Home / Browse projects / Mumbai Suburban, Maharashtra / Pride Panorama
Pride Panorama
RG-MH-76289 · RERA P51800034548 · Last updated on MahaRERA portal: 18 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- 1 complaint at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Pride Panorama is a Residential / Group Housing project by Landcare Realty LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800034548 on 11 Apr 2022. Possession was promised by 31 Dec 2025 and is now 10 months past that date. 1 complaint is on record with the regulator.
At a glance
Project
- NamePride Panorama
- TypeResidential / Group Housing
- Location
- Andheri Kurla Road
- Sakinaka
- Village Mohili
- Kurla
- Mumbai Suburban
- 400072
- Pincode400072
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800034548
- ReraGenie IDRG-MH-76289
Builder
- NameLandcare Realty LLP
- Entity typeOthers
- Named personSanjay Baboo Jain
- Other registrations1 more →
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on11 Apr 2022
- Promised completion31 Dec 2025
- Revised completionNone
- Buildings4 building records
- Documents filed101 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A Wing | NA | 17 | 0 | 0 | 0 | 0 |
| B Wing | NA | 17 | 0 | 0 | 0 | 0 |
| C Wing | NA | 17 | 0 | 0 | 0 | 0 |
| Club House | NA | 3 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 18 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
32 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is External plumbing and external plaster, at 85%.
A Wing86%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 75% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 85% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 85% |
B Wing86%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 75% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 85% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 85% |
C Wing86%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 75% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 85% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 85% |
Club House100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 18 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 50% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 75% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 90% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 75% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 85% |
| Electrical meter room, sub-station, receiving station | Yes | 80% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed4
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| A Wing | 1 | 1 |
| B Wing | 1 | 1 |
| C Wing | 1 | 1 |
| Club House | 1 | 1 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Fizza Alihusain Boxwala & Others | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Mandviwala Qutub & Associates |
| Architect | Spaceage Consultants |
| Engineer | JW Consultant |
| Engineer | Engineering Creation Services Consultant |
| Engineer | M B Andurlekar & Associates |
| Chartered Accountant | Sp Jain & Associates |
| Partner | Role in project |
|---|---|
| Landcare Realty LLP | - |
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12602766 | Priya Hozefa Sadriwala | Landcare Realty LLP | 12/05/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 28 Mar 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 Mar 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 31 Mar 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 14 Mar 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed101
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 101 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form 1.pdf | 18 Apr 2026 |
| Form 2File: Form 2.PDF | 18 Apr 2026 |
| Form 3File: Form 3 - Landcare.pdf | 18 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory -.pdf | 18 Apr 2026 |
| OthersFile: Form 3 - Promoter-.pdf | 18 Apr 2026 |
| Withdrawal Update Form 1File: Architects Certificate -.pdf | 16 Jan 2026 |
| Withdrawal Update Form 2File: Engineer_Certificate.pdf | 16 Jan 2026 |
| Withdrawal Update Form 3File: Form 3 - Landcare.pdf | 16 Jan 2026 |
| Form 3File: Form 3 - LC.pdf | 17 Dec 2025 |
| Form 2File: Form -2.pdf | 17 Dec 2025 |
| Form 1File: Form 1.pdf | 17 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Inventory.pdf | 17 Dec 2025 |
| OthersFile: Form 3 - Promoter.pdf | 17 Dec 2025 |
| Form 3File: Form 3 - LC.pdf | 17 Oct 2025 |
| OthersFile: Form 3 - Promoter.pdf | 17 Oct 2025 |
| Form 1File: Form 1.pdf | 17 Oct 2025 |
| Form 2File: Form -2.pdf | 17 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Inventory.pdf | 17 Oct 2025 |
| Form 1File: Form 1 - Architect Certificate - Q1.pdf | 18 Jul 2025 |
| Form 2File: FORM - 2 - Engineers Certificate - Q1.pdf | 18 Jul 2025 |
| Form 3File: Form 3 - CA Certificate - Q1 - Owner.pdf | 18 Jul 2025 |
