Home / Browse projects / Udupi, Karnataka / Pratham Nakshatra

Registration approved Residential/Group Housing project

Pratham Nakshatra

By S. S. PROPERTIES PVT. LTD.,

RG-KA-38143 · RERA PRM/KA/RERA/1273/318/PR/181103/002118 · Last updated on RERA Karnataka portal: 5 Jun 2022

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 21 months
  • 2 extensions taken

Clear

  • No complaints on record
  • Separate project account declared
Mar 2023Possession promisedmoved 21 months from the original
0 of 16Construction stages donefurthest along: Earth work and other leveling..., 0%
43 of 43Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 122 documents Report an error

Pratham Nakshatra is a Residential/Group Housing project by S. S. PROPERTIES PVT. LTD., in Udupi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1273/318/PR/181103/002118 on 3 Nov 2018. Possession is promised by 30 Mar 2023. The completion date has moved by 21 months from the original filing. 0 of the 43 units on this registration are recorded sold or booked, and 0 of 16 construction stages are filed complete.

At a glance

Project

  • NamePratham Nakshatra
  • TypeResidential/Group Housing
  • Location
    • Udupi
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1273/318/PR/181103/002118
  • ReraGenie IDRG-KA-38143

Builder

  • NameS. S. PROPERTIES PVT. LTD.,
  • Entity typeCompany
  • CINU45201MH2006PTC164524
  • Authorized SignatorySOMANATH S. SHETTY
  • DirectorsSHASHILATA SANTOSH SHETTY, VIJAYA DILIP PODDAR, SANTOSH MANJAYYA SHETTY
  • Declared earlier projects3 →

Key dates

this monthRegisteredNov 2018First promiseJun 2021Revised toMar 2023

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on3 Nov 2018
  • Promised completion30 Mar 2023
  • Revised completionRevised to 30 Mar 2023 (originally 30 Jun 2021)
  • Buildings1 building record
  • Documents filed122 files

Current status

0%0 of 43 units booked

Figures as on 5 Jun 2022, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Pratham Nakshathra---43043

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 5 Jun 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 16 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 0%.

Building: 0% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)Not applicable
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)Not applicable
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 5 Jun 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes-
Water conservationNoNot applicable
Energy managementYes-
Fire protection and fire safety requirementsYes-
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes-
Swimming PoolNoNot applicable
GymYes-
ParksNoNot applicable
Power BackupYes-
GasYes-
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,862 sq m
Land owned byNot the promoter
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 18.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectImran Shaikh
EngineerShivarama Bhat V.S.

