Home / Browse projects / Thane, Maharashtra / PRASADAM- PHASE IV- WING J K AND M

Registration lapsed No litigation declared Residential / Group Housing project

PRASADAM- PHASE IV- WING J K AND M

By SAI ASHRAY DEVELOPERS PVT LTD

RG-MH-26617 · RERA P51700011742 · Last updated on MahaRERA portal: 20 Jan 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 39 months past the filed date
  • 21 complaints at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Jul 2023Possession promised39 months past this date
5 of 11Construction stages donefurthest along: Staircases, 50%
21Complaints at MahaRERAon this registration
Jump to the 120 documents Report an error

PRASADAM- PHASE IV- WING J K AND M is a Residential / Group Housing project by SAI ASHRAY DEVELOPERS PVT LTD in Thane, Maharashtra, registered with MahaRERA as P51700011742 on 31 Aug 2017. Possession was promised by 17 Jul 2023 and is now 39 months past that date. The completion date has moved by 12 months from the original filing. 21 complaints are on record with the regulator.

At a glance

Project

  • NamePRASADAM- PHASE IV- WING J K AND M
  • TypeResidential / Group Housing
  • Location
    • Ambarnath
    • Ambarnath(M Cl)
    • Thane
    • 421501
  • Pincode421501
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700011742
  • ReraGenie IDRG-MH-26617

Builder

  • NameSAI ASHRAY DEVELOPERS PVT LTD
  • Entity typeCompany
  • DirectorJia Zhuowen Wei
  • Other registrations5 more →
  • No longer live6 lapsed, de-registered or revoked

Key dates

39 months past promisethis monthRegisteredAug 2017First promiseJul 2022Revised toJul 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on31 Aug 2017
  • Promised completion17 Jul 2023
  • Revised completionRevised to 17 Jul 2023 (originally 17 Jul 2022)
  • Buildings1 building record
  • Documents filed120 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PRASADAM WING JKMNA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 50%.

PRASADAM WING JKM: 52% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises26%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes75%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes80%
Landscaping & Tree PlantingYes0%
Street LightingYes50%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes100%

Parking filed30

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots30
Closed/Covered20
Open Space10

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,248 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
Darshna Anand DamleBadlapur (M Cl)Thane
Bharat J PatelAndheriMumbai Suburban

Approvals and building plan

Permissible FSI7928.05
Proposed, not sanctioned6,091 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSANA A Blg Junction Of Linking and Saraswati Road Santacruz West Mumbai 400054

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSYHAM J HEMRAJANI
PartnerRole in project
SAI ASHRAY DEVELOPERS PVT LTD-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700011896Jul 2022 → Jul 2023

Reason as filed by the promoterDue to the Prevailing Pandemic situation, more than three months labours & materials were not available on site.

Litigation declared2

CaseCourtStatus
371/2015Civil Court UlhasnagarPending
393/2018State Consumer Dispute Redressal CommissionPending

Complaints filed with MahaRERA21

Case no.ComplainantRespondentFiled
CC006000000000375SANJAY K. SONISai Ashray Developers Private Limited04/09/2017
CC006000000000402RAJESH SONIM/s. Sai Ashray Developers Private Limited05/09/2017
CC006000000058123RAJESH K. SONIM/s. Sai Ashray Developers17/02/2019
CC006000000056527ASHOK RAGHAVANSai Ashray Developers Pvt Ltd11/10/2018
CC006000000194674ASHOK RAGHAVANM/s SAI ASHRAY DEVELOPERS PVT LTD27/10/2020
CC006000000195051SANDEEP SHENOY KSAI ASHRAY DEVELOPERS PVT. LTD.30/11/2020
CC006000000044389MAHENDRA PRATAP SINGHSai Ashray Developers Private Limited02/05/2018
CC006000000078996Hindeshwar Narayan SinghSai Ashray Developers Pvt. Ltd.02/05/2019
CC006000000197767MR. SAMEER GOVING DALVIM/S SAI ASHRAY DEVELOPERS PVT. LTD.27/07/2021
CC006000000192801SEEMA K MOREJAGDISH BHAGWANDAS AHUJA05/03/2020
CC006000000195140Kusaraju chikkaleSai ashray developer pvt ltd/ahuja hive prasadam05/12/2020
CC006000000196737Dashrath Bacchav WalunjSai Ashray Developers Pvt Ltd.29/07/2021
CC006000000210105T V PADMAKUMAR MENONM/S SAI ASHRAY DEVELOPERS PRIVATE LIMITED23/02/2022
CC006000000251355SATISH GOKULDAS SHIVTARKARSAI ASHRAY DEVELOPERS PVT. LTD.04/06/2022
CC006000000395881Ashok NagpalSai Ashray Developers Pvt. Ltd.20/05/2023
CC006000000490390Kanchan NagpalSai Ashray Developers Pvt Ltd06/05/2024
CC006000000490392Ashok NagpalSai Ashray Developers06/05/2024
CC12400354Shirish Ulhas MundheSAI ASHRAY DEVELOPERS PVT LTD06/10/2024
CC12400560DEEPAK BHAJANLAL DUSEJASAI ASHRAY DEVELOPERS PVT LTD25/10/2024
CC12503936Hindeshwar Narayan SinghSAI ASHRAY DEVELOPERS PVT LTD09/11/2025
CC12604340Anand Ramchandra ReddySAI ASHRAY DEVELOPERS PVT LTD11/07/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Aug 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Aug 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Aug 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed120

