Home / Browse projects / Pune, Maharashtra / Playtor Paud D- Phase 1

De-registered No litigation declared Residential / Group Housing project

Playtor Paud D- Phase 1

By SANGAM REALTY

RG-MH-08748 · RERA P52100002705 · Last updated on MahaRERA portal: 7 Aug 2025

Source: official MahaRERA filing

Red flags

  • De-registered
  • Possession 40 months past the filed date
  • 3 complaints at MahaRERA
  • Completion date moved by 48 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2023Possession promised40 months past this date
4 of 22Construction stages doneacross 2 buildings; furthest along: Basement (if any), 70%
3Complaints at MahaRERAon this registration
Jump to the 179 documents Report an error

Playtor Paud D- Phase 1 is a Residential / Group Housing project by SANGAM REALTY in Pune, Maharashtra, registered with MahaRERA as P52100002705 on 2 Aug 2017. Possession was promised by 29 Jun 2023 and is now 40 months past that date. The completion date has moved by 48 months from the original filing. 3 complaints are on record with the regulator.

At a glance

Project

  • NamePlaytor Paud D- Phase 1
  • TypeResidential / Group Housing
  • Location
    • Paud-Mulshi Road
    • Next to Tehsil Office
    • Paud
    • Mulshi
    • Pune
    • 412108
  • Pincode412108
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100002705
  • ReraGenie IDRG-MH-08748

Builder

  • NameSANGAM REALTY
  • Entity typePartnership
  • PartnersSANTOSH MOTILAL BHANSALI, NANDKUMAR SOPAN GADHAVE
  • Other registrations4 more →
  • Completed1 of 5
  • No longer live4 lapsed, de-registered or revoked

Key dates

40 months past promisethis monthRegisteredAug 2017First promiseJun 2019Revised toJun 2023

Key facts

Registration and timeline

  • StatusDe-registered
  • Registered on2 Aug 2017
  • Promised completion29 Jun 2023
  • Revised completionRevised to 29 Jun 2023 (originally 30 Jun 2019)
  • Buildings2 building records
  • Documents filed179 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
D3NA80000
D4NA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 7 Aug 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 70%.

D329%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure13%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks5%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.1%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
D422%
ActivityProgress
Excavation100%
Basement (if any)70%
Podiums (if any)0%
Plinth70%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities18

As on 7 Aug 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes10%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes10%
Compound WallYes0%
Retaining WallYes90%
EarthworkYes100%

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,446 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI4269.38
Proposed, not sanctioned4,269 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchII- 5C , MITTAL COURT, 224 , NARIMAN POINT, MUMBAI- 400021

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
Chartered AccountantAkhil Lodha & Associates
Chartered AccountantAlok Shukla & Associates
PartnerRole in project
SANGAM REALTY-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100010409Jun 2019 → Dec 2022

Reason as filed by the promoterAttached list of Allottes have consented to extend Rera date of completion of the project form 30/12/2020 to 29/12/2022

EXT52100000856Jun 2019 → Jun 2020

Reason as filed by the promoterFor getting permission of plinth checking certificate from PMRDA, Pune.

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC005000000269423DATTARAM BALARAM SHINDESangam Realty11/09/2023
CC005000000269481VILAS RAJARAM SHINDEM/s. Sangam Realty21/09/2023
CC005000000269482CHANDRAKANT TUKARAM KARADKARM/s. Sangam Realty21/09/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 8 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Jul 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed179

