ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Prayagraj

Registered No litigation declared Others project

Prayagraj

By B K Khose Private Limited

RG-MH-31190 · RERA P52100079524 · Last updated on MahaRERA portal: 28 May 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedno revision filed
1 of 11Construction stages donefurthest along: Basement (if any), 50%
75 of 75Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 66 documents Report an error

Prayagraj is a Others project by B K Khose Private Limited in Pune, Maharashtra, registered with MahaRERA as P52100079524 on 10 Mar 2025. Possession is promised by 31 Dec 2027. 0 of the 75 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete.

At a glance

Project

  • NamePrayagraj
  • TypeOthers
  • Location
    • DP road
    • Bapu Buwaji Nagar
    • Tathwade
    • Mulshi
    • Pune
    • 411033
  • Pincode411033
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100079524
  • ReraGenie IDRG-MH-31190

Builder

  • NameB K Khose Private Limited
  • Entity typeCompany

Key dates

this monthRegisteredMar 2025PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on10 Mar 2025
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed66 files

Current status

0%0 of 75 units booked
20.5%Work done, per cost certificate

Figures as on 28 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building ANA1313651075

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 28 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 50%.

Building A: 14% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)50%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 28 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed153

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots153
Closed/Covered153

Land and ownership14

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,905 sq m
Land owned byNot the promoter
Named landowners14
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on29 Jul 2025
LandownerVillageDistrict
Aniruddha Madhav DikeSinhgad RoadPune
Prajakta Aniruddha DikeSinhgad RoadPune
Kanchan Ashok GadekarKothrudPune
Ashok Bajirao BorudeChinchwadPune
Bhaskar khandu KhoseChinchwadPune
Vilas vitthal LokhandeChinchwadPune
Sunita Sanjay BagadeChinchwadPune
Subhash Raghunath JadhavWahangaonPune
Mahesh Sadanand ShettyKamshetPune
Mithila Mukund AwateWadaPune
Shahaji Adinath KarkarThergaonPune
Abasaheb Krushnaji DhawaleChinchwadPune
Sambhaji vithoba KambaleSangaviPune
Ashok Dattatray GadekarKothrudPune

Approvals and building plan

Sanctioning authorityPimpri-Chinchwad Municipal Corporation
Permissible FSI10404.6
Proposed, not sanctioned7,059 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchOPP KALASAGAR HOTEL, NEAR DI-CHI CO, KASARWADI, DISTT. PUNE, MAHARASHTRA 411034
Estimated costRs 22.20 cr
Cost incurredRs 4.55 cr
Work done20.5%
BuildingWingEstimatedIncurred
Building ANARs 22.20 crRs 4.55 cr

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDream Space Architect Mahendra Thakur
EngineerPrayag Khose
Chartered AccountantChoudhary Chavan & Associates CA Shruti Choudhary and CA Sourabh Chavan
PartnerRole in project
B K Khose Private Limited-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 Feb 2025
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 Jan 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Jan 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Jan 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed66