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 120 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PRASADAM PHASE IV - Rera Eng Certi - JKM - Dec 24.pdf20 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PRASADAM PHASE IV - Rera Eng Certi - JKM - Sep 24.pdf18 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PRASADAM PHASE IV - Rera Eng Certi - JKM - Jun 24.pdf18 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: JKM.pdf9 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PRASADAM PHASE IV - Rera Eng Certi - JKM - Mar 24.pdf20 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PRASADAM PHASE IV - Rera Eng Certi - JKM - Dec 23.pdf6 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PRASADAM PHASE IV - Rera Eng Certi - JKM - Sep 23.pdf7 Oct 2023
Certificates of CA (Form 3)File: Form 3 CA Certificate for RERA Compliance - Prasadam JKM Sept 23.pdf7 Oct 2023
Certificates of CA (Form 5)File: RERA Certificate Form no 5 of FY 2022-23 - Prasadam Phase IV-JKM.pdf30 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: RERA Certificate Form no 5 of FY 2022-23 - Prasadam Phase IV-JKM.pdf30 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PRASADAM PHASE IV - Rera Eng Certi - JKM - Jun 23.pdf7 Jul 2023
Certificates of CA (Form 3)File: Form 3 CA Certificate for RERA Compliance - Prasadam JKM Jun 23.pdf7 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: JKM.pdf19 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: JKM.pdf17 Apr 2023
Certificates of CA (Form 3)File: Form 3 CA Certificate for RERA Compliance - Prasadam JKM Mar 23.pdf7 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PRASADAM PHASE IV - Rera Eng Certi - JKM - Mar 23.pdf6 Apr 2023
Proforma of Allotment letterFile: Revised RERA Proposed Allotment Letter Prasadam.pdf21 Mar 2023
Deviation Report with respect to Allotment letterFile: Revised Deviation Sheet Allotment Letter Prasadam.pdf21 Mar 2023
Proforma of Allotment letterFile: RERA Allotment Letter New Prasadam .pdf10 Feb 2023
Deviation Report with respect to Allotment letterFile: Deviation Sheet Allotment Letter Prasadam.pdf10 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PRASADAM PHASE IV - Rera Eng Certi - JKM - Dec 22.pdf7 Jan 2023
Certificates of CA (Form 3)File: Form 3 CA Certificate for RERA Compliance - Prasadam JKM Dec 22.pdf7 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Prasadam - JKM ( IV) - RERA Architect Certificate.pdf6 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PRASADAM PHASE IV - Rera Eng Certi - JKM - Sep 22.pdf7 Oct 2022
Certificates of CA (Form 3)File: Form 3 CA Certificate for RERA Compliance - Prasadam JKM Sept 22.pdf7 Oct 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Prasadam - JKM.pdf6 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form no 5 of FY 202122 Prasadam Phase IV JKM.pdf30 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form no 5 of FY 202122 Prasadam Phase IV JKM.pdf30 Sep 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Prasadam- JKM - Architect Certificate.pdf7 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PRASADAM PHASE IV - Rera Eng Certi - JKM - June 22.pdf7 Jul 2022
Certificates of CA (Form 3)File: Form 3 CA Certificate for RERA Compliance - Prasadam JKM June 22.pdf7 Jul 2022
Declaration about Commencement CertificateFile: Declaration about CC .pdf17 May 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: JKM_compressed.pdf17 May 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: JKM_compressed.pdf17 May 2022
CERSAI detailsFile: CERSAI_Search_Report_.pdf17 May 2022
Disclosure of sold/ booked inventoryFile: Sold and Unsold inventory.pdf17 May 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: CA .pdf9 May 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: CA 1.pdf9 May 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PRASADAM PHASE IV - Rera Eng Certi - JKM - Mar 22.pdf7 Apr 2022
Certificates of CA (Form 3)File: FORM 3 PRASADAM JKM.pdf7 Apr 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Prasadam - JKM -Phase IV- RERA Architect Certificate.pdf6 Apr 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Prasadam - JKM - Phase IV - Architect Certificate.pdf6 Apr 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PRASADAM PHASE IV - Rera Eng Certi - JKM - Dec-21.pdf7 Jan 2022
Certificates of CA (Form 3)File: FORM 3 PRASADAM JKM.pdf7 Jan 2022
Certificates of CA (Form 3)File: Form 3 CA Certificate for RERA Compliance - Prasadam JKM September 21.pdf7 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Prasadam - JKM - Phase IV- Architect Certificate.pdf6 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PRASADAM PHASE IV - Rera Eng Certi - JKM - Sep-21.pdf6 Oct 2021
Certificates of CA (Form 5)File: FORM 5 Prasadam Phase IV JKM.pdf21 Sep 2021
Building plan approvalFile: building plan.pdf19 Aug 2021
Layout approvalFile: building plan.pdf19 Aug 2021
Copy of Layout Approval (in case of layout)File: building plan.pdf19 Aug 2021
Building Plan Approval (IOD)File: building plan.pdf19 Aug 2021
Commencement Certificates / NA Order for plotted developmentFile: CC -.pdf19 Aug 2021
Certificates of CA (Form 3)File: Prasadam PH IV - JKM.pdf14 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PRASADAM PHASE IV - Rera Eng Certi - JKM - June-21.pdf13 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 9_PRASADAM _JKM_IV - RERA Architect Certificate-30.pdf10 Aug 2021
Details of encumbrancesFile: Prasadam -Details of Encumbrance-4.pdf1 Jul 2021
Certificates of CA (Form 3)File: Prasadam JKM FORM 3.pdf25 Jun 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Prasadam Phase IV JKM.pdf21 Jun 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 9_PRASADAM _JKM_IV - RERA Architect Certificate March21.pdf25 May 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5-PRASADAM PHASE IV (JKM).pdf2 Apr 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: prasadam phase iv Sept 20.pdf30 Mar 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Prasadam Phase IV Dec 20.pdf30 Mar 2021
Certificates of CA (Form 3)File: JKM SEP2020.pdf16 Mar 2021
Certificates of CA (Form 3)File: JKM DEC 2020.pdf16 Mar 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: PRASADAM JKM IV - Dec 2020.pdf25 Feb 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: prasadam phase 4 - March 20.pdf16 Feb 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: prasadam phase 4 - June20.pdf16 Feb 2021
Certificates of CA (Form 3)File: JKM - June20.pdf13 Feb 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 7_PRASADAM _JKM_IV - RERA Architect Certificate-30.pdf12 Feb 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 7_PRASADAM _JKM_IV - RERA Architect Certificate- - June,20.pdf12 Feb 2021
Certificates of CA (Form 3)File: Phase iv-JKM.pdf12 Feb 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Prasadam Phase IV.pdf7 Mar 2020
Certificates of CA (Form 3)File: CA CERTIFICATE RERA PRASADAM J,K,M.pdf24 Feb 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Prasadam Phase IV JKM.pdf17 Feb 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 10_PRASADAM PHASE IV.pdf10 Dec 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Sai Ashray Wing J,K,M.pdf30 Nov 2019
Certificates of CA (Form 3)File: JKM SEPT-19 RERA.pdf30 Nov 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 10_PRASADAM PHASE IV - 31 Aug.pdf5 Sep 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Sai Ashray Phase IV J,K,M.pdf30 Aug 2019

