PRASADAM -PHASE V- WING R S T AND U
By SAI ASHRAY DEVELOPERS PVT LTD
RG-MH-26572 · RERA P51700008671 · Last updated on MahaRERA portal: 20 Jan 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 39 months past the filed date
- 15 complaints at MahaRERA
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
PRASADAM -PHASE V- WING R S T AND U is a Residential / Group Housing project by SAI ASHRAY DEVELOPERS PVT LTD in Thane, Maharashtra, registered with MahaRERA as P51700008671 on 19 Aug 2017. Possession was promised by 19 Jul 2023 and is now 39 months past that date. The completion date has moved by 12 months from the original filing. 15 complaints are on record with the regulator.
At a glance
Project
- NamePRASADAM -PHASE V- WING R S T AND U
- TypeResidential / Group Housing
- Location
- Ambarnath
- Ambarnath(M Cl)
- Thane
- 421501
- Pincode421501
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700008671
- ReraGenie IDRG-MH-26572
Builder
- NameSAI ASHRAY DEVELOPERS PVT LTD
- Entity typeCompany
- DirectorJia Zhuowen Wei
- Other registrations5 more →
- No longer live6 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on19 Aug 2017
- Promised completion19 Jul 2023
- Revised completionRevised to 19 Jul 2023 (originally 19 Jul 2022)
- Buildings1 building record
- Documents filed122 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| PRASADAM WING RSTU | NA | 9 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 20 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 89%.
PRASADAM WING RSTU: 50% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 89% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 20% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 38% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 20 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed37
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership2
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Darshana Anand Damle | Badlapur (M Cl) | Thane |
| Bharat J Patel | Andheri | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SYHAM J HEMRAJANI |
| Partner | Role in project |
|---|---|
| SAI ASHRAY DEVELOPERS PVT LTD | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to the Prevailing Pandemic situation, more than three months labours & materials were not available on site.
Litigation declared1
| Case | Court | Status |
|---|---|---|
| 371/2015 | Civil Court Ulhasnagar | Pending |
Complaints filed with MahaRERA15
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000000267 | Kishorkumar Valmik Thakare | GAUTAM JAGDISH AHUJA | 10/09/2017 |
| CC006000000000502 | Manoj Raj Kuwar | M/S Sai Ashray Developers Pvt. Ltd. | 09/09/2017 |
| CC006000000192309 | Samadhan Jagannath Patil | Sai Ashray Developers Pvt. Ltd. | 06/02/2020 |
| CC006000000078254 | Leena Radhakrishnan | Sai Ashray Developers Pvt Ltd | 25/02/2019 |
| CC006000000023521 | SACHIN TITKARE | SAI ASHRAY DEVELOPERS PVT LTD | 26/02/2018 |
| CC006000000055960 | kamlesh D Ahire and Sangita Kamlesh Ahire | Sai Ashray Devlopers Private Limited | 27/08/2018 |
| CC006000000056582 | VIJAYKUMAR SHINDE | SAI ASHRAY DEVELOPER PVT LTD | 16/10/2018 |
| CC006000000171545 | Namdeo Bhimrao Jadhav and Mrs.Ranjana Namdeo Jadhav | M/s.Sai Ashray Developers Pvt. Ltd. | 14/11/2019 |
| CC006000000198672 | 1. Mr. S. K. Prakash Nair | Sai Ashray Developers Private Limited | 21/10/2021 |
| CC006000000194514 | PRADEEP PANDEY | M/S SAI ASHRAY DEVELOPERS PRIVATE LIMITED | 17/10/2020 |
| CC006000000209633 | Estatto Realty and Wealth Solutions LLP | Sai Ashray Developers Pvt. Ltd. | 31/01/2022 |
| CC006000000196103 | Nitin Lalji Dhande | Sai Ashray Developers Private Limited | 20/02/2021 |
| CC006000000591556 | Khushal Nanasaheb Kapate | SAI ASHRAY DEVELOPERS PVT LTD | 15/08/2024 |
| CC12504215 | Prasadam Triveni Phase V RSTU Cooperative Housing Society Limited | SAI ASHRAY DEVELOPERS PVT LTD | 28/11/2025 |
| CC12600881 | Vitthal Maruti Patil | SAI ASHRAY DEVELOPERS PVT LTD | 17/02/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 19 Aug 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 19 Aug 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 19 Aug 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed122