| OthersFile: Form 3 - CA Certificate - Q1 - Promoter.pdf | 18 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Form 3 - CA Certificate - Q1 - Owner.pdf | 18 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - PI.pdf | 19 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - PI.pdf | 19 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - PI - Promoter.pdf | 19 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM - 2 - PI.pdf | 19 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2 A - PI.pdf | 19 Apr 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5.pdf | 19 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 -.pdf | 26 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Landcare.pdf | 26 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Promoter.pdf | 26 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_.pdf | 26 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5.pdf | 4 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf | 27 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Certificate.pdf | 27 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form - 3.pdf | 27 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form - 3.pdf | 27 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 27 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 27 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate.pdf | 27 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate Phase.pdf | 27 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf | 27 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate -.pdf | 14 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer_Certificate.pdf | 14 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - PI - Landcare.pdf | 14 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - PI - Owner.pdf | 14 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate PI.pdf | 29 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate PI.pdf | 29 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Landcare - Phase I.pdf | 23 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Promoter - Phase I.pdf | 23 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate Phase I.pdf | 19 Jun 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate Phase I.pdf | 19 Jun 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Phase I.pdf | 19 Jun 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Phase I - Landowner.pdf | 19 Jun 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Certificate.pdf | 15 Dec 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineers Certificate.pdf | 15 Dec 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Landcare.pdf | 1 Dec 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form - 3 - Promoters.pdf | 1 Dec 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Chartered Accountant Certificate - Landcare.pdf | 20 Aug 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf | 18 Aug 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate.pdf | 18 Aug 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Chartered Accountant Certificate - Landcare.pdf | 18 Aug 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Chartered Account - Certificate - Promoter.pdf | 18 Aug 2022 |
| Declaration in FORM BFile: FORM B - Corrected.pdf | 6 Apr 2022 |
| Building plan approvalFile: 1.pdf | 31 Mar 2022 |
| Building plan approvalFile: 2.pdf | 31 Mar 2022 |
| Building plan approvalFile: 4.pdf | 31 Mar 2022 |
| Building plan approvalFile: 5.pdf | 31 Mar 2022 |
| Building plan approvalFile: 6.pdf | 31 Mar 2022 |
| Building plan approvalFile: 7.pdf | 31 Mar 2022 |
| Building plan approvalFile: 8.pdf | 31 Mar 2022 |
| Building plan approvalFile: 9.pdf | 31 Mar 2022 |
| Building plan approvalFile: 10.pdf | 31 Mar 2022 |
| Building plan approvalFile: 11.pdf | 31 Mar 2022 |
| Layout approvalFile: 2021-07-01 2nd IOD amendend approval letter.pdf | 31 Mar 2022 |
| Copy of Layout Approval (in case of layout)File: 2021-07-01 2nd IOD amendend approval letter.pdf | 31 Mar 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 1.pdf | 31 Mar 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 2.pdf | 31 Mar 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 4.pdf | 31 Mar 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 101 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Pride Panorama on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Sakinaka, Village Mohili6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 120 registered projects within 2 km.
AMARYLLIS TOWERS AND PLAZA
NAHAR BUILDERS LTD.
JANGID MEADOWS
JANGID HOME PVT LTD
NAHAR'S CHANDI VALLEY - PHASE I
NAHAR BUILDERS LIMITED
KABRA RESIDENCY PARK
AHINSA BUILDTECH PVT LTD
IBIS at L and T Realty Elixir Reserve
Larsen & Toubro Ltd. (Realty Division)
BARBET at L and T Realty Elixir Reserve
Larsen & Toubro Ltd. (Realty Division)
See every Mumbai Suburban project, with the district possession charts
Builder: Landcare Realty LLP
Landcare Realty LLP has 2 registrations on MahaRERA, including Pride Panorama and Pride Panorama. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that Pride Panorama shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Pride Panorama is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Pride Panorama?
The registered promoter entity is Landcare Realty LLP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Pride Panorama?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Pride Panorama?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Pride Panorama?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Pride Panorama?
The professionals named in the filing: Architect: Mandviwala Qutub & Associates; Architect: Spaceage Consultants; Engineer: JW Consultant; Engineer: Engineering Creation Services Consultant; Engineer: M B Andurlekar & Associates; Chartered Accountant: Sp Jain & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Pride Panorama?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback