Red flags

  • Completion date moved by 30 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Sangli registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 30 months from the original
30 of 55Construction stages doneacross 5 buildings; furthest along: Installation of Lifts, 95%
17 of 29Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 64 documents Report an error

MANOMAY is a Residential / Group Housing project by YUVRAJ JAYSINGRAO PATIL in Sangli, Maharashtra, registered with MahaRERA as P53100049168 on 3 Feb 2023. Possession is promised by 31 Dec 2026. The completion date has moved by 30 months from the original filing. 12 of the 29 units on this registration are recorded sold or booked, and 30 of 55 construction stages are filed complete.

At a glance

Project

  • NameMANOMAY
  • TypeResidential / Group Housing
  • Location
    • KUPWAD ROAD
    • TRITHANKAR COLONY NEAR SHARDA HOUSING SOC.
    • Sangli Miraj Kupwad (M Corp.)
    • Miraj
    • Sangli
    • 416436
  • Pincode416436
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P53100049168
  • ReraGenie IDRG-MH-92740

Builder

  • NameYUVRAJ JAYSINGRAO PATIL
  • Entity typeIndividual
  • Other registrations1 more →
  • Completed1 of 2

Key dates

this monthRegisteredFeb 2023First promiseJun 2024Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on3 Feb 2023
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 1 Jun 2024)
  • Buildings5 building records
  • Documents filed64 files

Current status

41%12 of 29 units booked
68.7%Work done, per cost certificate

Figures as on 28 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
UNIT-01NA22101
UNIT-02NA22101
UNIT-03NA22101
UNIT-04NA22101
MANOMAY - PHASE IINA8720525

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 28 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

30 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Installation of Lifts, at 95%.

UNIT-0172%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
UNIT-0272%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
UNIT-0372%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
UNIT-0472%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
MANOMAY - PHASE II40%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 28 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,162 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on17 Sep 2025

Approvals and building plan

Sanctioning authoritySANGLI MIRAJ KUPWAD CORPORATION
Permissible FSI2973.98
Proposed, not sanctioned2,476 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMAHADEV APARTMENT SHOP NO 1 2 2017 E WARD RAJARAMPURI 6TH LANE KOLHAPUR
Estimated costRs 5.40 cr
Cost incurredRs 3.71 cr
Work done68.65%
BuildingWingEstimatedIncurred
UNIT-01NARs 1.08 crRs 74.13 lakh
UNIT-02NARs 1.08 crRs 74.13 lakh
UNIT-03NARs 1.08 crRs 74.13 lakh
UNIT-04NARs 1.08 crRs 74.13 lakh
MANOMAY - PHASE IINARs 1.08 crRs 74.13 lakh

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSACHIN G KANOJE
EngineerN K PATIL
EngineerSHITAL S KAVTHEKAR
Chartered AccountantCA CHANDRABHAGA K PATIL
Chartered AccountantSHRINIWAS N BHOSALE
PartnerRole in project
YUVRAJ JAYSINGRAO PATIL-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT53100020914Jun 2024 → Dec 2026

Reason as filed by the promoterREVISED BUILDING TAKEN FROM SANGLI MIRAJ AND KUPWAD MINICIPAL CORPORATION THAT WAHY WE WANT EXTENSION

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Jan 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Jan 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Jan 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Jan 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed64