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionJun 2021 → Mar 2022

No reason recorded in the filing

EX/PRM/KA/RERA/1273/318/PR/220912/002118Mar 2022 → Mar 2023

Reason as filed by the promoterothers

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed122

As listed on the registration, under the names the promoter filed them with; the newest 80 of 122 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1273/318/PR/181103/002118 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
chartered accountant certificate-fund requiredFile: ca cert fund required.pdf5 Jun 2022
chartered accountant certificate-fund utilizedFile: ca cert fund utilized.pdf5 Jun 2022
Power nocFile: mescom noc.pdf5 Jun 2022
water noc affidavitFile: Affidavit on water noc.pdf5 Jun 2022
clarificationFile: CLARIFICATION.jpg5 Jun 2022
Designated bank account number clarificationFile: bank Change Request Conirmation.pdf27 May 2022
consent letterFile: consent letter.pdf27 May 2022
Project Contractors detailsFile: Contractor Details.pdf27 May 2022
Power supply NOCFile: mescom noc.pdf27 May 2022
FIRE NOCFile: FIRE NOC.pdf27 May 2022
PROFORMA AOSFile: profroma AOS.pdf27 May 2022
STP DRAWINGFile: STP LOCATIN DRAWING-Model.pdf27 May 2022
project specificationFile: Specifications.pdf27 May 2022
PROJECT EXTENSION CONFIMATIONFile: Extension Confirmation.pdf27 May 2022
Advocate Search ReportFile: Advocate Search Report.pdf27 May 2022
WATER NOC AFFIDAVITFile: Affidavit.pdf27 May 2022
CLARIFICATIONFile: Clarification.pdf27 May 2022
confirmation of bank change requestFile: bank Change Request Conirmation.pdf5 May 2022
Covid extension registration certificateFile: covid extension certficate.pdf5 May 2022
affidavit seeking extension in form- Ex07File: Affidavit.pdf5 May 2022
form-BFile: form B.pdf5 May 2022
Architects Certificates-for work completedFile: Arc certificate - work completed.pdf5 May 2022
Architects Certificates-work pendingFile: Arc certificate - work pending.pdf5 May 2022
Modification Approval From RERA-application confirmationFile: modification Change Request Conirmation.pdf5 May 2022
Engineer certificate-work completedFile: Engineer Certificate work completed.pdf5 May 2022
Engineer certificate-work pendingFile: Engineer Certificate-work pending.pdf5 May 2022
List of allotteesFile: allotment list.pdf5 May 2022
affidavit for paying compensation event due to delayFile: affidavit agree to pay componseation.pdf5 May 2022
affidavit for seeking extension with paying compensation event due to delayFile: Affidavit for extension along with agree to pay componseation.pdf5 May 2022
break up development detailsFile: development details.pdf5 May 2022
project contractors detailsFile: Contractor Details.pdf5 May 2022
fire nocFile: FIRE NOC.pdf5 May 2022
project specificationFile: Specifications.pdf5 May 2022
proforma AOSFile: profroma AOS.pdf5 May 2022
STP IN PROJECTFile: STP LOCATIN DRAWING-Model.pdf5 May 2022
clarificationFile: Clarification.pdf5 May 2022
CertificateFile: CERTIFICATE OF INCOROPORATION.jpg-
Modified plan details site plan, floor plans, Plan Licence LetterFile: building licence application copy.jpeg-
List Of AllotteesFile: allotment list.pdf-
Consent LetterFile: consent letter.pdf-
Chartered Accountant CertificateFile: CA MODIFICATION.pdf-
Notarized AffidavitFile: affidavit.pdf-
Engineer CertificateFile: engineer certficate.pdf-
Architect CertificateFile: Architect Certificate (1).pdf-
Structural Engineer Certificate for stability of structureFile: stability certficate.jpeg-
Modification of Plan DetailsFile: Site_Plan.pdf-
Modification of Plan DetailsFile: site plan.pdf-
Modification of Plan DetailsFile: old building licence.pdf-
Modification of Plan DetailsFile: building licence application copy.jpeg-
Modification of Plan DetailsFile: sold unsold unit as per old licence.pdf-
Modification of Plan DetailsFile: sold unsold unit as per new licence.pdf-
Document 1File: FIRE NOC.pdf-
consent letterFile: consent letter.pdf-
consent listFile: consent list.pdf-
allotment letterFile: allotment letter.pdf-
allottee listFile: allotment list.pdf-
EC 2018-2022File: EC 2018-2022.pdf-
INVENTORY DETAILSFile: inventory details.pdf-
SOLD UNSOLD ABSTRACTFile: sold unsold unit abstract.pdf-
NEW SANCTION PLANFile: new sanction plan_compressed.pdf-
SITE PLANFile: site plan.pdf-
LOWER GROUND FLOOR PLANFile: LG fllor plan.pdf-
UPPER GROUND FLOOR PLANFile: UG fllor plan.pdf-
FIRST FLOOR PLANFile: first floor plan.pdf-
FLOOR PLANFile: floor plan.pdf-
TERRACE PLANFile: terrace plan.pdf-
ELEVATIONFile: elevation.pdf-
SECTION PLANFile: section plan.pdf-
AffidavitFile: affidavit.pdf-
Latest Encumbrance CertificateFile: EC 2018-2022.pdf-
Consent letter from 2/3rd of AllotteesFile: consent list.pdf-
Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx-
Document 1File: consent letter.pdf-
Document 2File: consent list.pdf-
Document 3File: allotment letter.pdf-
Document 4File: allotment list.pdf-
Document 5File: Reason for delay.pdf-
Building Licence of Pratham Naksthra-
Single Layout of Pratham Nakshathra-
Sale_Deed_-_S_S_Nakshathra_-_Draft-

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 not delivered by the promised date
ProjectLocationStatusPromisedDelivered
Pratham Vrindavan 2nd Phase-Completed-Not delivered
Pratham Vrindavan 1st Phase-Completed-Not delivered
Pratham Krishna-Completed-Not delivered

How this compares with Udupi

0%of this project is bookeddistrict median 0%
22%of Udupi projects moved their completion datethis one moved by 21 months
0%of Udupi registrations have lapsed or been cancelledthis one is on the register

Computed across the 260+ Udupi projects on ReraGenie, from their own filings.

Keep Pratham Nakshatra on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Udupi260+ in Udupi

2 kmPratham NakshatraOther 35Dot size: filed unitsN

Filed coordinates, straight-line distance. 35 registered projects within 2 km.

Builder: S. S. PROPERTIES PVT. LTD.,

S. S. PROPERTIES PVT. LTD., has 1 registration on RERA Karnataka, including Pratham Nakshatra. Its filings disclose 3 earlier RERA Karnataka projects, none completed yet. Read the full track record. See more projects on the Udupi district page.

Frequently asked questions

What are my rights if Pratham Nakshatra is delayed beyond 30 Mar 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Pratham Nakshatra?

The registered promoter entity is S. S. PROPERTIES PVT. LTD.,, a company as per the filing. Its CIN U45201MH2006PTC164524 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Pratham Nakshatra?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Pratham Nakshatra?

The professionals named in the filing: Architect: Imran Shaikh; Engineer: Shivarama Bhat V.S.. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Pratham Nakshatra?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Pratham Nakshatra. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Pratham Nakshatra to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.