Layout approvalFile: layout B final.pdf31 Jul 2017
PAN CardFile: PanCard.pdf31 Jul 2017
Copy of the legal title reportFile: Search report Title Clearanc1.pdf31 Jul 2017
Details of encumbrancesFile: 7-12,ferfar-final.pdf31 Jul 2017
Details of encumbrancesFile: DECLARATION PRIME.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: layout B final.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: layout A final.pdf31 Jul 2017
Building Plan Approval (IOD)File: layout B final.pdf31 Jul 2017
Building Plan Approval (IOD)File: layout A final.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC-New.pdf31 Jul 2017
Declaration in FORM BFile: Declaration B-1.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Architect Report A-1.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Architect Report B-1.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Prime Engineer Certificate-1.pdf31 Jul 2017
Certificates of CA (Form 3)File: ca certificate final-1.pdf31 Jul 2017
Proforma of Allotment letterFile: Agreement of Sale-PBH.pdf31 Jul 2017

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 48 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PRIME BALAJI HEIGHT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Badlapur (M Cl)7,600+ in Thane

2 kmPRIME BALAJI HEIGHTCompleted 27Lapsed / revoked 14Other 20Dot size: filed unitsN

Filed coordinates, straight-line distance. 61 registered projects within 2 km.

Builder: PRIME HOUSING

PRIME HOUSING has 2 registrations on MahaRERA, including PRIME BALAJI HEIGHT and SANGEET JYOTI. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that PRIME BALAJI HEIGHT shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if PRIME BALAJI HEIGHT is delayed beyond 30 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PRIME BALAJI HEIGHT?

The registered promoter entity is PRIME HOUSING, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PRIME BALAJI HEIGHT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against PRIME BALAJI HEIGHT?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for PRIME BALAJI HEIGHT?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PRIME BALAJI HEIGHT?

The professionals named in the filing: Architect: SACHIN VILAS SAHANE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PRIME BALAJI HEIGHT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PRIME BALAJI HEIGHT. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PRIME BALAJI HEIGHT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.