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: form 1 Prayagraj _March 2026 (1).pdf28 May 2026
Withdrawal Update Form 2File: form 2 Prayagraj _March 2026 (1).pdf28 May 2026
Withdrawal Update Form 3File: Q 4 form 3.pdf28 May 2026
Withdrawal Update Form 1File: form 1 Prayagraj _March 2026 (1).pdf27 May 2026
Withdrawal Update Form 2File: form 2 Prayagraj _March 2026 (1).pdf27 May 2026
Withdrawal Update Form 3File: Revised form 3.pdf27 May 2026
Withdrawal Update Form 1File: form 1 Prayagraj _March 2026 (1).pdf24 Apr 2026
Withdrawal Update Form 2File: form 2 Prayagraj _March 2026 (1).pdf24 Apr 2026
Withdrawal Update Form 3File: form 3 Prayagarj_March 2026 (1)_compressed.pdf24 Apr 2026
Withdrawal Update Form 1File: Form 1_PRAYAGRAJ _Q3_25-26_compressed (2).pdf30 Jan 2026
Withdrawal Update Form 2File: Form 2_PRAYAGRAJ_Q3_25-26_compressed (2).pdf30 Jan 2026
Withdrawal Update Form 3File: Form 3_PRAYAGRAJ_Q3_25-26_compressed (1).pdf30 Jan 2026
Form 1File: Form 1 Arch cert.pdf16 Oct 2025
Form 2File: Form 2 Eng Cert.pdf16 Oct 2025
Form 3File: Form 3 CA Certificate_Prayagraj.pdf16 Oct 2025
Disclosure of Sold and Booked InventoryFile: 1 Prayagraj disclosure of sold units and inventory.pdf16 Oct 2025
Withdrawal Update Form 1File: Form 1 Arch cert.pdf16 Oct 2025
Withdrawal Update Form 1File: Form 1 Arch cert.pdf16 Oct 2025
Withdrawal Update Form 2File: Form 2 Eng Cert.pdf16 Oct 2025
Withdrawal Update Form 2File: Form 2 Eng Cert.pdf16 Oct 2025
Withdrawal Update Form 3File: Form 3 CA Certificate_compressed.pdf16 Oct 2025
Withdrawal Update Form 3File: Form 3 CA Certificate_compressed.pdf16 Oct 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: DECLARATION Wrt FORM3.pdf14 Feb 2025
Other - TechnicalFile: PHOTO-2025-02-21-11-52-29.pdf14 Feb 2025
Other - TechnicalFile: Annexure A .pdf14 Feb 2025
Copy of the legal title reportFile: khose title.pdf7 Feb 2025
Other - FinanceFile: 20250131182728-output.pdf7 Feb 2025
Proforma of Allotment letterFile: Allotment Letter FINAL PRAYAGRAJ.pdf4 Feb 2025
Deviation Report with respect to model copy of AgreementFile: pdf_to_scan_67a89c56e1278_temp_67a89c42746a1_11zon.pdf4 Feb 2025
Proforma of Agreement for saleFile: Prayagraj RERA DRAFT FINAL (3).pdf4 Feb 2025
Declaration in FORM BFile: form b (3).pdf1 Feb 2025
Details of encumbrances concerned to FinanceFile: fef.pdf31 Jan 2025
Details of encumbrances concerned to FinanceFile: lef.pdf31 Jan 2025
Declaration about Commencement CertificateFile: dec abt cc (2).pdf31 Jan 2025
CERSAI detailsFile: cersai (2).pdf31 Jan 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Declaration about RERA Designated Bank Accounts for Real Estate Projects (1).pdf31 Jan 2025
Deviation Report with respect to Allotment letterFile: allotment letter deviation.pdf31 Jan 2025
Details of encumbrances concerned to LegalFile: fef.pdf31 Jan 2025
Details of encumbrances concerned to LegalFile: lef.pdf31 Jan 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: other real estate.pdf31 Jan 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: real estate cc.pdf31 Jan 2025
Disclosure for secured/unsecured finance availed for the projectFile: secured unsecured.pdf31 Jan 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: prayagraj banl.pdf30 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: new Form_3_06-03-2025 4_11zon.pdf27 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf27 Jan 2025
Building plan approvalFile: na.pdf25 Jan 2025
Copy of the legal title reportFile: RERA.pdf25 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: na.pdf25 Jan 2025
Layout approvalFile: Plot_Layout_11zon (1).pdf15 Jan 2025
Layout approvalFile: Basement_2_11zon (1).pdf15 Jan 2025
Layout approvalFile: Basement_1_11zon (1).pdf15 Jan 2025
Layout approvalFile: Ground_First_Floor_11zon.pdf15 Jan 2025
Layout approvalFile: Second_Third_Typical_11zon.pdf15 Jan 2025
Layout approvalFile: Seventh_terrace_11zon.pdf15 Jan 2025
Layout approvalFile: Section_11zon (1).pdf15 Jan 2025
Copy of Layout Approval (in case of layout)File: Seventh_terrace_11zon.pdf15 Jan 2025
Copy of Layout Approval (in case of layout)File: Section_11zon (1).pdf15 Jan 2025
Copy of Layout Approval (in case of layout)File: Second_Third_Typical_11zon.pdf15 Jan 2025
Copy of Layout Approval (in case of layout)File: Ground_First_Floor_11zon.pdf15 Jan 2025
Copy of Layout Approval (in case of layout)File: Basement_1_11zon (1).pdf15 Jan 2025
Copy of Layout Approval (in case of layout)File: Basement_2_11zon (1).pdf15 Jan 2025
Copy of Layout Approval (in case of layout)File: Plot_Layout_11zon (1).pdf15 Jan 2025
Commencement Certificates / NA Order for plotted developmentFile: Badhkam Parvana_11zon.pdf15 Jan 2025
Other - LegalFile: 7 12.pdf15 Jan 2025
PAN CardFile: khose pan.pdf6 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 123.pdf6 Jan 2025

How this compares with Pune

0%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Prayagraj on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Bapu Buwaji Nagar13,700+ in Pune

2 kmPrayagrajCompleted 105Lapsed / revoked 35Other 109Dot size: filed unitsN

Filed coordinates, straight-line distance. 249 registered projects within 2 km.

Builder: B K Khose Private Limited

B K Khose Private Limited has 1 registration on MahaRERA, including Prayagraj. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Prayagraj is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Prayagraj?

The registered promoter entity is B K Khose Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Prayagraj?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Prayagraj?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Prayagraj?

The professionals named in the filing: Architect: Dream Space Architect Mahendra Thakur; Engineer: Prayag Khose; Chartered Accountant: Choudhary Chavan & Associates CA Shruti Choudhary and CA Sourabh Chavan. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Prayagraj?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Prayagraj. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Prayagraj to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.