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 179 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Cert no 16 July Sept 2023.pdf7 Aug 2025
Form 2File: Cert no 18 July Sept 2023.pdf7 Aug 2025
Form 3File: Cert no 18 July Sept 2023.pdf7 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold - Booked- Unsold Units - July Sept 2023.pdf7 Aug 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Cert no 21 Oct Dec 2024.pdf8 Mar 2025
Certificates of CA (Form 3)File: Cert No 23 Oct Dec 2024.pdf8 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Cert no 22 July Sept 2024.pdf8 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Cert no 23 Oct Dec 2024.pdf8 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Cert no 1 FY 2021 2022.pdf8 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Cert no 2 FY 2022 2023.pdf8 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Cert no 3 FY 2023 2024.pdf8 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Cert no 20 July Sept 2024.pdf28 Feb 2025
Certificates of CA (Form 3)File: Cert no 22 July Sept 2024.pdf28 Feb 2025
Other - LegalFile: Chandrakant Tukaram Karadkar - Complaint Withdrawal Application.pdf29 Nov 2024
Other - LegalFile: Dattaram Balaram Shinde - Complaint Withdrawal Application.pdf29 Nov 2024
Other - LegalFile: Vilas Rajaram Shinde - Complaint Withdrawal Application.pdf29 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Cert no 1 FY 2021 2022.pdf21 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Cert no 2 FY 2022 2023.pdf21 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Cert no 3 FY 2023 2024.pdf21 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Cert no 1 Oct Dec 2019.pdf8 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Cert no 2 Jan Mar 2020.pdf8 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Cert no 3 Apr June 2020.pdf8 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Cert no 4 July Sept 2020.pdf8 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Cert no 5 Oct Dec 2020.pdf8 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Cert no 6 Jan Mar 2021.pdf8 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Cert no 7 Apr Jun 2021.pdf8 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Cert no 8 July Sept 2021.pdf8 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Cert no 9 Oct Dec 2021.pdf8 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Cert no 10 Jan Mar 2022.pdf8 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Cert no 11 Apr Jun 2022.pdf8 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Cert no 12 July Sept 2022.pdf8 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Cert no 13 Oct Dec 2022.pdf8 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Cert no 14 Jan Mar 2023.pdf8 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Cert no 15 Apr Jun 2023.pdf8 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Cert no 16 July Sept 2023.pdf8 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Cert no 17 Oct Dec 2023.pdf8 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Cert no 18 Jan Mar 2024.pdf8 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Cert no19 Apr Jun 2024.pdf8 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Cert no 1 Apr Jun 2019.pdf8 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Cert no 2 July Sept 2019.pdf8 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Cert no 3 Oct Dec 2019.pdf8 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Cert no 4 Jan Mar 2020.pdf8 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Cert no 5 Apr Jun 2020.pdf8 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Cert no 6 July Sept 2020.pdf8 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Cert no 7 Oct Dec 2020.pdf8 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Cert no 8 Jan Mar 2021.pdf8 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Cert no 9 Apr Jun 2021.pdf8 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Cert no 10 July Sept 2021.pdf8 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Cert no 11 Oct Dec 2021.pdf8 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Cert no 12 Jan Mar 2022.pdf8 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Cert no 13 Apr Jun 2022.pdf8 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Cert no 14 July Sept 2022.pdf8 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Cert no 15 Oct Dec 2022.pdf8 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Cert no 16 Jan Mar 2023.pdf8 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Cert no 17 Apr Jun 2023.pdf8 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Cert no 18 July Sept 2023.pdf8 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Cert no 19 Oct Dec 2023.pdf8 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Cert no 20 Jan Mar 2024.pdf8 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Cert no 21 Apr Jun 2024.pdf8 Oct 2024
Certificates of CA (Form 3)File: Cert no 1 Apr Jun 2019.pdf8 Oct 2024
Certificates of CA (Form 3)File: Cert no 2 July Sept 2019.pdf8 Oct 2024
Certificates of CA (Form 3)File: Cert no 3 Oct Dec 2019.pdf8 Oct 2024
Certificates of CA (Form 3)File: Cert no 4 Jan Mar 2020.pdf8 Oct 2024
Certificates of CA (Form 3)File: Cert no 5 Apr Jun 2020.pdf8 Oct 2024
Certificates of CA (Form 3)File: Cert no 6 July Sept 2020.pdf8 Oct 2024
Certificates of CA (Form 3)File: Cert no 7 Oct Dec 2020.pdf8 Oct 2024
Certificates of CA (Form 3)File: Cert no 8 Jan Mar 2021.pdf8 Oct 2024
Certificates of CA (Form 3)File: Cert no 9 Apr Jun 2021.pdf8 Oct 2024
Certificates of CA (Form 3)File: Cert no 10 July Sept 2021.pdf8 Oct 2024
Certificates of CA (Form 3)File: Cert no 11 Oct Dec 2021.pdf8 Oct 2024
Certificates of CA (Form 3)File: Cert no 12 Jan Mar 2022.pdf8 Oct 2024
Certificates of CA (Form 3)File: Cert no 13 Apr Jun 2022.pdf8 Oct 2024
Certificates of CA (Form 3)File: Cert no 14 July Sept 2022.pdf8 Oct 2024
Certificates of CA (Form 3)File: Cert no 14 July Sept 2022.pdf8 Oct 2024
Certificates of CA (Form 3)File: Cert no 15 Oct Dec 2022.pdf8 Oct 2024
Certificates of CA (Form 3)File: Cert no 16 Jan Mar 2023.pdf8 Oct 2024
Certificates of CA (Form 3)File: Cert no 17 Apr Jun 2023.pdf8 Oct 2024
Certificates of CA (Form 3)File: Cert no 18 July Sept 2023.pdf8 Oct 2024
Certificates of CA (Form 3)File: Cert no 19 Oct Dec 2023.pdf8 Oct 2024
Certificates of CA (Form 3)File: Cert no 20 Jan Mar 2024.pdf8 Oct 2024

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 48 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Playtor Paud D- Phase 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Next to Tehsil Office13,700+ in Pune

2 kmPlaytor Paud D- Phase 1Completed 2Lapsed / revoked 5Dot size: filed unitsN

Filed coordinates, straight-line distance. 7 registered projects within 2 km.

Builder: SANGAM REALTY

SANGAM REALTY has 5 registrations on MahaRERA, including Playtor Paud C- Phase 1 and Playtor Paud C- Phase 2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Playtor Paud D- Phase 1 shows as de-registered on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Playtor Paud D- Phase 1 is delayed beyond 29 Jun 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Playtor Paud D- Phase 1?

The registered promoter entity is SANGAM REALTY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Playtor Paud D- Phase 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Playtor Paud D- Phase 1?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Playtor Paud D- Phase 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Playtor Paud D- Phase 1?

The professionals named in the filing: Chartered Accountant: Akhil Lodha & Associates; Chartered Accountant: Alok Shukla & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Playtor Paud D- Phase 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Playtor Paud D- Phase 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Playtor Paud D- Phase 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.