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM-1 31-12-2025.pdf28 May 2026
Withdrawal Update Form 1File: FORM-1 31-03-2025.pdf28 May 2026
Withdrawal Update Form 2File: FORM-2 31-12-2025.pdf28 May 2026
Withdrawal Update Form 2File: FORM-2 31-03-2025 .pdf28 May 2026
Withdrawal Update Form 3File: FORM-3 31-12-2025.pdf28 May 2026
Withdrawal Update Form 3File: FORM-3 31-03-2025.pdf28 May 2026
Withdrawal Update Form 1File: FORM-1 30-06-2025 .pdf21 May 2026
Withdrawal Update Form 1File: FORM-1 30-09-2025 .pdf21 May 2026
Withdrawal Update Form 2File: FORM-2 30-06-2025 .pdf21 May 2026
Withdrawal Update Form 2File: FORM-2 30-09-2025 .pdf21 May 2026
Withdrawal Update Form 3File: FORM-3 30-06-2025 .pdf21 May 2026
Withdrawal Update Form 3File: FORM-3 30-09-2025 .pdf21 May 2026
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD.pdf27 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1.pdf23 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf23 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FROM 2.pdf23 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf10 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf10 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf10 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf10 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf10 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf10 Oct 2024
Declaration in FORM BFile: FROM B.pdf3 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf3 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf3 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf3 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf3 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2a.pdf3 Jun 2024
Disclosure of sold/ booked inventoryFile: book 1010.pdf3 Jun 2024
Disclosure of sold/ booked inventoryFile: book 10124.pdf3 Jun 2024
Disclosure of sold/ booked inventoryFile: book 10424.pdf3 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf3 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A CERTIFICATE.pdf3 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FROM 5.pdf3 Jun 2024
Building plan approvalFile: MODIFIED DRG.pdf10 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: MODIFIED DRG.pdf10 Jan 2024
Commencement Certificates / NA Order for plotted developmentFile: bandhakam pramanpatra.pdf10 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate.pdf6 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineers certificate.pdf6 Sep 2023
Disclosure of sold/ booked inventoryFile: disclosure of sold.pdf6 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: c a certificate.pdf6 Sep 2023
Layout approvalFile: NAKASHA.pdf10 Jan 2023
Building plan approvalFile: dwg.pdf10 Jan 2023
PAN CardFile: PAN CARD1.pdf10 Jan 2023
Copy of the legal title reportFile: legal title report.pdf10 Jan 2023
Details of encumbrances concerned to FinanceFile: enc - fin.pdf10 Jan 2023
Details of encumbrances concerned to FinanceFile: encumbrance certificate.pdf10 Jan 2023
Details of encumbrances concerned to LegalFile: enc - fin.pdf10 Jan 2023
Details of encumbrances concerned to LegalFile: encumbrance certificate.pdf10 Jan 2023
Copy of Layout Approval (in case of layout)File: NAKASHA.pdf10 Jan 2023
Building Plan Approval / NA Order for plotted developmentFile: dwg.pdf10 Jan 2023
Commencement Certificates / NA Order for plotted developmentFile: building permission certificate.pdf10 Jan 2023
Declaration about Commencement CertificateFile: DCC.pdf10 Jan 2023
Declaration in FORM BFile: form b.pdf10 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate.pdf10 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineers certificate.pdf10 Jan 2023
CERSAI detailsFile: cersai.pdf10 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_compressed (1).pdf10 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: disclosure of intrest in other real estate organisation.pdf10 Jan 2023
Proforma of Agreement for saleFile: AGRIMENT.pdf10 Jan 2023
Proforma of Allotment letterFile: model form of allotment letter.pdf10 Jan 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: declaration about separate bank account for real estate projects.pdf10 Jan 2023
Deviation Report with respect to Allotment letterFile: in order no 31 about the allotment letter is no any deviation.pdf10 Jan 2023
Deviation Report with respect to model copy of AgreementFile: agreement for sale is no any deviation.pdf10 Jan 2023

How this compares with Sangli

41%of this project is bookeddistrict median 16%
11%of Sangli projects moved their completion datethis one moved by 30 months
29%of Sangli registrations have lapsed or been cancelledthis one is on the register

Computed across the 790+ Sangli projects on ReraGenie, from their own filings.

Keep MANOMAY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near TRITHANKAR COLONY NEAR SHARDA HOUSING SOC.,790+ in Sangli

2 kmMANOMAYCompleted 21Lapsed / revoked 17Other 6Dot size: filed unitsN

Filed coordinates, straight-line distance. 44 registered projects within 2 km.

Builder: YUVRAJ JAYSINGRAO PATIL

YUVRAJ JAYSINGRAO PATIL has 2 registrations on MahaRERA, including MORYA APARTMENT and MANOMAY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Sangli district page.

Frequently asked questions

What are my rights if MANOMAY is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MANOMAY?

The registered promoter entity is YUVRAJ JAYSINGRAO PATIL, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MANOMAY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for MANOMAY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MANOMAY?

The professionals named in the filing: Architect: SACHIN G KANOJE; Engineer: N K PATIL; Engineer: SHITAL S KAVTHEKAR; Chartered Accountant: CA CHANDRABHAGA K PATIL; Chartered Accountant: SHRINIWAS N BHOSALE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MANOMAY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MANOMAY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MANOMAY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.