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 122 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PRASADAM PHASE V - Rera Eng Certi - RSTU - Dec 24.pdf | 20 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PRASADAM PHASE V - Rera Eng Certi - RSTU - Sep 24.pdf | 18 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PRASADAM PHASE V - Rera Eng Certi - RSTU - Jun 24.pdf | 18 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RSTU.pdf | 9 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PRASADAM PHASE V - Rera Eng Certi - RSTU - Mar 24.pdf | 20 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PRASADAM PHASE V - Rera Eng Certi - RSTU - Dec 23.pdf | 6 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PRASADAM PHASE V - Rera Eng Certi - RSTU - Sep 23.pdf | 7 Oct 2023 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate for RERA Compliance - Prasadam RSTU Sept 23.pdf | 7 Oct 2023 |
| Certificates of CA (Form 5)File: RERA Certificate Form no 5 of FY 2022-23 - Prasadam Phase V-RSTU.pdf | 30 Sep 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: RERA Certificate Form no 5 of FY 2022-23 - Prasadam Phase V-RSTU.pdf | 30 Sep 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PRASADAM PHASE V - Rera Eng Certi - RSTU - Jun 23.pdf | 7 Jul 2023 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate for RERA Compliance - Prasadam RSTU Jun 23.pdf | 7 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Prasadam -RSTU - Phase V.pdf | 4 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RSTU.pdf | 19 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: G2.pdf | 17 Apr 2023 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate for RERA Compliance - Prasadam RSTU Mar 23.pdf | 7 Apr 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PRASADAM PHASE V - Rera Eng Certi - RSTU - Mar 23.pdf | 6 Apr 2023 |
| Proforma of Allotment letterFile: Revised RERA Proposed Allotment Letter Prasadam.pdf | 21 Mar 2023 |
| Deviation Report with respect to Allotment letterFile: Revised Deviation Sheet Allotment Letter Prasadam.pdf | 21 Mar 2023 |
| Proforma of Allotment letterFile: RERA Allotment Letter New Prasadam .pdf | 10 Feb 2023 |
| Deviation Report with respect to Allotment letterFile: Deviation Sheet Allotment Letter Prasadam.pdf | 10 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PRASADAM PHASE V - Rera Eng Certi - RSTU - Dec 22.pdf | 7 Jan 2023 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate for RERA Compliance - Prasadam RSTU Dec 22.pdf | 7 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Prasadam - RSTU (V) - RERA Architect Certificate.pdf | 6 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PRASADAM PHASE V - Rera Eng Certi - RSTU - Sep 22.pdf | 7 Oct 2022 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate for RERA Compliance - Prasadam RSTU Sept 22.pdf | 7 Oct 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Prasadam - RSTU.pdf | 6 Oct 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form no 5 of FY 202122 Prasadam Phase V RSTU.pdf | 30 Sep 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form no 5 of FY 202122 Prasadam Phase V RSTU.pdf | 30 Sep 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Prasadam- RSTU - Architect Certificate.pdf | 7 Jul 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PRASADAM PHASE V - Rera Eng Certi - RSTU - June 22.pdf | 7 Jul 2022 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate for RERA Compliance - Prasadam RSTU June 22.pdf | 7 Jul 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: CA (Form 5).pdf | 24 May 2022 |
| Declaration about Commencement CertificateFile: Declaration about CC.pdf | 17 May 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: RSTU_compressed.pdf | 17 May 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: RSTU_compressed.pdf | 17 May 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_.pdf | 17 May 2022 |
| Disclosure of sold/ booked inventoryFile: Rera extn 2_compressed.pdf | 17 May 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: download.pdf | 17 May 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: download.pdf | 17 May 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PRASADAM PHASE V - Rera Eng Certi - RSTU - Mar 22.pdf | 7 Apr 2022 |
| Certificates of CA (Form 3)File: FORM 3 PRASADAM RSTU.pdf | 7 Apr 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Prasadam - RSTU -Phase V RERA Architect Certificate.pdf | 6 Apr 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Prasadam - RSTU - Phase V - RERA Architect Certificate.pdf | 6 Apr 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PRASADAM PHASE V - Rera Eng Certi - RSTU - Dec-21.pdf | 7 Jan 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 3 PRASADM RSTU.pdf | 7 Jan 2022 |
| Certificates of CA (Form 3)File: FORM 3 PRASADM RSTU.pdf | 7 Jan 2022 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate for RERA Compliance - Prasadam RSTU September 21.pdf | 7 Oct 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Prasadam RSTU - Phase V - Architect Certificate.pdf | 6 Oct 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PRASADAM PHASE V - Rera Eng Certi - RSTU - Sep-21.pdf | 6 Oct 2021 |