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 12 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PRASADAM- PHASE IV- WING J K AND M on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Ambarnath7,600+ in Thane

2 kmPRASADAM- PHASE IV- WINGCompleted 55Lapsed / revoked 26Other 34Dot size: filed unitsN

Filed coordinates, straight-line distance. 115 registered projects within 2 km.

Builder: SAI ASHRAY DEVELOPERS PVT LTD

SAI ASHRAY DEVELOPERS PVT LTD has 6 registrations on MahaRERA, including PRASADAM - CLUB HOUSE and PRASADAM -PHASE V- WING R S T AND U. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that PRASADAM- PHASE IV- WING J K AND M shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if PRASADAM- PHASE IV- WING J K AND M is delayed beyond 17 Jul 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PRASADAM- PHASE IV- WING J K AND M?

The registered promoter entity is SAI ASHRAY DEVELOPERS PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PRASADAM- PHASE IV- WING J K AND M?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against PRASADAM- PHASE IV- WING J K AND M?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for PRASADAM- PHASE IV- WING J K AND M?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PRASADAM- PHASE IV- WING J K AND M?

The professionals named in the filing: Architect: SYHAM J HEMRAJANI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PRASADAM- PHASE IV- WING J K AND M?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PRASADAM- PHASE IV- WING J K AND M. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PRASADAM- PHASE IV- WING J K AND M to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.