| Certificates of CA (Form 5)File: FORM 5 Prasadam Phase V RSTU.pdf | 21 Sep 2021 |
| Building plan approvalFile: building plan.pdf | 19 Aug 2021 |
| Layout approvalFile: building plan.pdf | 19 Aug 2021 |
| Copy of Layout Approval (in case of layout)File: building plan.pdf | 19 Aug 2021 |
| Building Plan Approval (IOD)File: building plan.pdf | 19 Aug 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: CC -.pdf | 19 Aug 2021 |
| Certificates of CA (Form 3)File: Prasadam PH V - RSTU.pdf | 14 Aug 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PRASADAM PHASE V - Rera Eng Certi - RSTU - June-21.pdf | 13 Aug 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 10_PRASADAM _RSTU_ V - RERA Architect Certificate-30.pdf | 10 Aug 2021 |
| Details of encumbrancesFile: Prasadam -Details of Encumbrance-4.pdf | 1 Jul 2021 |
| Certificates of CA (Form 3)File: Prasadam RSTU FORM 3.pdf | 25 Jun 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Prasadam Phase V RSTU.pdf | 21 Jun 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 10_PRASADAM _RSTU_ V - RERA Architect Certificate March21.pdf | 25 May 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5-PRASADAM PHASE V (RSTU PROJECT).pdf | 2 Apr 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: prasadam phase v Sept 20.pdf | 30 Mar 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Prasadam Phase V Dec 20.pdf | 30 Mar 2021 |
| Certificates of CA (Form 3)File: RSTU SEP 2020.pdf | 16 Mar 2021 |
| Certificates of CA (Form 3)File: RSTU DEC 2020.pdf | 16 Mar 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: PRASADAM - RSTU - V -Dec2020.pdf | 25 Feb 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: prasadam phase 5 - March 20.pdf | 16 Feb 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: prasadam phase 5 - June20.pdf | 16 Feb 2021 |
| Certificates of CA (Form 3)File: RSTU - June20.pdf | 13 Feb 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 8_PRASADAM _RSTU_ V - RERA Architect Certificate-30.pdf | 12 Feb 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 8_PRASADAM _RSTU_ V - RERA Architect Certificate-June,20.pdf | 12 Feb 2021 |
| Certificates of CA (Form 3)File: Phase V - RSTU.pdf | 12 Feb 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Prasadam Phase V.pdf | 7 Mar 2020 |
| Certificates of CA (Form 3)File: CA CERTIFICATE RERA PRASADAM R,S,T,U.pdf | 24 Feb 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Prasadam Phase V RSTU.pdf | 17 Feb 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Sai Ashray Wing R,S,T,U.pdf | 30 Nov 2019 |
| Certificates of CA (Form 3)File: RSTU SEPT-19 RERA.pdf | 30 Nov 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 5 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 122 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep PRASADAM -PHASE V- WING R S T AND U on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Ambarnath7,600+ in Thane
Filed coordinates, straight-line distance. 115 registered projects within 2 km.
CHADHA RESIDENCY
CHADHA DEVELOPERS AND PROMOTERS
KRUSHNA VIHAR - PHASE I
KRUSHAN DHAM BUILDERS & DEVELOPERS
VISHWAJEET MYSPACE
GULABRAO BABURAO KARANJULE PATIL
KHATRI SPARSH
KHATRI REALTY
Tulsi Galaxy
Manas Associates
WALEKAR HOMES
WALEKAR & SON'S DEVELOPERS
See every Thane project, with the district possession charts
Builder: SAI ASHRAY DEVELOPERS PVT LTD
SAI ASHRAY DEVELOPERS PVT LTD has 6 registrations on MahaRERA, including PRASADAM - CLUB HOUSE and PRASADAM -PHASE V- WING R S T AND U. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that PRASADAM -PHASE V- WING R S T AND U shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if PRASADAM -PHASE V- WING R S T AND U is delayed beyond 19 Jul 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of PRASADAM -PHASE V- WING R S T AND U?
The registered promoter entity is SAI ASHRAY DEVELOPERS PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in PRASADAM -PHASE V- WING R S T AND U?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against PRASADAM -PHASE V- WING R S T AND U?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for PRASADAM -PHASE V- WING R S T AND U?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at PRASADAM -PHASE V- WING R S T AND U?
The professionals named in the filing: Architect: SYHAM J HEMRAJANI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in PRASADAM -PHASE V- WING R S T AND U?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback